↑ Parent Menu⌂ Main Menu
← Railway Ground Hazard Risk Management
Benesch benesch
Railway Ground Hazard Risk Management · Part VII · Stabilization Methods
Sections · click a car to open it

Chapter 15 — Construction Monitoring and Field Testing

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel

Geotechnical Services Manual for Railroad Clients

A Consultant's Reference for Delivering Geotechnical Engineering Services Across North American Railroad Capital Programs

Apps for this Chapter3

Apps on dirtbert.com that support this chapter. Each one runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (I.3). Tools marked TOOLS open in the Geotechnical Analysis Suite (Benesch sign-in); the orange card below lists each one by section.

NANCY pages ask you to accept the Use and Disclaimers once in each browser. MINA is a monitoring aid and is not for operational dispatch decisions.

Analytical Tools for this Chapter8

Calculators and workbook tools from the Benesch Geotechnical Analysis Suite that support this chapter: 3 interactive calculators and 5 workbook guides. Each one is also placed inside the section it supports, in an orange tools strip.

FFField Observation DataUsed in 15.6 Settlement MonitoringCalculator ▸Guide
FFDynamic Cone Field LogUsed in 15.2 Compaction TestingCalculator ▸Guide
PVFAA P-501 Random SamplingUsed in 15.2 Compaction TestingCalculator ▸Guide
FFDaily Log — Compaction Testing (Nuclear Gauge)Used in 15.2 Compaction Testingguide onlyGuide
DFCSL Analysis (Crosshole Sonic Logging)Used in 15.4 Pile Installation Monitoringguide onlyGuide
DFPile PDA Field Data ComputationsUsed in 15.4 Pile Installation Monitoringguide onlyGuide
DFPile Load Test Calculations (Compression)Used in 15.5 Static Axial Load Testing (ASTM D1143)guide onlyGuide
FFNuclear Density — SoilUsed in 15.2 Compaction Testingguide onlyGuide

Tools open on dirtbert.com and need the Benesch sign-in. Drafts pending Benesch final review, not for use in design.

Reference Graphics
15.0 Executive Summary

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet specification, and that construction methods produce the intended product. In railroad capital programs, the consequences of failed construction QA are measured not only in dollars but in operational downtime, derailment risk, and long-term maintenance cost. A well-designed embankment that is poorly compacted will fail progressively. A pile that is driven through the wrong soil horizon will under-perform. A staged embankment advanced too quickly will trigger slope failure.

This chapter covers the full scope of construction-phase geotechnical services delivered to all nine client railroads: compaction testing (nuclear gauge and sand cone methods), proof rolling, pile installation monitoring (WEAP, PDA, CAPWAP), static axial load testing, settlement monitoring (settlement plates and survey), piezometric monitoring during staged construction, inclinometer monitoring for slope and wall movements, trigger levels and action plans, and construction QA/QC documentation. All test methods are referenced to current ASTM standards. Client-specific inspection and reporting requirements are tabulated for all nine railroads.

Empirical Equations — Use and Limitations

The correlations below are used or referenced in this chapter. Each is a statistical fit to a particular data set, so a value from one is an estimate: it applies only within the materials and ranges stated, carries the scatter of the original data, and must be confirmed by site-specific testing or calibration before it is relied on for design.

When an equation is used, note it with the result: give the equation ID and source, state that the soil or rock is within its range of applicability, mark the value as correlated (not tested), and record the limitation that governs. The Empirical Equations & Correlations reference has every entry with its full references.

Referenced in this chapter

IS-01SPT energy & procedure correctionN₆₀
N60 = Nm · CE · CB · CS · CR
CE = ERm / 60

Variables. Nm = field blow count; ERm = measured hammer energy ratio (%); CB = borehole diameter (1.0 for 65–115 mm, 1.05 for 150 mm, 1.15 for 200 mm); CS = sampler (1.0 standard, 1.1–1.3 liner-less); CR = rod length (0.75 <3 m; 0.8 3–4 m; 0.85 4–6 m; 0.95 6–10 m; 1.0 >10 m)

Use. All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations.

Limitations. CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).

Source. Skempton 1986; Youd et al. 2001 · In this chapter: 15.4 · Full entry and references

Also applicable to this chapter

IX-05Secondary compression ratioC_α
Cα / Cc ≈ 0.04 ± 0.01   (inorganic clays and silts)
≈ 0.05 ± 0.01 (organic clays and silts); ≈ 0.075 ± 0.01 (peats)

Variables. Cα = Δe / Δlog t

Use. Secondary consolidation of soft soils; the ratio holds at a given effective stress level.

Limitations. Use Cc corresponding to the final stress (Cc varies with stress in structured clays).

Source. Mesri & Godlewski 1977; Mesri & Castro 1987 · Full entry and references

IS-12Corrected cone resistanceqₜ
qt = qc + u2 (1 − an)

Variables. u2 = pore pressure behind cone tip; an = net area ratio (typically 0.70–0.85, from calibration)

Use. All piezocone (CPTu) soundings; essential in soft clays and silts.

Limitations. Correction negligible in clean sands; critical in soft fine-grained soils. Requires u2 filter position.

Source. Lunne et al. 1997 · Full entry and references

IS-17Preconsolidation stress / OCR from CPTσ'ₚ, OCR
σ'p ≈ k · (qt − σv0)
OCR = σ'p / σ'v0
k ≈ 0.33 (range 0.2–0.5)

Variables. k = empirical factor

Use. Intact, inorganic clays.

Limitations. k is higher in aged/heavily OC clays and lower in fissured clays; calibrate with oedometer tests.

Source. Kulhawy & Mayne 1990; Mayne 1995 · Full entry and references

15.1 Background and Railroad Context

Railroad construction monitoring differs from typical civil construction monitoring in three critical ways:

  1. Active railroad operations. Most railroad capital projects are constructed while adjacent or parallel tracks remain in service. Contractor and geotechnical inspector access requires roadway worker protection (RWP) and must be coordinated with the dispatcher. Monitoring instruments must be read without delaying trains, and inspectors must be prepared to evacuate work zones on short notice.
  2. Tight schedule windows. Track outages (track windows) for construction are typically 4–8 hours per day, with total project schedules measured in weeks, not months. Monitoring data must be processed in near-real-time so that decisions on embankment lifts, pile acceptance, or shoring movements can be made before the next construction window.
  3. Client construction inspectors are co-present. All Class I railroads assign their own construction inspectors to capital projects. The geotechnical inspector works alongside — not instead of — the railroad inspector. Role delineation must be established at the pre-construction meeting. The geotechnical inspector owns subsurface QA; the railroad inspector owns track geometry, clearances, and operational compliance.
Project management · ASCE (2012)

QA versus QC: Who Is Responsible for What

ASCE Manual 73 (ASCE 2012) separates two functions that are often blurred together as “QA/QC.” Quality assurance is the planned, systematic work of the owner or its agent to gain confidence that the design complies with codes and criteria and that construction complies with the contract documents; it verifies that the other parties’ quality control is working. Quality control belongs to the design professional (control of the contract documents) and to the constructor (control of the work), and includes observations, calculations, inspections, tests and documentation.

The owner sets the value placed on quality, funds it, and decides whether to use a standing generic QA plan, a project-specific plan, or a tailored generic plan. The owner may specify the designer’s and constructor’s QC plans prescriptively or in performance terms. During construction the owner must choose who inspects: the owner, the design professional, an independent agency, a code official, or the constructor. The Manual stresses that none is always best and the choice should balance cost, safety, schedule and quality. A resident project representative (RPR) may oversee the constructor’s QC and reviews the constructor’s QC plan before production starts.

A typical constructor project-specific QC plan addresses a skilled workforce, a QC organization, a submittal schedule, inspections, mock-ups and sample construction, a testing plan including special inspections, documentation, and corrective action when acceptance criteria are not met. It should also cover subcontractor qualification, control of measuring and test equipment, and segregation of nonconforming material. The Manual summarizes responsibilities in a chart: the owner establishes the QA program; the designer develops design-phase QC; the constructor develops and documents construction QC; and all communicate regularly.

For railroad work: On a railroad-funded embankment or subgrade project the railroad (or its engineering consultant acting as RPR) performs QA, and the contractor performs QC testing such as compaction and gradation. When the geotechnical consultant’s field staff perform acceptance testing, the scope should say whether that testing is QA (owner verification) or is replacing contractor QC, because the two carry different responsibility for rework and different testing frequencies. State this explicitly in the construction monitoring scope and the GSP.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 169–170, 191–199. Summarized and paraphrased. Full reference under Supplemental Sources.

15.2 Compaction Testing
15.2.1 Standard and Modified Proctor (Maximum Dry Density Reference)

Compaction acceptance is based on relative compaction (RC) referenced to the laboratory maximum dry density (MDD):

RC = (γ_d,field / γ_d,max) × 100%

where:

  • γ_d,field = field dry unit weight (pcf)
  • γ_d,max = maximum dry unit weight from Proctor test (pcf); Standard Proctor per ASTM D698; Modified Proctor per ASTM D1557

All nine client railroads specify Modified Proctor (ASTM D1557) as the reference for embankment, blanket layer, and subballast compaction. Standard Proctor is used only for structure backfill behind retaining walls at G&W (per G&W Engineering Bulletin).

Client compaction requirements (from Chapter 18, Table 10-7, restated here for construction context):

RailroadMin. RC (Subgrade/Blanket)Min. RC (Embankment)Test MethodGoverning Std.
CSXT95%90%ASTM D6938 (nuclear)CSXT Eng. Std. Sec. 7
NSR95%90%ASTM D6938 or D1556NSR Eng. Std. Sec. 7
G&W95%90%ASTM D6938 or D1556G&W Eng. Bulletin
UPRR95%92%ASTM D6938UPRR Eng. Instr. Manual
BNSF95%92%ASTM D6938BNSF Eng. Instructions
CPKC95%90%ASTM D6938CPKC Track Standards
Amtrak95%92%ASTM D6938 or D1556Amtrak Eng. Std.
CN95%90%ASTM D6938CN Eng. Standards

Reference graphics

Proctor Compaction Test
Proctor Compaction Test
15.2.2 Nuclear Moisture-Density Gauge (ASTM D6938)

The nuclear gauge measures in-place density and moisture content using a radioactive source (cesium-137 for backscatter; americium-241/beryllium for direct transmission). The gauge reports:

γ_d,field = (WD - count ratio correction) × calibration constant (pcf)

In practice, results are read directly from the calibrated gauge display. Field procedure:

  1. Prepare a level, smooth test surface (scarify and rerake if necessary); remove all loose material
  2. Seat the gauge; take 4 counts at 1-min intervals (backscatter or direct transmission at specified depth)
  3. Record WD and MC%; compute γ_d,field = WD / (1 + MC/100)
  4. Calculate RC = γ_d,field / γ_d,max × 100%
  5. Compare to specification; if RC < minimum, rework and retest

Gauge calibration: ASTM D6938 requires calibration on a reference block before each use. Nuclear gauges are licensed NRC devices; technician must hold current radiation safety training certification. All nine client railroads require gauge operators to carry their radiation license during field work.

Gauge correction for materials containing significant gravel or rock: ASTM D6938 permits an oversize correction when more than 30% of material is retained on the ¾-in. sieve:

γ_d,corrected = γ_d,gauge + [(G_c − G_s) × P_c × γ_w] (pcf)

where G_c = specific gravity of coarse fraction; G_s = average specific gravity assumed by gauge; P_c = fraction coarser than ¾ in.

15.2.3 Sand Cone Method (ASTM D1556)

The sand cone method is required by NSR, Amtrak, and G&W for acceptance testing in compacted structural fill adjacent to structures and retaining walls, and as the verification method when nuclear gauge results are disputed.

