Railway Ground Hazard Risk Management · Part IV · Failure Mechanisms (Triggers)
Sections · click a car to open it

Chapter 4 — Failure Mechanisms and Triggers

How track-support and ground-hazard failures develop, the conditions that set them up, and the events that set them off.
Authors: Daniel P. Colwell and Mario Ruel

Railway Ground Hazard Risk Management

Primary sources: Selig, E.T. and Waters, J.M. (1994), Track Geotechnology and Substructure Management; Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016), Railway Geotechnics; Cruden, D.M. and Varnes, D.J. (1996), Landslide Types and Processes, TRB Special Report 247; Hungr, O., Leroueil, S. and Picarelli, L. (2014), The Varnes classification of landslide types, an update, Landslides 11; Caine, N. (1980), The rainfall intensity–duration control of shallow landslides and debris flows, Geografiska Annaler 62A; FHWA HEC-18; FRA 49 CFR Part 213; and Chapters 1, 2, 3 and 13 of this manual.

New chapter drafted September 2026 for the Railway Ground Hazard Risk Management reorganization. Verify client-specific values against the governing client standard before use on a project.

Apps for this Chapter3
4.0 Executive Summary

Chapter 1 classifies railway ground hazards by what they are: landslide, hydraulic erosion and subsidence. This chapter explains how they happen. For each family of hazard it describes the physical failure mechanism, the conditions that make a site susceptible, and the triggers that turn susceptibility into an event.

The distinction is practical. Mitigation that addresses only the trigger (for example, a rain-based slow order) manages exposure but leaves the hazard in place. Mitigation that addresses the mechanism (drainage, buttressing, subgrade replacement) reduces the hazard itself. Correctly diagnosing the mechanism is therefore the step that controls whether repair money solves the problem or only treats the symptom. Chapter 1 makes this point about "muddy track": identical surface symptoms can come from quite different root causes.

Key outputs: a mechanism–condition–trigger framework (Section 4.1); mechanism tables for track substructure, embankments and slopes, hydraulic, subsidence and seismic hazards (Sections 4.2–4.6); a trigger inventory (Section 4.7); the use of rainfall thresholds in weather-based operating protocols (Section 4.8); a symptom-to-mechanism diagnostic table (Section 4.9); and monitoring indicators (Section 4.10).

4.1 Mechanism, Condition and Trigger

Ground failures rarely have a single cause. It is useful to separate three groups of factors:

FactorDefinitionRailroad ExamplesCan the Railroad Change It?
Predisposing conditionsInherent site characteristics that make failure possibleSoft or sensitive clay, steep slope, fouled ballast over plastic clay, soluble bedrock, loose saturated sandOnly by engineering works (improvement, regrading, replacement)
Preparatory (progressive) factorsProcesses that reduce the margin of safety over timeBallast fouling, subgrade softening, toe erosion, weathering, rising tonnage, culvert corrosion, creepYes — through maintenance, drainage and inspection
TriggersThe event that tips a marginal site into failureIntense or prolonged rainfall, snowmelt, flood, rapid drawdown, earthquake, toe excavation, blocked culvertRarely — but exposure can be managed (slow orders, patrols, warning systems)

The factor of safety concept from Chapter 1 ties these together. Predisposing conditions set the starting factor of safety, preparatory factors erode it, and the trigger is whatever finally pushes it below 1.0. A site with a large margin survives the same storm that fails a marginal site next to it. This is why a risk program targets sites whose margin is being eroded, not just sites that have already failed.

Project management · Bissonette (2016)

Cause–Risk–Effect Statements (Risk Metalanguage)

Bissonette separates three things that risk registers often blur. A cause is a fact or existing condition. A risk is an uncertain event that may or may not happen. An effect is the possible impact on one or more project objectives (schedule, cost, scope or quality). To keep them apart he uses a fixed sentence form, or risk metalanguage:

As a result of <CAUSE>, <RISK> may occur, which will lead to <EFFECT>.

The short version for a register title is “<RISK> due to <CAUSE>.” One of his examples reads: “As a result of more than expected test failures, more design/build/test cycles may occur, which will lead to schedule delays and added project costs.” Its register title is “More design/build/test cycles due to more than expected test failures.” Writing every risk this way shows which part can be measured or controlled, whether the cause or the event. It also indicates which objective the impact rating should refer to. The same form keeps a known condition, which is a fact to design for, from being logged as though it were uncertain.

For railroad work: The metalanguage lines up with this chapter’s condition–mechanism–trigger framework. The cause is the condition plus the trigger, the risk is the mechanism being activated, and the effect is the consequence to track or to the project. For example: “As a result of a high-plasticity clay subgrade with a clogged ditch line (condition) and sustained wet-season rainfall (trigger), progressive shear and heave of the subgrade may occur (mechanism), which will lead to repeated surfacing, a slow order and possible mud-pumping derailment risk (effect).” The register title becomes “Subgrade shear failure due to saturated CH subgrade and blocked drainage.” Writing hazard and project risks in this form makes plain which field observation would confirm the cause and which treatment targets the trigger. It also makes the risk register consistent with the diagnostic tables in this chapter.

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 3, “Causes Versus Risks” (unpaginated e-book; PDF pp. 38–40). Summarized and paraphrased. Full reference under Supplemental Sources.

4.2 Track Substructure Failure Mechanisms

These mechanisms act within the ballast, subballast and subgrade (Chapter 2) and the upper part of the embankment (Chapter 3). They account for most of what track patrols encounter day to day: the "subsidence" category of Chapter 1.

MechanismWhat HappensSusceptible ConditionsField IndicatorsSee
Ballast degradation and foulingParticle breakage and abrasion, plus infiltration of fines, fill voids and reduce drainage and strengthWeak or soft aggregate, heavy tonnage, tamping cycles, wind-blown or spilled finesFouled shoulders, reduced voids, geometry loss after surfacingChapter 2, Section 2.7
Subgrade attrition and mud pumpingWater plus cyclic loading at the ballast–subgrade contact produces a slurry that is pumped into the ballastPlastic fine-grained subgrade, no or inadequate subballast, poor drainageMud at tie ends and in cribs, "white spots" on shoulders, rapid surface defectsChapter 2, Section 2.5
Progressive shear failureRepeated stress near the subgrade strength remolds the soil and squeezes it laterally beneath the tiesSoft, wet fine-grained subgrade; thin granular layerHeave of the ballast shoulder or ditch side ("subgrade squeeze"), ties hanging, recurring cross-level defectsChapter 2, Section 2.5
Excessive cumulative plastic deformationGradual accumulation of permanent strain under millions of load cycles forms ballast pockets and troughsFine-grained subgrade with moderate strength; heavy axle loadsBallast pockets in trench sections; gradual long-wave settlementChapter 2, Section 2.5
Consolidation settlementVolume decrease of saturated clay and organic soil under sustained loadSoft clay or peat foundations; new fill, raises or a second trackLong-wave settlement, often continuing for years after constructionChapter 12
Frost heave and thaw weakeningIce lens growth heaves track in winter; excess water on thaw softens the subgradeFrost-susceptible silts and silty clays, available water, freezing climateSeasonal differential heave, spring pumping and soft spotsChapter 2, Section 2.5; Chapter 18
Swell and shrinkageMoisture change in expansive clay causes volume changeHigh-plasticity clay, clay shale in cuts, seasonal wetting and dryingSeasonal geometry cycling, shoulder cracking in dry periodsChapters 3, 8
Cyclic softening ("subgrade dynamic liquefaction")Pore pressure buildup under repeated loading in saturated low-plasticity silt causes loss of strengthSaturated silts, poor drainageSudden loss of support in wet periods, mud boilsChapters 1, 14

Reading the substructure through maintenance demand

Profillidis uses a maintenance coefficient k = I / Im, where I is the annual number of maintenance sessions on a section and Im the average for track of the same age, UIC group and axle load. k = 1 is average; k = 0.5 is good; on poor subgrade k can reach 10. Maintenance hours rise steeply with k and with years since renewal (Figure 4-1). He uses k to judge whether the track bed is adequately sized:

Table 4-1. Assessment of track-bed sizing from the maintenance coefficient k
kAssessment
k < 1Correct dimensioning
1 < k < 2.5Track-bed structures slightly under-dimensioned
2.5 < k < 5Track-bed structures under-dimensioned; poor functioning of drainage
k > 5Renewal and strengthening of track-bed structures necessary

When I passes a threshold, geometry can no longer be held by surfacing alone and the remedy is to reduce k, mainly by thickening the track bed. Applied with Dormon’s rule, subgrade stress also depends on maintenance: traffic between sessions scales with T/k, so tracks with different k values load the subgrade differently. For a ground-hazard program the practical point is that a segment needing repeated spot surfacing (high k) is evidence of a substructure mechanism, and that evidence lives in maintenance records.

Figures · click to zoom

Figure 4-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.
Figure 4-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.