Field bulk density:

ρ_bulk = (M_soil) / V_hole (pcf)

Volume of hole:

V_hole = (M_cone−sand,initial − M_cone−sand,final − M_sand,funnel) / ρ_sand,calibrated (ft³)

Dry density:

γ_d = ρ_bulk / (1 + w/100) (pcf)

where w = gravimetric water content (%) from oven-dried sample (ASTM D2216).

Sand cone testing is slower than nuclear gauge but is considered the more accurate reference method. Minimum test frequency: 1 test per 500 cy compacted fill per NSR; 1 per 1,000 cy per CSXT.

Reference graphics · click to zoom

Field Density Test
Field Density Test
15.2.4 Compaction Test Frequency
Table 15-1. Minimum Compaction Testing Frequency by Application
ApplicationFrequencyTrigger for Retest
Embankment lift (main body)1 test per 500 ft of track per liftRC < minimum
Blanket layer / subgrade prep1 test per 250 ft of track per liftRC < minimum
Structural fill (bridge abutment)1 test per 2 ft lift per 50 ft lengthRC < minimum
MSE wall reinforced fill1 test per 2 ft lift per 100 ftRC < minimum
Retaining wall backfill1 test per 2 ft lift per 50 ftRC < minimum
Trench backfill (pipe, drain)1 test per 50 linear ft per liftRC < minimum

Source: Compiled from CSXT Eng. Std. Sec. 7, BNSF Eng. Instructions, NSR Eng. Std. Sec. 7, AREMA MRE Ch. 1.

Compaction is about properties, not density

The purpose of compaction is to gain strength and stiffness, reduce compressibility, plastic strain under repeated load, permeability and swell. Density is just the convenient thing to specify. Keep these points in mind when setting and checking specifications:

  • The same percent compaction (ASTM D698) does not give the same stiffness in different soils. Stiffness ranks clay < silt < sand, and clay needs far more effort to reach the same percentage.
  • A roller is effective to about 12–24 in.. Below that, remove the material and replace it in loose lifts of 6–12 in..
  • Drying is feasible for coarse and silty soils but difficult for clay. Saturated coarse or silty soils imply dewatering. Soft saturated clay is removed and replaced.
  • Organic soil is not acceptable as track subgrade and must be removed.
  • Place subballast in loose lifts of 4–6 in., with each distinct layer at least 6 in. thick when compacted.

After Selig & Waters (1994), chs. 9 and 11. Full reference under Supplemental Sources.

Supplemental reference · LEVI Library

Roller-integrated compaction control (CCC / IC) as an acceptance method

Spot tests sample a tiny fraction of a lift. Roller-integrated measurement covers 100% of the area and can find soft zones deeper than a nuclear gauge. SHRP2 distinguishes CCC (the roller records a drum-response stiffness value with GPS position) from intelligent compaction (the roller also adjusts amplitude, frequency or speed automatically). It is best suited to granular fills, sand, crushed gravel and rock fill — i.e., subballast and embankment granular layers. The Austrian contractual provisions summarized by Adam (2007) show how to make it an acceptance test:

  • Calibrate on a test field within the actual section (about 330 ft long, full width), with measuring passes forward and static passes in reverse. Then take nine static plate tests (Ev1, 12-in. plate) at low, medium and high roller values and fit a linear regression. The correlation coefficient must be at least 0.7, or more tests are required. The calibration is valid only for that roller, soil, amplitude, frequency and speed.
  • Limits from the regression: MIN at 95% of the required Ev1; mean (MW) at 105% (100% in jump mode); 0.8 MIN; MAX = 150% of MIN.
  • Acceptance per measuring pass: (1) mean ≥ MW; (2) values below MIN on no more than 10% of the track, and never below 0.8 MIN; (3) uniformity — standard deviation ≤ 20% of the mean (or, if some values fell below MIN, no value above MAX). Continue passes while the mean still rises by more than 5% per pass.
  • Operating controls: constant speed 1.2–3.7 mph (± 0.12 mph) and constant frequency (± 2 Hz) during measuring passes. Avoid drum “(double) jump” by lowering amplitude or raising speed, and record it when it occurs. The surface must be even, and the lift reasonably homogeneous. The measuring depth (about 2.6–5 ft for a 13-ton roller) exceeds the compaction depth, so a soft layer below the lift will show up.

A falling roller value on repeated passes indicates loosening, particle crushing or pore pressure build-up — a reason to stop rolling, not to add passes.

Source: Adam, D. (2007). “Roller-integrated Continuous Compaction Control (CCC): Technical Contractual Provisions & Recommendations.” In Gomes Correia, A., Momoya, Y. and Tatsuoka, F. (eds.), Design and Construction of Pavements and Rail Tracks. Taylor & Francis/Balkema · SHRP2 R02 / GeoTechTools (2012). Intelligent Compaction — technology fact sheet

Compaction targets for the formation layer

UIC practice compacts the formation layer (the improved top-of-subgrade layer over S1 or S2 subsoil) to 100% of Standard Proctor, compared with 95% routinely specified for embankment subsoil. The formation layer also has to be homogeneous, without local concentrations of fine material, and placed on subsoil with a low water content. Otherwise subsoil fines migrate into it and the 3–5% crossfall is lost. Field QA should therefore watch uniformity and subsoil moisture as well as density.

After Profillidis (2014), §9.7.1. Full reference under Supplemental Sources.

Hold points before track is laid

Profillidis sets two checks before track laying begins: the subgrade has been properly compacted, and the 3–5% crossfall is correctly formed. Ballast is then delivered by special wagons, placed, levelled, graded and consolidated with a vibrating plate or roller. Uniform tie spacing matters as much as the nominal spacing. A high-speed laying machine averages about 0.81 mi per 6-hour shift, with peaks of 1,640 ft/h and 0.93–1.2 mi per shift. Once laid, the rails are set with a rail-positioning machine (Figure 15-11).

For the geotechnical inspector, those two checks are natural hold points. Document the subgrade density results and a crossfall survey before the contractor places ballast, because neither can be corrected afterward without removing the track.

Figures · click to zoom

Figure 15-11. Rail-positioning machine placing rail on newly laid ties (photo). Profillidis Fig. 16.1.
Figure 15-11. Rail-positioning machine placing rail on newly laid ties (photo). Profillidis Fig. 16.1.

After Profillidis (2014), §16.1.1, Fig. 16.1. Full reference under Supplemental Sources.

Trench and backfill practice on track repairs

Backfill and compact every 2-ft lift; skipped lifts leave voids that resettle under traffic. Match the compactor to the soil: a smooth-drum vibratory roller for granular fill, and never a sheepsfoot on saturated silt or clay, which can liquefy. Excavate in lifts and shore or slope trenches; trench collapses kill roughly 50 people a year in Canada. Wear rain gear and keep clear of live track when digging beside the rail.

Figures · click to zoom

Figure 15-14. Backfilling a trench beside the track in lifts.
Figure 15-14. Backfilling a trench beside the track in lifts.
Figure 15-15. Placing a geotextile liner in a cross trench.
Figure 15-15. Placing a geotextile liner in a cross trench.
Figure 15-16. Smooth-drum vibratory roller on a prepared fill.
Figure 15-16. Smooth-drum vibratory roller on a prepared fill.
Figure 15-17. Recording trench depth for the record.
Figure 15-17. Recording trench depth for the record.

After Geotechnology for Railroaders Program, Module 6.2, Module 6.1; Module 6.2 §02, §05; Module 6.1 §02. Full reference under Supplemental Sources.

Case study: 15.18.1 Field moisture ratios behind 5,649 passing density tests (Look 2023), in §15.18 Case Studies.

15.3 Proof Rolling

Proof rolling is a rapid field technique for identifying soft, pumping, or inadequately compacted subgrade zones prior to placing overlying layers. It is required by CSXT, NSR, UPRR, and BNSF for all mainline subgrade preparation.

Method: A loaded dump truck (minimum 25-ton axle load, or loaded hi-rail tanker as approved) traverses the prepared subgrade at 2–3 mph. The geotechnical inspector observes for:

  • Visible rutting > ½ in. under tire passes
  • Visible pumping (water or fines appearing at surface)
  • Lateral displacement of subgrade adjacent to tire path
  • Resilient deflection > ¾ in. (estimated by visual observation)

Reporting: GPS-tagged station of each deficiency location. Soft areas are marked, overexcavated to competent material (confirmed by nuclear gauge or hand penetrometer), and replaced with approved compacted fill.

Limitation: Proof rolling detects near-surface softness (top 18–24 in.) only. It does not evaluate deeper consolidation or deep subgrade conditions. Supplement with nuclear gauge density testing.

Reference graphics

Intelligent compaction roller (Cat CS563)
Intelligent compaction roller (Cat CS563)
Intelligent compaction roller (BOMAG)
Intelligent compaction roller (BOMAG)
Continuous impact response (CIR) compaction map
Continuous impact response (CIR) compaction map

Reference graphics · click to zoom

Why Proofrolling Matters
Why Proofrolling Matters

Subgrade, geotextile, sub-ballast and ballast checks during track construction

Inspect the subgrade at every stage of preparation, and again just before geotextile or sub-ballast is placed. Once the subgrade is covered, problems are expensive to find and fix.

Table 15-S1. Construction checks for subgrade, geotextile, sub-ballast and ballast
ItemRequirementInspector check
SubgradeInspected at each stage of preparation and before geotextile or sub-ballast is placedProof roll (§15.3); record stations of soft areas and repairs
DrainageDitches, culverts, subdrains and nearby earthwork complete before final subgrade preparationInspect subdrains before covering; check ditch flow lines and sections before track work starts
Geotextile exposureNo more than 7 days from removal of the shipping cover to final placementRecord delivery and uncovering dates in the daily field report
Geotextile coverNo equipment on geotextile until it has at least 6 in. of sub-ballast or ballast coverStop equipment tracking onto exposed fabric
Geotextile overlapAt least 3 ft, longitudinal and transverseMeasure at each seam
Geotextile contaminationSurface drainage directed away from placed fabricCheck for silted or blinded fabric before covering
Sub-ballastPlaced to plan lines and grades; compacted to at least 95% of ASTM D1557 (modified Proctor) maximum dry densityTest at the Table 15-1 frequency; check grade
Ballast placed by truckNo rutting that blocks drainage of sub-ballast or subgradeLevel and grade any ruts to drain before more ballast is placed

Ballast delivery. For large quantities (several hundred tons or more), unloading from ballast hopper cars is usually the most efficient method. Where the owner has a locomotive and crew, using them to spot ballast cars for the contractor can lower the unit cost. Settle that arrangement in the contract documents and at the pre-construction meeting. Where trucks place ballast, watch for rutting: ruts in sub-ballast or subgrade hold water under the track.

After UFC 4-860-01FA (2004), ch. 9, §4 and §5a, 5c. Full reference under Supplemental Sources.

15.4 Pile Installation Monitoring

Reference graphics

Pile Foundation Execution Inspection
Pile Foundation Execution Inspection
Pile Integrity Test (PIT)
Pile Integrity Test (PIT)
15.4.1 WEAP Analysis (Wave Equation Analysis of Piles)

WEAP is a predictive analysis performed before driving to establish the driving criterion (blow count per foot at target penetration depth or refusal) that corresponds to the required pile capacity. It models the pile, hammer, and soil system using wave propagation theory.