After Profillidis (2014), §9.9, Table 9.5, Fig. 9.6. Full reference under Supplemental Sources.

Ballast or subgrade: which one sets the maintenance cycle?

Short-term versus long-term settlement. On most track, ballast causes most of the settlement between surfacings, both average and differential. This is the short-term component. The subgrade adds a long-term component that builds slowly over decades of traffic. Ballast governs only when three conditions hold:

  • A filter or separation layer is present.
  • The subgrade is strong enough.
  • Surface drainage is good.

If any of these is missing, the subgrade dictates the maintenance cycle.

Why track subgrade fails by creep, not by sudden collapse. Train loading on the subgrade does not reverse the direction of shear stress. Under that kind of loading, pore pressure rises to a limit and failure comes as permanent strain accumulating at an increasing rate. Cyclic strain stays small. Two factors make it worse:

  • Static shear stress, such as beneath an embankment shoulder or slope, magnifies the plastic strain caused by traffic.
  • Subgrade saturation changes with the seasons, so the same section can perform differently in spring and in autumn.

After Selig & Waters (1994), chs. 3, 4 and 8. Full reference under Supplemental Sources.

4.3 Embankment and Slope Failure Mechanisms

Classify slope movements by material (rock, debris, earth) and movement type (fall, topple, slide, spread, flow), following Cruden and Varnes (1996) as adopted in Chapter 1. The mechanism determines the analysis method (Chapter 13) and the likely warning time.

MechanismTypical Railroad SettingWarning SignsWarning Time
Rotational slide (slump)Embankments and cuts in clay; river-bank fillsCrest cracks parallel to track, back-tilted blocks, bulging toeDays to months; often progressive
Translational slideFill over sloping bedrock or weak planar layer; colluviumTension cracks upslope, displaced ditch, leaning polesHours to weeks
Earthflow and retrogressive slideSensitive and quick clays in river valleysOften little; small initial slide at the bankMinutes to hours once started
Lateral spreadSensitive clay or liquefiable layers near free facesGround cracking, bulging toward channelRapid
Debris flowSteep channels above track; source areas often out of sightAccumulated debris in upper channel, burn scars, intense rainMinutes; can reach track 1–2 miles from source (Chapter 1)
Rockfall and toppleRock cuts and natural rock facesFresh debris in ditch, open joints, freeze-thaw season activitySeconds
CreepClay slopes and colluviumCurved tree trunks, slow drift of track alignment and structuresYears; may accelerate to sliding
Shallow sloughing and surface erosionSteep, unvegetated fill slopesRills and gullies, slumped surface layerStorm-dependent
Embankment spreading or foundation squeezeEmbankment on soft foundationToe heave, lateral displacement, crest settlementWeeks to months

Mass-movement types and internal-erosion collapse

Mass movements are classified by rate against water content, from extremely slow dry creep through earthflows and rotational or translational slides to extremely rapid rockfalls, debris flows and debris avalanches in saturated ground. An earthflow has a characteristic hourglass shape. Creep is spotted by its effects: curved trunks, bent fences and tilted poles.

Embankment collapse by internal erosion (rated Severe) is the hidden mode. Water moves through the fill or overflows through buried rock drains, carrying soil out and leaving voids until the surface collapses. In one case a culvert roof failed about 45 ft inside the fill and produced a sink hole up to 70 ft deep. In another, a 6.5-ft multi-plate culvert with a rusted-out invert let water erode beneath it, causing outlet and toe scour, an over-steepened slope, head-scarp cracks, 14 in. of mainline settlement and 2 in. of lateral deflection.

Figures · click to zoom

Figure 4-7. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.
Figure 4-7. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.
Figure 4-8. Mass-movement classification: rate of movement vs. water content.
Figure 4-8. Mass-movement classification: rate of movement vs. water content.
Figure 4-9. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 4-9. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 4-10. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 4-10. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 4-11. A sink hole forming under the track from internal erosion.
Figure 4-11. A sink hole forming under the track from internal erosion.

After Geotechnology for Railroaders Program, Module 5; §05, §09, §14. Full reference under Supplemental Sources.

Case study: 4.16.1 Slope failures whose consequences left the site (Look 2023), in §4.16 Case Studies.

4.4 Hydraulic Failure Mechanisms

Chapter 1 splits hydraulic erosion into surface-flow and seepage mechanisms. They fail differently and call for different controls.