WEAP output:

  • Bearing graph: ultimate capacity (tons) vs. blow count (blows/ft)
  • Stress wave propagation: compressive and tensile stress peaks (psi)
  • Transfer efficiency: (E_transferred / E_rated) × 100%

Hammer energy — English units:

E_rated = W_ram × h (ft·lb)

where:

  • W_ram = ram weight (lb)
  • h = stroke height (ft) for drop hammers; rated for diesel/hydraulic

Transferred energy:

E_transferred = F_max² × L_pile / (2 × E_pile × A_pile) (ft·lb, from wave equation solution)

Required input parameters for WEAP:

  • Pile: type, cross-section (area A in.², modulus E = 29,000 ksi for steel, 57√f'_c for concrete), length (ft), elastic modulus
  • Hammer: type, rated energy, efficiency, cushion and capblock properties
  • Soil: ultimate capacity distribution (side friction vs. tip) from static analysis; quake and damping factors (Smith damping)

Smith damping constants (typical):

Soil TypeSide Quake (in.)Tip Quake (in.)Side Damping (s/ft)Tip Damping (s/ft)
Sand0.100.100.050.15
Clay0.100.100.200.15
Silt0.100.100.150.15

WEAP is required by UPRR and BNSF Engineering Instructions for all bridge foundation piles; by CSXT and NSR for piles > 60 ft length or in soft clay.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
15.4.2 Pile Driving Analyzer (PDA) — ASTM D4945

The PDA measures force and velocity at the pile head during driving using strain gauges and accelerometers. It provides a real-time assessment of:

  • Transferred hammer energy (E_transferred, ft·lb)
  • Peak compressive stress at pile top (CSX, ksi)
  • Peak tensile stress (TSX, ksi)
  • Integrity (BTA flag for damage)
  • Estimated capacity via Case Method

Case Method capacity:

R_total = ½ × (1 + J_c) × [F(t₁) + Z × V(t₁)] + ½ × (1 − J_c) × [F(t₁ + 2L/c) + Z × V(t₁ + 2L/c)] (lb)

where:

  • F(t) = measured force at time t (lb)
  • V(t) = measured velocity at time t (ft/s)
  • Z = pile impedance = E × A / c (lb·s/ft); c = wave speed in pile (ft/s); c = 16,800 ft/s for steel
  • J_c = Case damping factor (0.10–0.20 for sand; 0.40–0.70 for clay)
  • t₁ = time of peak force
  • L = pile length below gauge (ft)

Transfer ratio: ETR = (E_transferred / E_rated) × 100%. Per UPRR and BNSF requirements: ETR ≥ 60% for hydraulic hammers; ETR ≥ 40% for diesel.

Minimum PDA testing frequency:

  • UPRR: 10% of production piles (minimum 5 per bridge)
  • BNSF: 10% of production piles
  • CSXT, NSR: 5% of production piles minimum; 100% of first 5 test piles
  • Amtrak: 100% of all piles on NEC projects
15.4.3 CAPWAP Analysis

CAPWAP (CAse Pile Wave Analysis Program) is a post-processing signal matching analysis of PDA records that provides:

  • Ultimate total capacity (tons)
  • Skin friction distribution by depth (tons/ft)
  • End bearing capacity (tons)
  • Unit skin friction and unit end bearing values

CAPWAP replaces WEAP as the definitive capacity prediction when PDA data is available. All nine client railroads accept CAPWAP results as equivalent to 1 static load test when performed on ≥ 2% of production piles with approved restrike protocol (restrike after minimum setup time: 24 hours in sand; 7 days in clay).

Supplemental reference · LEVI Library

Field practice checks during driving

  • Vibration near track and structures (USACE EI 02G001): with impact hammers, consider a smaller or double-acting hammer. With vibratory hammers, use a high-frequency, low-amplitude unit. Vibratory hammers typically cause more ground vibration than impact hammers. If neither works, use a non-driven foundation. Monitor during test piles and production driving where susceptible structures are nearby.
  • Obstructions (old fill, riprap, timber in railroad embankments): drive a heavy spud and withdraw it, or probe with a vibratory hammer that can extract and reinsert the pile. Hard driving through obstructions invites pile damage.
  • Sequence and heave: drive groups from the center outward. Restrike piles that heave when neighbors are driven to confirm resistance and embedment.
  • Driving stresses: AASHTO/FHWA limit steel piles to 0.9 fy during driving (FHWA NHI-05-042). Classroom notes (Swan) use more conservative limits of 0.8 fy for steel and 0.6 f′c for concrete. Damage risk is highest at refusal on stiff soil or rock.
  • Dynamic formulas (ENR and variants) ignore setup in clay and rate effects in sand. Where they are used at all, FS of 4–6 on formula capacity is customary, which is why Table 11-S2 assigns the Gates formula FS = 3.5 and wave equation or dynamic testing much less.
  • Load-test count by project size (Engel, 1988): cumulative driven length 0–1.1 mi, none; 1.1–1.9 mi, 1; 1.9–3.7 mi, 2; 3.7–5.6 mi, 3; 5.6–7.5 mi, 4. Quick maintained-load tests without rate correction can overestimate capacity and underestimate settlement relative to slow tests.

Source: U.S. Army Corps of Engineers (1997). Pile Driving Equipment. Engineering Instructions EI 02G001 · Swan, C. C. Field Estimates of Pile Capacities, 53:139 Foundation Engineering supplemental notes. The University of Iowa · Hannigan, P. J. et al. (2006). Design and Construction of Driven Pile Foundations. FHWA NHI-05-042

Case study: 15.18.2 Sinkhole beside a piling rig on a sound working platform (Look 2023), in §15.18 Case Studies.

Project management · Goldbloom (1989)

Specifying, Measuring and Paying for Driven Piles

Goldbloom gives a checklist of what a bearing-pile section must state. Pile monitoring depends on these items, so they should be confirmed before driving starts:

  • the design capacity;
  • a requirement that excavation be complete before piles are driven;
  • driving criteria: minimum tip elevation, minimum penetration, and final blow count in blows per inch over the last 6 in. Where test piles and load tests are included, set the blow count after the load tests;
  • driving sequence for groups, from the center outward;
  • a minimum distance from concrete less than 7 days old (60 ft in his example);
  • submittal of the driving equipment;
  • limits on jetting, which must stop 3 to 6 ft above the expected final tip so the last few feet are driven;
  • conditions under which predrilling is allowed;
  • whether cut-offs may be spliced and reused.

His example tolerance is a maximum deviation of ¼ in per ft from vertical or plan batter, and 3 in in any direction at cut-off elevation.

For payment, he separates fixed costs from variable costs so that neither party gains or loses unfairly when the pile footage changes:

  • Mobilization of pile-driving equipment: lump sum, including moves between locations and demobilization. This is the largest fixed cost, especially for barge work.
  • Production piles: per linear foot from tip to actual cut-off, by type and size. The unit price normally covers jetting, followers, rejected and damaged piles, and, depending on the contract, cut-offs.
  • Cut-offs on timber or precast piles: pay separately by the linear foot when the engineer sets the ordered lengths.
  • Test piles: pay separately. They cost more per foot than production piles even if they become permanent.
  • Load tests: pay per each, because the number is uncertain.
  • Predrilled holes: per linear foot. Pipe-pile points, H-pile tips and splices: per each.

For railroad work: On bridge and culvert replacement projects, the pile monitoring plan in this section should check that the driving criteria and tolerances in the contract match the design, and that the pay items match what the inspector will record. Tip elevation, penetration, final set, cut-off elevation, and splice and cut-off lengths should all appear on the pile log. Where tie-in work is restricted to short track windows, mobilization and remobilization between windows should be priced explicitly so they do not end up as claims.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 20, 225–233. Summarized and paraphrased. Full reference under Supplemental Sources.

Project management · Seeley (1993)

Recording Piling Data to Match the Pay Items

Seeley shows how CESMM3 (Classes P and Q) splits piling so that a variation can be valued fairly. Items are grouped by piles of the same type, material and section at one location. Each group produces two or three items:

  1. The number of piles. This covers moving the rig to each position, setting up and preparing to drive or bore.
  2. The length of piles. This covers the material. For cast-in-place piles it is measured from the cut-off level to the toe level that was expressly required.
  3. The depth driven or bored, measured from a stated commencing surface. Raked piles are identified, with the rake stated.

Interlocking sheet piling is measured by area: the mean horizontal length of the wall times the depth. Corner, junction, closure and taper piles are extra linear items. Plant mobilization and temporary staging suit fixed method-related charges, and operating the piling plant suits a time-related charge. Ancillary work is measured only when expressly required. That includes cutting off surplus length, preparing pile heads, and extensions, which are paid as a number item for each joint plus a length item split at about 10 ft. Breaking out obstructions above the founding stratum is paid by the hour, and only when ordered, so the engineer can control and record it. Load tests and non-destructive tests are separate items.

For railroad work: on bridge pier, abutment and retaining-wall piling, the inspector’s driving record is the evidence for each of these quantities, so record them on the log as the work proceeds. For every pile, record:

  • pile ID and group
  • ground or commencing elevation when driving starts
  • tip elevation reached and the cut-off elevation
  • length delivered, length cut off and splices made
  • batter
  • start and stop times of any ordered obstruction work, with the reason
  • any re-strike or dynamic test

When a pile runs past its plan length, separate records for the pile count, the length furnished and the depth driven let the change be priced from the bid items. It does not have to become a lump-sum claim. Where piling is done under track windows or next to live track, note the time lost waiting for trains, so that time-related standby can be reconciled against the railroad’s own records.

Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 166–167. Summarized and paraphrased. Full reference under Supplemental Sources.

15.5 Static Axial Load Testing (ASTM D1143)

Static load testing is the most reliable method for confirming driven or drilled pile capacity. It is required by UPRR, BNSF, and Amtrak for all new bridge foundations; by CSXT and NSR for projects with design load > 200 tons per pile.

15.5.1 Quick Load Test Method (ASTM D1143, Method B)

Load is applied in 8% increments of the anticipated failure load, each increment held for 2.5 minutes, until failure or 200% of design load is reached. Total test duration is typically 2–4 hours.

Load application:

Test load applied by hydraulic jack against a reaction system (kentledge deadweight, reaction piles, or helical anchor reaction frame).

Jack force:

P_jack = p_hydraulic × A_ram (lb)

where p_hydraulic = hydraulic pressure (psi) and A_ram = ram area (in.²).

Settlement measurement: Four dial gauges or LVDTs at 90° spacing, referenced to a stable reference beam. Resolution ≥ 0.001 in.

Reference graphics

Static Vertical Pile Load Testing
Static Vertical Pile Load Testing
Pile Load Test – Vertical Compression
Pile Load Test – Vertical Compression
Pile Testing — Purpose Behind Each Test
Pile Testing — Purpose Behind Each Test

Reference graphics · click to zoom

Pile Load Test
Pile Load Test
15.5.2 Failure Criteria

Davisson Offset Method (standard for driven piles, adopted by UPRR, BNSF, CSXT, NSR):

Δ_failure = (Q × L) / (A_pile × E_pile) + (D/120) + 0.15 in.

where:

  • Q = applied load (lb)
  • L = pile length (in.)
  • A_pile = pile cross-sectional area (in.²)
  • E_pile = elastic modulus of pile material (psi); 29 × 10⁶ psi for steel
  • D = pile diameter or width (in.)
  • 0.15 in. = constant offset

Plot load-settlement curve; intersection of load-settlement curve with Davisson offset line defines Q_failure (tons).

Design capacity: Q_allow = Q_failure / FS

FS = 2.0 (with PDA + CAPWAP); FS = 2.5 (without load test); FS = 2.0 (with static load test) — per AREMA MRE Chapter 8 and UPRR/BNSF Engineering Instructions.

Reference graphics

Why Are Some Foundation Piles Tested Until They Move
Why Are Some Foundation Piles Tested Until They Move
15.5.3 Drilled Shaft (Drilled Pier) Load Testing — ASTM D1143

For UPRR crane rail foundations and BNSF intermodal structure piers, Osterberg Cell (O-Cell) testing is preferred over top-down testing when reaction frames would conflict with existing structures. The O-Cell is a bidirectional load cell embedded in the shaft; it loads the tip against the side in two directions simultaneously.