4.4.1 Surface-Flow Mechanisms
  • Scour at bridge piers and abutments: local scour around obstructions, contraction scour where the channel is narrowed, and long-term degradation of the bed. Evaluate per FHWA HEC-18 (Chapter 3, Section 3.7).
  • Bank and toe erosion where the alignment parallels a river, lake or coast. This removes toe support and leads to slope failure (Section 4.3).
  • Overtopping and washout when a culvert or bridge opening is exceeded or blocked. Water flowing over the embankment erodes the downstream face and can remove the fill entirely.
  • Beaver dam failure releasing stored water as a surge, a recognized washout cause in wooded territory (Chapter 1).
4.4.2 Seepage (Internal) Mechanisms
  • Piping and internal erosion where water flows through or beneath an embankment with enough gradient to move particles. This is especially common along the outside of culvert barrels and through fills ponded on one side.
  • Seepage forces and uplift reducing effective stress in slopes and at the toe.
  • Rapid drawdown when flood water recedes faster than pore pressure in the embankment can dissipate, leaving the saturated slope without the stabilizing water load on its face.

Underestimated peak flows

Undersized drainage is a hydraulic mechanism in its own right. Profillidis gives the U.S. Soil Conservation Service method based on Fuller’s formula for the peak flow from a catchment of A km² for a return period of T years:

Qmax = Q1 · (1 + 0.8 log T) · (1 + 2.66 / A0.3),   with Q1 = 1.8 · A0.8 (m³/s)

His worked values: A = 10 km², T = 10 years gives Q1 = 11.6 and Qmax = 47.7 m³/s; A = 15 km², T = 20 years gives 15.7 and 69.9 m³/s. He cautions that such semi-empirical formulas must be checked against measured data. On the TGV Méditerranée, observed extreme runoff was about twice the top of the predicted range (Chapter 3, §3.5). He argues that increasing rainfall intensity calls for return periods far longer than the traditional 50–100 years, up to 1,000 years, with the probable maximum flood as the reference event.

After Profillidis (2014), §9.14.2–9.14.3, Eq. 9.11. Full reference under Supplemental Sources.

Scour: why it is invisible from the hi-rail

Local scour forms horseshoe and wake vortices around piers and abutments; contraction scour deepens the channel through a constricted opening. Both can undermine a foundation well below the water surface. Away from bridges, any bend near the track is scour-critical: the outer radius scours while the inner radius deposits. Banks migrate as the stream undercuts and collapses them. Attack migration before it passes a 2:1 intercept slope with the track, because cost rises steeply with delay, and get engineering help, since riprap alone may not be enough.

Signals stay green when track is undermined by side scour or washed out. Peak flow can arrive after the rain stops, and a long moderate storm can do more damage than a short intense one. Get off the hi-rail and walk the bank at scour-critical locations. AREMA countermeasures (after FHWA) are riprap at piers and abutments, guide banks, spurs and revetments, with riprap always placed from the toe upward.

Figures · click to zoom

Figure 4-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 4-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 4-13. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 4-13. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 4-14. Bank migration toward the railroad.
Figure 4-14. Bank migration toward the railroad.
Figure 4-15. A trestle span that did not survive the flood.
Figure 4-15. A trestle span that did not survive the flood.
Figure 4-16. A trestle left hanging after the approach embankment washed out.
Figure 4-16. A trestle left hanging after the approach embankment washed out.

After Geotechnology for Railroaders Program, Module 6.3; §02–05. Full reference under Supplemental Sources.

Differential head, beaver dams and rapid drawdown

When the water level on one side of an embankment exceeds the other by more than about 6 ft, flow is forced beneath the track. Within days, depending on the fill, wet spots appear at the downhill toe. Dirty or milky seepage and sand fans at the outlet mean soil is being carried out and cavities are forming. In spring, a culvert plugged with ice is the most frequent cause.

Beaver dams in culverts and ditches cause about 80% of beaver trouble but less than 10% of the risk. Dams far uphill, sometimes 100 ft or more above the track and outside railway property, are about 20% of problems but carry the highest risk. The 1992 Nakina derailment, in which two employees were killed, followed a rapid drawdown of a lake after a dam failure and led to the formal Beaver Activity Hazard Assessment (BAHA) program. The program rates watersheds and dams 1–5 and combines them into a global score:

Table 4-2. BAHA global risk matrix (watershed rating × worst dam rating, with additional severe dams)
WatershedDam 1Dam 2Dam 3Dam 4Dam 5+1 severe+2 severe+3 severe
100000000
200012468
3002615304661
40282664128192256
5052580195391586781

Never use explosives on a beaver dam or culvert plug. In one case a dynamited dam overloaded a 3-ft culvert and more than 300 ft of a 60-ft-high embankment failed, with the water travelling through old permeable fill from a buried timber bridge. After any high water is drawn down, the embankment is least stable for about 12–24 hours, while the confining water is gone but the fill is still saturated and seepage reverses. Beaver ponds are protected fish habitat under the Canadian Fisheries Act; permits are required, and penalties can reach $1,000,000 and imprisonment for individuals.