O-Cell net upward force:

Q_side = Q_cell − Q_tip(mobilized) (lb)

The O-Cell test produces separate side friction and tip resistance load-settlement curves, which are combined analytically to produce the equivalent top-down capacity.

Reference graphics

O-Cell Load Testing — Pile Resistance
O-Cell Load Testing — Pile Resistance
CSL Access Tube Requirements for Drilled Piles
CSL Access Tube Requirements for Drilled Piles
Bored Pile Tremie Concreting
Bored Pile Tremie Concreting

Reference graphics · click to zoom

Bi-Directional Static Load Testing
Bi-Directional Static Load Testing
15.6 Settlement Monitoring
15.6.1 Settlement Plates

Settlement plates are installed at the base of embankment construction to measure total settlement of the underlying foundation soils during and after filling. They consist of a steel plate (24 in. × 24 in. × ¼ in.) with a vertical measurement rod extending through the embankment fill.

Settlement measurement:

S = E_initial − E_reading (in. or ft)

where E_initial = initial elevation of plate top (ft); E_reading = current survey elevation (ft).

Settlement plates are read by differential leveling survey with ±0.01 ft precision. Reading frequency:

Table 15-2. Settlement Plate Reading Frequency by Construction Stage
StageReading FrequencyPurpose
Embankment filling (active)Daily or each fill liftTrack rate of settlement vs. fill height
End of fillingDaily for first 2 weeksConfirm no sudden increase
Consolidation monitoringWeekly for first 3 monthsConfirm consolidation progressing per design
Long-term monitoringMonthly until ΔS < 0.01 ft/monthConfirm primary consolidation complete

CSXT Engineering Standards require settlement plate data to be delivered to the project engineer within 24 hours of each reading during active filling.

15.6.2 Embankment Fill Rate Control

During staged construction over soft ground (Chapter 17), the fill rate must be controlled to prevent undrained shear failure. The maximum safe fill rate:

ΔH_max per lift = (ΔS_u / γ_fill) × FS_slope (ft/lift)

where:

  • ΔS_u = strength gain of subgrade per inch of consolidation (SHANSEP, Chapter 17)
  • γ_fill = unit weight of fill = 120–130 pcf
  • FS_slope = required slope stability FS ≥ 1.25 (short-term per AREMA/USACE)

Field monitoring trigger: if settlement rate increases disproportionately to fill rate (creep rupture indicator), suspend filling immediately and notify the geotechnical engineer. BNSF Engineering Instructions define this as ΔS > 1 in./day without new fill added.

Supplemental reference · LEVI Library

Monitoring track support after construction: wayside instrumentation and GPR

Wayside monitoring of fouled ballast (FRA/BNSF waiver research). Under an FRA waiver from 49 CFR §213.103 (2017–2019, 340 route miles of BNSF track), six solar-powered wayside sites near Lincoln, NE and Kansas City, MO recorded rail and tie strain, accelerations, video displacement and ballast moisture from 2017 to 2020. Support was measured by the distribution efficiency DE = PDist/PC × 100%, where PC is the wheel load from crib strain gauges and PDist is the load still carried by the rail over the tie. DE = 100% is a hanging tie, and a well-supported tie carries about 40% (DE ≈ 40%). Findings:

  • Fouling at every site was CL–CH clay at or near its liquid limit — derived from the subgrade, not ballast breakdown or spillage.
  • At Parkville, MO, DE was 29% while frozen and 47% after thaw, and rose to 71% with repeated freeze–thaw. Surfacing brought it back to 36% (about a 50% stiffness gain). Fouled ballast took up to 7 days to freeze but only 1–3 days to thaw, so stiffness is lost faster than it is gained.
  • Higher-plasticity fouling produced larger freeze–thaw swings than more visible but lower-PI fouling: the type of fouling may matter more than the amount. Concrete-tie sites were more sensitive to rain and freeze–thaw than timber-tie sites.

Network GPR (BNSF). BNSF has used ground-penetrating radar since 2009 and in 2018 added it to its train-based geometry car (Figure 15-S1). It reports a Ballast Fouling Index (BFI, the GPR estimate of Selig’s FI = P4 + P200 in the top 16 in.) for the center and shoulders, and since 2018 a Free Draining Layer depth (FDL, 0–16 in. of clean ballast above the fouled zone; Figure 15-S2). Calibration used an automated “Vibro Sampler” for physical gradations. The goal is to group track reliably into clean, moderate and fouled rather than to match FI exactly. BFI and FDL, with geometry, tonnage and maintenance history, feed a model that chooses among surfacing, shoulder ballast cleaning (fast, but does not fix high center fouling), track lifting and undercutting (productivity drops with high fines and moisture), and ditching. For geotechnical work, low FDL with clay-type fines points to a subgrade source, which ballast cleaning alone will not cure.

Source: Stark, T. D., Thompson, H. B., Sussmann, T. R., Bruzek, R. and Banister, R. (2021). “Long-Term Field Monitoring of Fouled Ballast.” AREMA 2021 Annual Conference · Bankston, A. (BNSF) and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve BNSF’s Ballast Maintenance Planning.” AREMA 2021 Annual Conference

Supplemental figures · LEVI Library
GPR antennas on BNSF&rsquo;s train-based track geometry inspection platform.
Supplemental Figure 15-S1. GPR antennas on BNSF’s train-based track geometry inspection platform. Source: Bankston, A. (BNSF) and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve BNSF’s Ballast Maintenance Planning.” AREMA 2021 Annual Conference.
Ballast Fouling Index (BFI) and Free Draining Layer (FDL) as measured by GPR.
Supplemental Figure 15-S2. Ballast Fouling Index (BFI) and Free Draining Layer (FDL) as measured by GPR. Source: Bankston, A. (BNSF) and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve BNSF’s Ballast Maintenance Planning.” AREMA 2021 Annual Conference.

Geometry acceptance after construction or maintenance

After tamping, a survey crew sets the lift and line corrections, the tamper corrects and compacts under the ties, and a recording car checks the remaining defects against acceptance values. Stabilizing machines that follow the tamper raise lateral resistance. If heavy machinery does the leveling, no further lifts should be made until traffic has stabilized the track. Defects left after that period are corrected with light equipment without re-lifting.

Table 15-7. Acceptance values of track defects after maintenance (European practice)
Track speed (mph)> 155124–15575–124> 50< 50
Longitudinal defect (in.)0.0790.120.120.160.2
Horizontal defect (in.)0.0790.120.120.160.2
Track twist (in./ft)0.0120.0120.0120.0180.018
Track gauge (in.)±0.079±0.079±0.079±0.12±0.12

The period up to about 2 million tons after the work (about 1–4 months on a UIC group 4 line, 15–40 days on busier lines) is when defects grow fastest. Profillidis calls continuous monitoring and prompt local correction during this period the key to track longevity. The same window applies after subgrade repairs, undercutting and new embankment tie-ins.

Figures · click to zoom

Figure 15-12. Tamping machine during track maintenance. Profillidis Fig. 16.9.
Figure 15-12. Tamping machine during track maintenance. Profillidis Fig. 16.9.
Figure 15-13. Flow chart of planning and implementation stages for track renewal and maintenance (years N−3 to N+1). Profillidis Fig. 16.12.
Figure 15-13. Flow chart of planning and implementation stages for track renewal and maintenance (years N−3 to N+1). Profillidis Fig. 16.12.

After Profillidis (2014), §16.6.3, §16.8–16.10, Table 16.3, Figs. 16.9, 16.12. Full reference under Supplemental Sources.

15.7 Piezometric Monitoring During Staged Construction

During staged embankment filling over soft saturated fine-grained soils, piezometers are installed to monitor excess pore pressure buildup. Rapid excess pore pressure buildup indicates faster loading than the soil can drain, creating instability risk.

15.7.1 Excess Pore Pressure and Safety Check

Excess pore pressure ratio:

r_u = Δu / σ_v

where Δu = excess pore pressure (psf) and σ_v = total vertical stress increase from fill (psf).

Safe fill criterion: If r_u > 0.5, suspend filling. This is the practical trigger used by CSXT, NSR, and CN for staged construction projects, based on USACE EM 1110-2-1901.

Degree of consolidation from piezometer:

U_field = 1 − (Δu / Δu₀)

where Δu₀ = initial excess pore pressure immediately after fill placement; Δu = current excess pore pressure.

Compare U_field to the design U from the time-rate analysis (Chapter 12). If U_field is lagging behind design U, fill placement may be advanced at a reduced rate; never faster than design.

15.7.2 Vibrating Wire (VW) Piezometer Readings

VW piezometers output a frequency reading (Hz) that is converted to pressure:

P = G × (R − R₀) + K × (T − T₀) (psf or psi)

where:

  • G = gauge factor (psi/digit, from calibration sheet)
  • R = current reading (digits = Hz²)
  • R₀ = baseline reading (Hz²)
  • K = temperature correction factor (psi/°F)
  • T − T₀ = temperature change (°F)

Typical VW reading cycle: automated datalogger at 15-minute intervals during active filling; hourly during consolidation monitoring. CSXT and Amtrak require automated datalogger downloads every 24 hours to project engineer during active construction.

Reference graphics

Groundwater Monitoring for Slope Stability
Groundwater Monitoring for Slope Stability
15.8 Inclinometer Monitoring

Inclinometers measure lateral ground movement (horizontal deflection) in embankments, slopes, and retaining walls. A probe is lowered through a casing installed in a near-vertical borehole to measure deviation from vertical.

Reference graphics

Slope Stability Radar
Slope Stability Radar
15.8.1 Deflection Calculation

Incremental displacement:

δ_h = L × sin(θ) (in. per segment)

where L = probe wheel spacing (usually 2.0 ft) and θ = tilt angle read by accelerometer (radians or degrees).

Cumulative deflection from depth z to surface:

Δ_H = Σ (L × sin θ_i) (in.)

Plotted as deflection profile vs. depth. The shear zone (zone of maximum rate-of-change of deflection with depth) indicates the failure plane location.

15.8.2 Trigger Levels and Action Plans
Table 15-3. Inclinometer Trigger Levels — Railroad Applications
Trigger LevelCriteriaAction Required
AlertΔ_H > 0.25 in. in any 7-day periodNotify geotechnical engineer; increase reading frequency to daily
ActionΔ_H > 0.50 in. in any 7-day periodSuspend construction operations in affected zone; convene engineer review
EmergencyΔ_H > 0.10 in./day on 3 consecutive daysImmediately halt all loading; implement emergency support if needed; notify RR dispatcher

Source: Compiled from CSXT Eng. Std., NSR Eng. Std. Manual, UPRR Eng. Instr. Manual, and USACE EM practice.

Reading frequency during active construction:

  • Baseline: 3 readings prior to construction (establish stable reference)
  • Active filling: twice weekly minimum; daily if Alert level reached
  • Post-construction: weekly for first 3 months; monthly until stable

Simple crack monitoring and stabilization follow-up

Before or alongside instruments, crews monitor tension cracks with survey markers driven at the crack and paint marks across it, recording whether it is widening. After stabilization, the course’s program confirms effectiveness through follow-up geotechnical inspections over at least two years, tracked against track-inspection results. Keep records of trench-drain locations, since silt can clog them within 2–6 years.

Figures · click to zoom

Figure 15-18. Tension crack with a survey marker at Togo 73.0.
Figure 15-18. Tension crack with a survey marker at Togo 73.0.
Figure 15-19. Tension crack along the track shoulder.
Figure 15-19. Tension crack along the track shoulder.

After Geotechnology for Railroaders Program, Module 6.1, Module 7.1, Module 1, Module 6.6; Module 6.1 §05; Module 7.1 §05; Module 1 §10. Full reference under Supplemental Sources.

15.9 Client-Specific Construction Monitoring Requirements
Table 15-4. Construction Monitoring Requirements by Railroad Client
RailroadCompaction Test (method)Proof Roll (required?)PDA Piles (%)Static Load TestSettlement PlateInclinometerPiezometerGoverning Std.
CSXTD6938 nuclearYes (mainline)5%> 200T designRequired: staged const.Soft subgradeStaged const.CSXT Eng. Std. Sec. 7
NSRD6938 or D1556Yes (mainline)5%> 200T designRequired: staged const.Soft subgradeStaged const.NSR Eng. Std. Sec. 7
G&WD6938 or D1556Case-by-caseNot requiredNot requiredCase-by-caseCase-by-caseCase-by-caseG&W Eng. Bulletin
UPRRD6938 nuclearYes (mainline)10%All bridgesRequired: staged const.Staged const.Staged const.UPRR Eng. Instr. Manual
BNSFD6938 nuclearYes (mainline)10%All bridgesRequired: staged const.Staged const.Staged const.BNSF Eng. Instructions
CPKCD6938 nuclearYes (mainline)10%All bridgesRequired: staged const.Staged const.Staged const.CPKC Track Standards
AmtrakD6938 or D1556Yes (all track)100% (NEC)All bridgesRequired: allAll embankmentsAll soft groundAmtrak Eng. Std.
CND6938 nuclearYes (mainline)10%All bridgesRequired: staged const.Staged const.Staged const.CN Eng. Standards
15.10 Construction QA/QC Documentation

Reference graphics

Concrete Defects — Repair vs Rejection
Concrete Defects — Repair vs Rejection
Concrete Inspection
Concrete Inspection

Reference graphics · click to zoom

Quality Assurance vs Quality Control
Quality Assurance vs Quality Control
15.10.1 Daily Field Report

The geotechnical inspector is responsible for a daily field report for each day of active monitoring. Minimum content:

  • Project identification (railroad, project number, location/station limits)
  • Weather conditions (temperature, precipitation)
  • Work performed by contractor (description, location, quantities)
  • Compaction test results (test location, lift number, test type, γ_d,field, MC%, RC%, pass/fail)
  • Anomalies observed (soft areas, wet materials, equipment problems)
  • Monitoring instrument readings (settlement plates, piezometers, inclinometers)
  • Photographs (minimum 4 per day: general progress, each compaction test location, any anomaly)
  • Inspector name, certification, and signature

All nine client railroads require daily field reports to be submitted electronically (PDF) within 24 hours. CSXT uses ProjectWise; UPRR and BNSF use their proprietary project management portals; NSR requires submission to the project engineer of record by email with a structured naming convention.

Reference graphics

Daily Site Inspection Checklist
Daily Site Inspection Checklist
15.10.2 Compaction Test Log Format
Table 15-5. Sample Compaction Test Log (Nuclear Gauge)
Test No.DateStationLift No.Depth (in.)γ_d,field (pcf)MC (%)γ_d,max (pcf)RC (%)Min. RC (%)Pass/Fail
00106/01/26240+5036121.410.2127.095.695.0Pass
00206/01/26241+0036118.712.5127.093.595.0Fail
00306/01/26241+0036122.110.8127.096.195.0Pass (retest)
15.10.3 Pile Driving Log Format

A pile driving log must be completed for every driven pile:

  • Pile identification: cap reference, pile number, type, dimensions, length, cut-off elevation
  • Hammer: type, rated energy, stroke (measured or reported by contractor)
  • Driving record: blow count per foot from ground to tip; record in intervals ≤ 1 ft
  • PDA monitoring: ETR, CSX, TSX, Case method capacity (if PDA equipped)
  • Final set: blows per inch at final 6 in. of driving
  • Tip elevation (ft); total pile length driven (ft)
  • Inspector name and RWP certification number

UPRR and BNSF Engineering Instructions require the final pile driving log to be signed by both the geotechnical inspector and the railroad construction inspector.

Project management · Skill Right (2013)

Tracking Cost Against Plan and Managing Change in Construction-Phase Services

During execution, the course compares progress to plan with three tools: quality reviews, Gantt schedule performance charts and cost performance charts. Its cost chart plots cumulative planned value (PV) against cumulative actual cost (AC) by week. In the example, planned value reaches $44,000 by week 5 against an actual cost of $66,000, so spending is 50% above plan and the gap has widened every week.

Table 15-PM1. Cumulative planned value and actual cost, $1,000 (after Skill Right 2013, Cost Performance Chart)

Week12345
PV36183044
AC816304866

For change, the course separates customer-requested changes (usually the largest source) from internal requests, regulation and team-generated changes. Its procedure is: hold a team meeting, explain the change, get feedback, identify alternatives, prepare a decision matrix, select a recommendation, present it to management or the customer, and implement the approved course.

For railroad work: a PV-versus-AC chart cannot by itself tell overspending apart from work being done ahead of schedule. Add the budgeted value of the work actually performed, measured in physical units: inspector shifts actually needed, density tests, piles observed, monitoring rounds and reports issued. Construction-phase geotechnical budgets on railroad projects are often consumed by standby and repeat mobilizations when track windows are cancelled or the contractor’s sequence changes. Log those days as a separate cost line from the first occurrence. Then, when the change procedure is invoked, the decision matrix compares real alternatives:

  • keep a full-time inspector on standby;
  • switch to on-call coverage with notice requirements;
  • request a scope and fee amendment for the extended duration.

Report cost status with the same frequency and in the same document as the QA/QC test summaries, so the railroad sees quality, schedule and cost together.

Cumulative planned value and actual cost by week, with actual cost running well above plan by week 5.
Figure 15-PM1. Cumulative planned value and actual cost by week, with actual cost running well above plan by week 5. Source: Skill Right (2013), Slide: Cost Performance Chart.

Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 81–83, 86–87. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Project management · Sears et al. (2015)

Change Orders, Claims and the Daily Job Log

Sears et al. list the main sources of project change: added or altered work ordered by the owner or engineer, contractor value-engineering proposals, delays caused by the owner or other contractors, and job-site conditions that differ materially from those anticipated. Their procedure for handling a change:

  1. Document each change when it arises, estimate its cost and time effects before the work starts, and get written approval to proceed.
  2. To find the time effect, bring the schedule network fully up to date without the change, calculate it, then insert the change and recalculate. The difference is the change. A change on a non-critical path may justify no time extension, but it still uses up float.
  3. Watch for knock-on effects. A foundation problem can push later work into bad weather. In their bridge example, a delayed abutment could put the work into the season when the dry riverbed becomes a stream.
  4. Treat overhead carefully. A fixed markup (10–15% of direct cost is common) covers processing the change but not extended field overhead. Where the duration grows, the network shows how many days of job overhead apply ($869 per day on the example bridge).

Their rule for claims is documentation, and the core record is the daily job log. Each entry records the date, weather, workers by craft, equipment by type, activities started and finished with quantities, subcontractors on site, deliveries (including late or damaged ones), visitors and inspectors, meetings and decisions, problems, and corrective steps. To be accepted as evidence, entries must be original, made on the date shown in the regular course of business, based on the writer’s own knowledge, and kept in a bound book or an equivalently secure electronic system. Entries should state facts without opinion or emotion.

For railroad work: The inspector’s daily report on a railroad job should add the items that drive most disputes there: the track window granted versus planned, with start and stop times; flagging availability; train delays and slow orders in effect; and quantities of undercut, unsuitable material removed and fill placed by station. When the subgrade exposed in an undercut differs from the boring logs, photograph it, note the stations and depths, and notify the railroad’s representative the same day. Then run the “with and without change” schedule comparison before the next window is booked.

Source: Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons, pp. 328–332. Summarized and paraphrased. Full reference under Supplemental Sources.

Project management · Levy (2007)

Daily Logs, Photographs and Event Records as Claim-Grade Documentation

Levy (2007) treats documentation as part of the work itself and places his documentation chapter immediately before the one on claims for that reason. Good records are not volume; they are prompt, accurate entries made when important events happen. For any significant event he recommends recording what happened, when and how it happened, when it was discovered, whether responsibility can be assigned with certainty, who was notified and when, its impact, the immediate and longer-term actions required and by whom, and which party will resolve it. Facts should be separated from opinions; useful remarks at meetings can be noted separately to show intent.

The superintendent’s daily record is the backbone. Levy notes that a bound diary with daily entries meets the legal definition of a business record, while loose sheets may not, and suggests reviewing electronic logs with counsel. At a minimum each entry should give the date (with “No Work” on idle days); weather and temperature at start, midday and end of shift; each subcontractor on site with crew size, work and location; the firm’s own workforce and tasks; visitors and their purpose; inspections by agencies, testing labs or the engineer; work performed and where; deliveries with ticket numbers; unusual events and stoppages; and every accident, reportable or not.

Photographs document progress or lack of it, conditions that differ materially from those expected, support for change orders, and complex details. Levy recommends a tape or rule in close-ups for scale, and specifically lists rock, groundwater and buried debris as conditions to photograph even when they seem unlikely to matter contractually. His closing advice is simply: document, document, document.

For railroad work: The geotechnical field representative’s daily report on a subgrade rehabilitation, slide repair or culvert replacement should add railroad-specific fields: track and work-window times granted and released, the employee in charge or flagman, trains passed during the window, any slow order in effect, and lost window time with its cause. Photograph undercut subgrade, seepage, slip surfaces and unsuitable material in place with a scale and a station reference before it is removed or covered, and link each photo to the daily report and test locations.

Sample bound daily log page with workforce tally, subcontractor activity, visitors, inspections and supervisor signature.
Figure 15-PM2. Sample bound daily log page with workforce tally, subcontractor activity, visitors, inspections and supervisor signature. Source: Levy (2007), Figure 11.3a.

Source: Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill, pp. 229–230, 255–260. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Project management · Goldbloom (1989)

Method versus End-Result Requirements and the QC/QA Split

Goldbloom states a basic rule: responsibility for the result follows whoever prescribed the method. If a specification dictates how the work is done and the contractor follows it, the contractor is not liable for a bad result. His common bad example is embankment specifications that fix loose-lift thickness, compactor type and size, and number of passes, and then also demand a minimum in-place density. When the procedure is followed and the density is missed, the owner has no position. His recommended end-result approach is to:

  • limit loose-lift thickness and the moisture range;
  • specify the required density as a percentage of the laboratory maximum dry density;
  • let the contractor choose hauling, spreading, moisture control and compaction equipment;
  • have the engineer verify compliance by in-place density tests.

Lift thickness, moisture, the dumping method, and the type and size of the compactor all affect the number of passes needed. That is why the means should be left to the contractor.

He also separates two functions:

  • Quality control (QC) is the contractor’s responsibility for running its operations so they produce conforming work.
  • Quality assurance (QA) is the owner’s representative checking that the work conforms.

Each technical section should say which tests the engineer will perform and by what method, so the contractor knows how acceptance will be judged. His cautionary example is a contract that made the contractor hire the testing laboratory for in-place density, batch-plant inspection and concrete cylinders. A lab paid by the contractor owes its first loyalty to the contractor, so this cannot serve as QA.

On tolerances, he notes that rigid wording such as “true to line and grade” leads to claims. In one spillway case the court allowed the contractor to recover the cost of forming to tolerances tighter than the finished structure required.

For railroad work: Ballast, subballast and subgrade QA/QC documentation should state for each item whether it is an end-result or a method requirement, and should not mix the two. When a method requirement is unavoidable, such as track-time-limited proof rolling or prescribed lift placement under a work window, write the acceptance criterion as conformance to that method. Keep acceptance testing (nuclear gauge, plate load, proof roll observation) with the railroad’s representative or its own consultant. Contractor testing should be identified as QC only. Give grade and cross-slope tolerances that track and drainage design can actually live with.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 20–21, 183–184, 188. Summarized and paraphrased. Full reference under Supplemental Sources.

Project management · Anglin (2020)

Documenting a Differing Site Condition in the Field

Anglin works through the general-conditions clause on concealed or unforeseen conditions, quoting AIA A201 (Article 4.3.4), and illustrates it with a case from his own practice. The clause recognizes two types:

  1. Subsurface or concealed physical conditions that differ materially from those shown in the contract documents.
  2. Unknown conditions of an unusual nature that differ materially from those normally encountered in that kind of work.

Whoever observes the condition must give notice promptly, before it is disturbed, and in any case within 21 days. The architect or engineer then investigates. If the condition does differ materially, a change follows; if not, the reasons must be given in writing. Anglin stresses giving written notice of cost or delay even before the amount is known. A continuing delay needs to be documented only once.

In his fire-college case, excavation for a new building uncovered a fire line that turned unexpectedly under the footprint. The contractor took these steps:

  • Stopped excavating at the pipe.
  • Traced its path on the ground and photographed it.
  • Sketched the planned and actual alignments.
  • Notified the architect the same day.
  • Priced the relocation.
  • Issued a notice of continuing delay.

The owner argued that a plan note required the contractor to field-verify utilities. The contractor answered that, under the contract, studying the documents is meant to facilitate construction, not to discover errors. He also showed that no one had specified a particular sequence of excavation. The owner paid.

For railroad work: on subgrade, slope and culvert jobs, the geotechnical field representative is usually the first to see the condition. Typical examples are:

  • buried timber or old trestle bents
  • cinders, or pockets of fouled ballast deeper than the planned undercut
  • springs
  • soft clay below the design subgrade elevation
  • an unmarked utility or fiber-optic line

The daily report should record:

  • the location by milepost and station, offset and depth
  • photos with a scale and a reference point
  • samples and a quick classification
  • a direct comparison with the baseline in the geotechnical report and the boring logs
  • the time work stopped and the time it resumed
  • who was notified, and when

Railroad and agency contracts set their own notice periods and procedures, so put them in the field instructions before work starts.

Source: Anglin, G. (2020). Introduction to Estimating, Plan Reading and Construction Techniques. Abingdon: Routledge, pp. 381–382, 387–390. Summarized and paraphrased. Full reference under Supplemental Sources.

15.11 Worked Calculation Examples
Example 15-1: CSXT Bridge Abutment — Compaction Acceptance

Project context: CSXT Georgia Division bridge abutment replacement. Structural fill compacted with a Cat 836K landfill compactor. Modified Proctor reference: γ_d,max = 125.5 pcf at w_opt = 11.2%.

Given (nuclear gauge readings from Test 014):

  • Wet density from gauge: WD = 139.4 pcf
  • Moisture from gauge: MC = 11.8%

Step 1: Field dry density

γ_d,field = WD / (1 + MC/100) = 139.4 / (1 + 0.118) = 139.4 / 1.118 = 124.7 pcf

Step 2: Relative compaction

RC = (124.7 / 125.5) × 100% = 99.4%

Step 3: Compare to specification

CSXT requirement for structural fill: RC ≥ 95%. RC = 99.4% >> 95% ✓

Step 4: Moisture check

CSXT Engineering Standards require moisture within ±3% of w_opt = 11.2%: acceptable range 8.2%–14.2%. Field MC = 11.8% ✓

Result: Test 014 — PASS. Document on daily field report and compaction test log.

Example 15-2: UPRR Bridge Pile — PDA Case Method Capacity Check

Project context: UPRR Columbia River crossing. 14-in. H-pile (HP14×117), L = 75 ft, driven with ICE 660 hydraulic hammer (E_rated = 66,000 ft·lb). PDA equipped. Clay subgrade.

Given (PDA record at final set):

  • F(t₁) = 650,000 lb (measured peak force)
  • V(t₁) = 8.5 ft/s
  • F(t₁ + 2L/c) = 280,000 lb; V(t₁ + 2L/c) = −2.1 ft/s
  • Z = E × A / c; E = 29 × 10⁶ psi; HP14×117: A = 34.4 in.²; c = 16,808 ft/s
  • J_c = 0.50 (clay)

Step 1: Pile impedance

Z = (29 × 10⁶ psi × 144 in.²/ft² × 34.4 in.²) / (16,808 ft/s × 144)

Actually: Z = (E × A) / c with consistent units:

E = 29 × 10⁶ lb/in.² × 144 in.²/ft² = 4.176 × 10⁹ lb/ft²

Z = (4.176 × 10⁹ × 34.4/144) / 16,808 = (4.176 × 10⁹ × 0.2389) / 16,808 = (997,646,400) / 16,808 = 59,356 lb/(ft/s) ≈ 59,400 lb·s/ft

Step 2: Case Method capacity

R_total = ½ × (1 + 0.50) × [650,000 + 59,400 × 8.5] + ½ × (1 − 0.50) × [280,000 + 59,400 × (−2.1)]

= ½ × 1.50 × [650,000 + 504,900] + ½ × 0.50 × [280,000 − 124,740]

= 0.75 × 1,154,900 + 0.25 × 155,260

= 866,175 + 38,815 = 905,000 lb = 452 tons

Step 3: Allowable capacity

Q_allow = 452 / 2.0 (FS with PDA + CAPWAP restrike) = 226 tons

Design load = 180 tons. FS_actual = 452 / (180 × 2) = 1.26... Wait — with PDA: Q_allow = R_total / FS = 452 / 2.0 = 226 tons > 180 tons design ✓

Conclusion: Pile meets design load requirement. Schedule CAPWAP analysis of this record and two additional PDA records per UPRR requirements.

Example 15-3: NSR Soft Clay Embankment — Piezometer Alert Evaluation

Project context: NSR Alabama Division embankment over soft Gulf Coast clay. Staged construction with PVDs installed. Current embankment height H = 12 ft (fill placed in last 3 days). VW piezometer at 15 ft depth reads Δu = 850 psf. Fill unit weight γ_fill = 122 pcf.

Step 1: Vertical stress increase from new fill

σ_v = γ_fill × H = 122 × 12 = 1,464 psf

Step 2: Excess pore pressure ratio

r_u = Δu / σ_v = 850 / 1,464 = 0.581

r_u = 0.581 > 0.50 → Action threshold exceeded.

Step 3: Required response

Per NSR Engineering Standards and USACE EM 1110-2-1901: suspend filling immediately. Notify NSR project engineer and geotechnical engineer within 1 hour. Increase piezometer reading frequency to every 2 hours. Do not resume filling until r_u falls below 0.35 (NSR staged construction protocol).

Step 4: Field consolidation check

Settlement plate data shows ΔS = 0.82 in. over last 3 days (0.27 in./day). No excessive rate yet but r_u exceeded. This is consistent with rapid load application exceeding drainage capacity of PVDs. Verify PVD installation spacing matches design (see Chapter 17).

Step 5: Document

Issue written Piezometer Alert notification to NSR project manager, contractor superintendent, and NSR construction inspector within 24 hours (NSR Engineering Standards requirement). Attach VW reading log and r_u calculation.

Project management · Sears et al. (2015)

Earned Value Analysis of a Construction Contract

Sears et al. point out that a standard monthly cost forecast shows only whether the job will finish over or under budget. It cannot tell whether the variance comes from cost performance, schedule performance or both. The earned value management system (EVMS) separates the two by comparing three cumulative quantities at each update:

  • BCWS (budgeted cost of work scheduled): the planned value of the work that the baseline schedule calls for by the update date.
  • BCWP (budgeted cost of work performed): the earned value, meaning the budgets of the work actually accomplished.
  • ACWP (actual cost of work performed): what the accomplished work actually cost.

From these: cost variance CV = BCWP − ACWP; schedule variance SV = BCWP − BCWS, expressed in dollars; CPI = BCWP/ACWP; SPI = BCWP/BCWS. An index below 1.0 calls for management attention. The estimate at completion is bracketed by EAC1 = ACWP + (BAC − BCWP)/CPI and EAC2 = ACWP + (BAC − BCWP)/(CPI × SPI), where BAC is the budget at completion. The to-complete index TCPI = (BAC − BCWP)/(EAC − ACWP) gives the cost efficiency needed on the remaining work.

Source example (highway bridge, day 27): BAC = $390,214; BCWS = $160,622; BCWP = $147,011; ACWP = $157,582. Then CV = −$10,571 and SV = −$13,611; CPI ≈ 0.93 and SPI ≈ 0.92. The forecast range is EAC1 ≈ $418,273 to EAC2 ≈ $442,409. In other words, if the cost inefficiency continues, the job finishes about $28,000 over, and continued schedule slippage could raise that to about $52,000.

The authors also describe the time-cost envelope (early-start and late-start cumulative cost curves) as the graphical forerunner of EVMS.

For railroad work: On a unit-price subgrade rehabilitation or slope repair, use the bid items as the budget lines and the construction monitoring quantities (cubic yards of undercut, tons of subballast or riprap, linear feet of drain, piles driven) as the earned value. Because work is confined to track windows, a low SPI often means windows were lost or shortened, not that crews were slow. Keep the window log next to the EV report so the cause is clear. A falling CPI combined with deeper-than-planned undercut is an early quantitative sign of a differing-condition trend that should be raised with the railroad before the next window, not at close-out.

Earned value plot showing BCWS, BCWP and ACWP curves at the present date, the cost and schedule variances, and the projected EAC range against the budget at completion.
Figure 15-PM3. Earned value plot showing BCWS, BCWP and ACWP curves at the present date, the cost and schedule variances, and the projected EAC range against the budget at completion. Source: Sears et al. (2015), Figure 11.9.

Source: Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons, pp. 298–303. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

15.12 Representative Monitoring Data Table
Table 15-6. Construction Monitoring Summary — NSR Alabama Staged Embankment
DayFill H (ft)σ_v (psf)Δu (psf)r_uS_plate (in.)ΔS/day (in.)Status
000000—Baseline
34.04881950.400.220.07OK
78.09764400.450.680.11OK
1012.01,4648500.581.500.27Alert — Suspend
1412.01,4646100.422.100.15Consolidating
2112.01,4643850.263.200.16OK — Resume fill
2515.01,8305200.283.850.16OK
3518.02,1964900.225.100.13OK
15.13 Figure Placeholders
  • Figure 15-1. Construction monitoring layout plan: settlement plate locations, piezometer clusters, inclinometer casings, and pile test locations relative to track centerline.
  • Figure 15-2. Nuclear gauge operating modes: backscatter mode (surface) and direct transmission mode (probe rod inserted) with depth settings.
  • Figure 15-3. Proof rolling: loaded truck traversing prepared subgrade; annotated photograph showing rut measurement technique.
  • Figure 15-4. WEAP bearing graph: ultimate capacity (tons) vs. blow count (blows/ft) for HP14×117 pile with ICE 660 hammer.
  • Figure 15-5. PDA force-velocity trace: annotated time-history showing peak force F(t₁), impedance check, and 2L/c return signal.
  • Figure 15-6. Davisson offset method plot: load-settlement curve with elastic compression line and Davisson offset line intersection defining Q_failure.
  • Figure 15-7. Settlement plate time-history: fill height (ft) and settlement (in.) vs. time (days) for NSR Example 15-3 embankment.
  • Figure 15-8. Piezometer excess pore pressure ratio (r_u) vs. time with alert and action threshold lines marked.
  • Figure 15-9. Inclinometer profile: cumulative deflection (in.) vs. depth (ft) from baseline to construction completion; shear zone highlighted.
  • Figure 15-10. Compaction test log format (annotated blank form showing all required fields for nuclear gauge testing).

Reference graphics

Pile load test
Pile load test
Plate Load Test Bearing Capacity Determination
Plate Load Test Bearing Capacity Determination
Foundation Failure - Excessive Settlement
Foundation Failure - Excessive Settlement
Settlement Plate Installation
Settlement Plate Installation
Triaxial Shear Test
Triaxial Shear Test
15.14 Practical Recommendations
  1. Establish trigger levels in writing before construction begins. Trigger levels for piezometers, settlement plates, and inclinometers must be defined in the geotechnical monitoring plan and agreed upon by the consultant, railroad project engineer, and contractor before any instrumentation is read. Ambiguous triggers during construction lead to decision paralysis at critical moments.
  2. Calibrate nuclear gauges against sand cone tests at each project. At least 5 paired nuclear/sand-cone tests at the start of each project verify gauge performance in the specific soil being tested. Nuclear gauges are accurate for most applications but can be unreliable in gravelly fills or soils with high organic content.
  3. Never accept PDA Case Method results as final capacity without CAPWAP. Case Method is a real-time field screening tool, not a definitive capacity method. CAPWAP signal matching provides the accepted capacity. All nine client railroads that require PDA monitoring also require CAPWAP analysis for final acceptance.
  4. Require restrike tests for piles driven in fine-grained soils. Skin friction in clay can be temporarily reduced by remolding during driving (setup loss) and then recovers (soil setup or freeze). UPRR and BNSF Engineering Instructions require restrikes at 24 hours (sand) and 7 days (clay) minimum. Restrike PDA data with CAPWAP often reveals 30–80% capacity gain in clay over initial drive capacity.
  5. Assign GPS coordinates to every compaction test and monitoring reading. Modern nuclear gauges have integrated GPS. For older gauges, use a handheld GPS unit. Station + offset alone is insufficient for QC documentation on long linear projects. GPS coordinates allow test results to be plotted on a project map and deficiency patterns to be identified.
  6. Submit inclinometer and settlement plate data to the railroad engineer weekly during active construction. Do not wait for the final report. Real-time data allows fill rate adjustments before unstable conditions develop. BNSF and CN Engineering Standards treat delayed submission of monitoring data as a scope deficiency.
  7. Document all oral decisions in writing within 24 hours. Construction monitoring generates many verbal field decisions (suspend filling, add a lift, reduce hammer stroke). Every decision made verbally in the field must be confirmed in writing by the geotechnical engineer and communicated to the contractor and railroad inspector. Undocumented field decisions are the primary source of claims and disputes in railroad geotechnical construction.

Reference graphics

Backfilling and Trench Compaction
Backfilling and Trench Compaction
Construction Rarely Fails at the Point of Failure
Construction Rarely Fails at the Point of Failure

Reference graphics · click to zoom

Critical Lift Planning
Critical Lift Planning

Building in track quality: renewal, tamping and stabilization

Inherent quality is set at construction. After every tamping, track drifts back toward the shape it acquired when it was built or renewed. Three findings show how strong this effect is:

  • A bend in the rail persisted 313 days after ballast renewal and four tampings, and reappeared within 2 months of each tamping. Keep rails straight in handling, and straighten them in place.
  • Long-wave faults in an uncompacted, as-laid ballast surface were still present after 3 years and 6 tampings. Lay track on a compact, fault-free ballast surface.
  • British Rail’s layered renewal reopened at full speed (about 125 mph) within a 48-hour possession, with a longer maintenance cycle afterward. The method: cut about 16 in. under laser depth control; place ballast in layers, then regulate and tamp each one to the same datum and compact it with a dynamic track stabilizer; then make a final stabilizer pass with compaction control.

Undercutter depth control. On a manually controlled undercutter, the cut depth follows the machine’s bogies, and deviations of about ±3 in. were recorded. Laser or water-level control gives a far smoother cut. Specify it, together with a cut surface sloped to the side drains that does not damage an existing blanket.

After tamping. Tamping loosens the cribs and shoulders, so lateral resistance drops. It is substantially regained after about a month of traffic.

  • One full-load stabilizer pass is roughly equivalent to 100,000 tons of traffic for lateral stability, and recovers about half of the loss. For settlement it is equivalent to 100,000–700,000 tons.
  • Relative to freshly tamped track at 0.079 in. of lateral displacement, crib consolidation raised resistance to about 115% and the dynamic track stabilizer to about 134%.
  • Crib and shoulder compaction also cut the scatter of later settlement. Tamped-only track varied 2 to 4 times more.

Tamping policy. Tamp only when geometry requires it. A low-lift tamp does not produce a lasting improvement; a lasting change needs a lift greater than the ballast D50. Stoneblowing complements tamping: use it for low lifts and short-wavelength faults, and use tamping for high lifts and long-wavelength faults.

After Selig & Waters (1994), chs. 14 and 15. Full reference under Supplemental Sources.

Project management · Haidar (2016)

Delay Analysis: Gross and Net Extensions, Concurrent Delay and Constructive Acceleration

Haidar reviews how extensions of time are calculated when an excusable event occurs while the contractor is already late through its own fault (culpable delay). Under the gross method, the extension runs from the date the event occurred, which sets a new completion date and removes liquidated damages up to it. Under the net method, the contractor receives only the time needed to absorb the event, added to the original completion date. In his example, a contractor six months late is delayed one further month by a relevant event. Under the net method the completion date moves one month past the original date, and five months of culpable delay remain exposed to liquidated damages. The net approach follows Lord Denning’s reasoning in Amalgamated Building Contractors v Waltham Holy Cross (1952).

On concurrent delay, Haidar cites Henry Boot v Malmaison (2000). If a week of work is lost both to exceptional weather (an excusable event) and to a labor shortage (not excusable), the contractor may still be entitled to a one-week extension. He warns that retrospective CPM analysis of very large networks is unreliable, because every logic link is an assumption and a network can be adjusted to make almost any work critical. Liquidated damages work only if the contract also provides a workable extension mechanism. To recover for constructive acceleration, a contractor must show that the owner failed to grant an adequate extension, insisted on the original date, received notice that the contractor was treating this as acceleration, and that extra cost was actually incurred. The cases cited are English, so the governing contract and jurisdiction control on any U.S. project.

For railroad work: the geotechnical field record is often the evidence in these analyses, so record in daily reports:

  • Track time requested, granted, and cancelled or shortened by operations, with times.
  • Weather and site conditions that stopped earthwork, compaction testing or drilling.
  • Hold points imposed because of monitoring results (inclinometer movement, settlement rate, pore pressure) and the time each was released.
  • Contractor resource shortfalls observed (crews, equipment, material) on the same days.

With all four recorded side by side, the railroad and the contractor can separate excusable delay from culpable delay without reconstructing events months later.

Gross method, which restarts the extension from the date of the delaying event, compared with the net method, which adds only the time for the extra work to the completion date.
Figure 15-PM4. Gross method, which restarts the extension from the date of the delaying event, compared with the net method, which adds only the time for the extra work to the completion date. Source: Haidar (2016), Fig. 3.10.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 75–79. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Project management · Cretu et al. (2011)

Risk Monitoring, Control and Contingency Drawdown

Cretu et al. stress that risk management fails most often after the analysis is finished. They invert the usual pyramid: planning and analysis take less effort than carrying out and tracking the responses. Their monitoring and control step includes tracking every risk in a master register, identifying new risks and retiring old ones, adjusting responses that are not working, managing the risk reserve (contingency) as it is spent, and checking that responses are actually carried out. Each risk gets an owner and a task manager who tracks how well the response works and reports on a set schedule. Updates go back to a single master register held by the project manager. The response action plans can be loaded into the project schedule as dated activities so that overdue responses stand out at each status date. On large projects the authors recommend formal risk reviews at the end of concept development (where “project-killer” risks surface), during preliminary design and during final design (construction and contract risks), with interim reviews during construction.

They close with keys to success from NCHRP Report 658. These include: identify risks early and tie contingencies to explicit risks; communicate cost uncertainty as ranges or explicit contingency; assign responsibility for each risk; and monitor threats and opportunities as the way to resolve contingency. They also note that responsibility shared by everyone tends to end up with no one.

For railroad work: Construction monitoring data are the evidence for retiring or escalating geotechnical risks. Link each instrument and test program to the register entries it tests. For example, inclinometer and piezometer readings during staged fill test the “foundation instability” risk, and proof-rolling and density results test the “unsuitable subgrade quantity” risk. Set the threshold that would trigger the planned response. Report contingency drawdown against those same entries at each progress meeting, so the railroad can see that the reserve is being spent on risks that actually occurred or released as they are retired, not absorbed by unrelated changes.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 149–150, 164–168. Summarized and paraphrased. Full reference under Supplemental Sources.

15.15 Construction Monitoring Checklist

Checklist · Part VII · Stabilization Methods

Construction Monitoring Checklist

Pre-Construction0 of 9
During Construction0 of 10
Post-Construction0 of 8
Ticks are saved in this browser.
Plain text version

Pre-Construction

  • [ ] Pre-construction meeting held; geotechnical inspector role vs. railroad inspector role defined
  • [ ] RWP certification obtained for all field personnel (correct client railroad certification; see Introduction Table)
  • [ ] Nuclear gauge licensed; operator radiation certification current
  • [ ] Modified Proctor reference tests (γ_d,max, w_opt) completed for all fill materials before construction begins
  • [ ] Trigger levels defined in writing and signed by geotechnical engineer
  • [ ] Monitoring instruments installed and baseline readings recorded (minimum 3 consecutive readings over 1 week before construction)
  • [ ] Automated datalogger programmed and communication verified
  • [ ] Pile driving equipment inspection: hammer type, rated energy, leads, and cushion condition
  • [ ] WEAP analysis completed; driving criterion established and submitted to railroad engineer

During Construction

  • [ ] Compaction test performed at required frequency; failing tests reworked and retested same day
  • [ ] Proof rolling performed on each subgrade lift; soft areas flagged and overexcavated
  • [ ] PDA monitoring performed on required percentage of piles; ETR checked at each blow
  • [ ] Pile driving log completed for every pile
  • [ ] Settlement plates read per Table 15-2 schedule; data plotted same day
  • [ ] Piezometers read per schedule; r_u calculated; Alert/Action evaluated each reading
  • [ ] Inclinometers read per schedule; deflection profiles updated
  • [ ] Daily field report submitted within 24 hours (including weekends during active filling)
  • [ ] Any Alert or Action trigger: written notification issued within 1 hour; filling suspended if required
  • [ ] Photographs taken at each inspection visit; GPS-referenced; filed to project folder

Post-Construction

  • [ ] Final compaction summary table prepared (all test results, locations, pass/fail)
  • [ ] Pile installation summary table prepared (all piles: location, tip elevation, blow count, capacity)
  • [ ] CAPWAP analyses completed for all PDA-monitored piles; results submitted
  • [ ] Static load test results analyzed (Davisson method); Q_allow confirmed
  • [ ] Settlement and piezometer data plotted through end of monitoring period
  • [ ] Construction monitoring report submitted to railroad project engineer
  • [ ] PE seal on monitoring report (required by CSXT, NSR, UPRR, BNSF, CPKC, Amtrak, CN)
  • [ ] All instrument casings located, documented, and protected (or abandoned per railroad protocol)
15.16 Cross-Reference Table
TopicSee Also
Pile capacity design (static analysis)Chapter 11
Embankment settlement during constructionChapter 12
Staged construction slope stabilityChapter 13
PVD design for staged constructionChapter 17
Subgrade compaction specificationChapter 18
Retaining wall construction monitoringChapter 16
Geotechnical Special Provisions (construction)Appendix C
Final report construction monitoring sectionAppendix E
Lab testing for reference ProctorChapter 10
15.17 Practice Questions

Q1. A nuclear gauge reads WD = 135.8 pcf and MC = 9.5% on a compacted embankment fill. The Modified Proctor reference is γ_d,max = 130.2 pcf. Calculate: (a) γ_d,field, (b) RC, and (c) does this pass UPRR's 92% compaction requirement?

Answer:

  • (a) γ_d,field = 135.8 / (1 + 0.095) = 135.8 / 1.095 = 124.0 pcf
  • (b) RC = (124.0 / 130.2) × 100% = 95.2%
  • (c) 95.2% > 92% → PASS ✓

Q2. A 12-in. diameter concrete pile (E = 57,000√4,500 psi = 3,824,000 psi; A = 113.1 in.²; L = 60 ft) is tested using ASTM D1143. At Q = 300 kips, total measured settlement is 0.68 in. Calculate the Davisson offset limit and determine if failure has occurred.

Answer: Davisson offset: Δ_failure = (Q × L) / (A × E) + D/120 + 0.15

= (300,000 lb × 60 ft × 12 in./ft) / (113.1 × 3,824,000) + 12/120 + 0.15

= (216,000,000) / (432,754,400) + 0.10 + 0.15

= 0.499 + 0.10 + 0.15 = 0.749 in.

Measured settlement = 0.68 in. < 0.749 in. → Failure has NOT occurred at Q = 300 kips. Continue loading.

Q3. A VW piezometer in a staged construction project reads R = 5,280,000 (Hz²) and R₀ = 5,210,000 (Hz²). Gauge factor G = 0.0015 psi/digit; temperature correction is negligible. New fill added in the last 24 hours: H = 6 ft, γ_fill = 120 pcf. (a) Calculate Δu. (b) Calculate σ_v from the new fill. (c) Calculate r_u. (d) Is filling safe to continue?

Answer:

  • (a) Δu = G × (R − R₀) = 0.0015 × (5,280,000 − 5,210,000) = 0.0015 × 70,000 = 105 psi = 15,120 psf
  • (b) σ_v = 120 × 6 = 720 psf
  • (c) r_u = 15,120 / 720 = 21.0 — this is unreasonably large, indicating the piezometer is reading a legacy excess pressure from prior fills (Δu includes cumulative excess pressure, not just the new fill). Compare Δu to the total σ_v from all fills above the piezometer. If piezometer is measuring total excess: r_u must be evaluated against total σ_v from all fill, not just last lift. If r_u (total) > 0.50: suspend filling.
  • (d) Cannot determine solely from new fill σ_v. Evaluate r_u = Δu / σ_v(total above instrument). This example illustrates that r_u must always be computed against total vertical stress from all fill, not just the most recent lift.

Q4. An inclinometer casing shows the following cumulative deflections (A-direction, positive toward fill) over three consecutive weekly readings: Week 1: 0.15 in., Week 2: 0.38 in., Week 3: 0.65 in. (a) Calculate the weekly incremental movements. (b) Do any weeks trigger the Action level? (c) What action is required?

Answer:

  • (a) Week 1→2: 0.38 − 0.15 = 0.23 in./week; Week 2→3: 0.65 − 0.38 = 0.27 in./week
  • (b) Alert threshold = 0.25 in./7 days; Action = 0.50 in./7 days. Week 2→3: 0.27 in. > 0.25 in. → Alert level triggered. Neither week exceeds 0.50 in./week → Action level not yet triggered.
  • (c) Alert response: notify geotechnical engineer immediately; increase reading frequency to daily; evaluate slope stability with current conditions. Do not yet suspend construction but be prepared to escalate to Action level if daily readings show continued acceleration.

Q5. A proof roll of prepared subgrade identifies two soft spots at Sta. 185+50 and Sta. 186+20 where rutting exceeds ½ in. Nuclear gauge tests at these locations give RC = 88.2% and RC = 86.5% vs. BNSF's 92% minimum. (a) What is the corrective action? (b) After rework, the re-test gives γ_d,field = 126.8 pcf and γ_d,max = 133.5 pcf. Does this pass?

Answer:

  • (a) Overexcavate soft material to bottom of soft zone (confirmed by hand penetrometer ≥ 4.5 tsf or nuclear gauge re-test showing RC ≥ 92% at depth). Backfill with approved borrow material in 6-in. loose lifts. Compact each lift with approved equipment. Retest each lift with nuclear gauge before placing next lift. Do not place next fill layer until RC ≥ 92% on all reworked areas.
  • (b) RC = (126.8 / 133.5) × 100% = 95.0% ≥ 92% → PASS ✓. Document rework in daily field report; note original failing tests, corrective action taken, and passing retest results.
15.18 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental Sources.

Case Study 15.18.1 — Field moisture ratios behind 5,649 passing density tests
Case study · Look (2023) §7.8

Related section: 15.2 Compaction Testing

Look examined 5,649 compaction results, mainly low- to medium-plasticity material, all meeting a 95% density ratio target. Placement moisture was mostly dry of optimum:

  • below 90% of OMC: 50.9% of results
  • 90%–110% of OMC: 45.7%
  • above 110% of OMC: 3.4%

The median was 90% of OMC, with a ±1 standard deviation range of 75%–103%. Heavy equipment has its own “optimum” dry of laboratory OMC because it delivers so much energy. For 279 tests on high-quality base material (CBR 45), the median density was 103% of MDD at a median moisture of only 63% of OMC.

Laboratory OMC is not a requirement for reaching density in the field. It ignores both the equipment used and the moisture the material will reach in service.

For railroad work: on embankment and subgrade work, a density pass with heavy rollers dry of OMC is common. Where the fill is a plastic clay that will wet up afterwards, see the expansive-clay case under Chapter 3, §3.2.

Distribution of field moisture ratio (MC/OMC) for 5,649 compaction tests; median 0.90.
Figure 15-LK1. Distribution of field moisture ratio (MC/OMC) for 5,649 compaction tests; median 0.90. Source: Look (2023), Figure 7.8-2, p. 231.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §7.8, pp. 228–230. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Case Study 15.18.2 — Sinkhole beside a piling rig on a sound working platform
Case study · Look (2023) §3.6

Related section: 15.4 Pile Installation Monitoring

A temporary liner was socketed to the top of rock for a bored pile. While soil was being extracted from inside the liner, a sinkhole opened next to it: bedrock dipped at depth, the liner was embedded unevenly, and material caved in under the edge. The piling rig and the site supervisor were right beside the liner. The operator reversed the rig and the supervisor stepped away in under a minute, and nobody was hurt.

The platform itself was correctly designed; no working platform can bridge a void of this kind. Look draws three points from it: rig operators must be ready to act without notice, so phones should be restricted in critical areas; old trenches and services should be marked and avoided; and instrumentation (survey, inclinometers, extensometers, settlement gauges, piezometers, earth pressure cells) gives early warning, and should be mandatory where the factor of safety is 1.2 or less. Offset distances of about 6.6 ft, or three times the track width of tracked plant, should be kept from any sloping edge.

For railroad work: bridge piling next to live track adds train surcharge and vibration to the same mechanism. Casing embedment on sloping rock should be confirmed, and the exclusion zone around an open casing should be part of the track-protection briefing.

Working platform adequate, but the temporary pile casing had non-uniform fixity on inclined bedrock.
Figure 15-LK2. Working platform adequate, but the temporary pile casing had non-uniform fixity on inclined bedrock. Source: Look (2023), Figure 3.7-1a, p. 89.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §3.6, pp. 88–90. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

  • ASTM D6938, D1556, D698, D1557, D2216 (compaction and field density)
  • ASTM D1143, D4945 (pile load and dynamic testing)
  • FHWA NHI-05-042, Design and Construction of Driven Pile Foundations
  • USACE EM 1110-2-1901
  • AREMA MRE Chapters 1 and 8
  • Client railroad engineering standards as cited in the text (CSXT, NSR, UPRR, BNSF, CPKC, CN, Amtrak, G&W)

Supplemental sources (LEVI Library)

  • Adam, D. (2007). “Roller-integrated Continuous Compaction Control (CCC): Technical Contractual Provisions & Recommendations.” In Gomes Correia, A., Momoya, Y. and Tatsuoka, F. (eds.), Design and Construction of Pavements and Rail Tracks. Taylor & Francis/Balkema
  • SHRP2 R02 / GeoTechTools (2012). Intelligent Compaction — technology fact sheet
  • Stark, T. D., Thompson, H. B., Sussmann, T. R., Bruzek, R. and Banister, R. (2021). “Long-Term Field Monitoring of Fouled Ballast.” AREMA 2021 Annual Conference
  • Bankston, A. (BNSF) and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve BNSF’s Ballast Maintenance Planning.” AREMA 2021 Annual Conference
  • U.S. Army Corps of Engineers (1997). Pile Driving Equipment. Engineering Instructions EI 02G001
  • Swan, C. C. Field Estimates of Pile Capacities, 53:139 Foundation Engineering supplemental notes. The University of Iowa
  • Hannigan, P. J. et al. (2006). Design and Construction of Driven Pile Foundations. FHWA NHI-05-042
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §3.6, §7.8

File locations for these documents are listed under Supplemental Sources — LEVI Library.

Project management sources

  • American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE
  • Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold
  • Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press
  • Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]
  • Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons
  • Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill
  • Anglin, G. (2020). Introduction to Estimating, Plan Reading and Construction Techniques. Abingdon: Routledge
  • Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing
  • Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons
Supplemental Sources — LEVI Library

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After UFC 4-860-01FA (2004)” draw on item S10 and are rewritten for railroad clients. Blocks marked “After Selig & Waters (1994)” summarize item S11 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Adam, D. (2007). “Roller-integrated Continuous Compaction Control (CCC): Technical Contractual Provisions & Recommendations.” In Gomes Correia, A., Momoya, Y. and Tatsuoka, F. (eds.), Design and Construction of Pavements and Rail Tracks. Taylor & Francis/Balkema
  2. SHRP2 R02 / GeoTechTools (2012). Intelligent Compaction — technology fact sheet
  3. Stark, T. D., Thompson, H. B., Sussmann, T. R., Bruzek, R. and Banister, R. (2021). “Long-Term Field Monitoring of Fouled Ballast.” AREMA 2021 Annual Conference
  4. Bankston, A. (BNSF) and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve BNSF’s Ballast Maintenance Planning.” AREMA 2021 Annual Conference
  5. U.S. Army Corps of Engineers (1997). Pile Driving Equipment. Engineering Instructions EI 02G001
  6. Swan, C. C. Field Estimates of Pile Capacities, 53:139 Foundation Engineering supplemental notes. The University of Iowa
  7. Hannigan, P. J. et al. (2006). Design and Construction of Driven Pile Foundations. FHWA NHI-05-042
  8. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)
  9. Benesch. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. Colwell
  10. U.S. Army Corps of Engineers, Naval Facilities Engineering Command and Air Force Civil Engineer Support Agency (2004). UFC 4-860-01FA, Railroad Design and Rehabilitation. Unified Facilities Criteria, 16 January 2004 (supersedes TI 850-02, 1 March 2000); approved for public release, distribution unlimited. Used on this page: ch. 9 (§§4, 5)
  11. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 9, 11, 14 and 15
  12. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §3.6, §7.8
  13. American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE. Used on this page for project-management material
  14. Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold. Used on this page for project-management material
  15. Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press. Used on this page for project-management material
  16. Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]. Used on this page for project-management material
  17. Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management material
  18. Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill. Used on this page for project-management material
  19. Anglin, G. (2020). Introduction to Estimating, Plan Reading and Construction Techniques. Abingdon: Routledge. Used on this page for project-management material
  20. Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing. Used on this page for project-management material
  21. Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management material
← Previous · Part VI Chapter 14 — Seismic Hazard and Liquefaction
Next · Part VII → Chapter 16 — Retaining Structures