Figures · click to zoom

Figure 4-17. High differential water level driving seepage beneath the track.
Figure 4-17. High differential water level driving seepage beneath the track.
Figure 4-18. Seepage under the track creating internal voids.
Figure 4-18. Seepage under the track creating internal voids.
Figure 4-19. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 4-19. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 4-20. Partial culvert obstruction by beaver debris.
Figure 4-20. Partial culvert obstruction by beaver debris.
Figure 4-21. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Figure 4-21. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Figure 4-22. After the dynamited-dam failure: more than 300 ft of bank removed.
Figure 4-22. After the dynamited-dam failure: more than 300 ft of bank removed.

After Geotechnology for Railroaders Program, Module 6.5, Module 7.1, Module 4; Module 6.5 §02–06; Module 7.1 §04, §06. Full reference under Supplemental Sources.

4.5 Subsidence and Collapse Mechanisms

Chapter 1 separates progressive settlement from sudden collapse. The mechanisms below produce sudden collapse. They are the most dangerous for train operations because warning time is short.

MechanismProcessWhere to Expect It
Karst sinkholesSoil ravels into solution cavities in limestone, dolomite or gypsum until the overlying arch collapses (cover-collapse) or sags (cover-subsidence)Karst regions; often triggered by water-table changes or concentrated drainage
Mine subsidenceCollapse of underground workings producing troughs (sag) or pitsAbandoned coal and mineral mining districts
HydrocollapseLow-density, dry soils lose their bonding and compress when first wettedLoess and some arid-region alluvium; triggered by new drainage or leaks
Culvert and pipe failureBackfill lost through corroded or separated barrels leaves voids that collapseAging metal culverts; clay tile and masonry drains
Decay of buried timberRotting of buried trestles and cribbing leaves voids in the fillFills built over or around former timber structures
Leaking utilitiesWater and sewer leaks wash fines into the pipe or away along the trenchUtility crossings (Chapter 3, Section 3.9)
Burrowing animalsBurrows provide seepage paths and voids in embankmentsEmbankments near water; flood-control levee analogs
4.6 Seismic Mechanisms

Earthquakes act as triggers for several of the mechanisms above, and they also introduce mechanisms of their own: liquefaction of loose saturated granular soils, lateral spreading toward free faces, cyclic softening of soft clays, and seismically induced slope failures and rockfall. Evaluate these using Chapter 14. After a felt earthquake, the railroad's earthquake notification protocol (Chapter 1, Section 1.8) sets the inspection radius and speed restrictions.

Seismic train-protection thresholds

Profillidis treats earthquakes in two parts: designing structures, track and subgrade for the regional design acceleration (up to about 0.3 g in his text), and protecting trains during an event. For the second, accelerometer sensors in protected housings along the line report to an alarm center:

  • measured acceleration above 0.066 g (2.1 ft/s²): stop traffic immediately;
  • between 1.3 and 2.1 ft/s² (≈ 0.04–0.066 g): reduce permitted speeds;
  • an alarm is issued when three consecutive sensors report within 5 seconds;
  • reliability target: no more than one false alarm in 30 years.

These values describe one European system and can be compared with client post-earthquake inspection protocols (Chapter 14).

After Profillidis (2014), §9.17. Full reference under Supplemental Sources.

What earthquakes have done to track

More than 1,500 seismic events are recorded in Canada each year, with a significant one every two to five years. Energy travels farther through dense eastern Precambrian rock. The 1935 Temiskaming M6.2 earthquake caused an embankment failure more than 220 mi from the epicenter. The 1988 Saguenay M~6.3 event temporarily liquefied a muskeg zone and triggered nine slope failures; derailments were avoided only because the track was closed. In a 2010 event, straight rail was left kinked into S-curves, buckled at ties and disturbed at culverts, damage not visible from a moving train. Post-event inspection must cover track and roadbed, drainage, culverts, retaining walls, tunnels, overpasses, bridges and approaches, adjacent buildings, fiber and utilities, and signals. Response criteria are in Chapter 14.

Figures · click to zoom

Figure 4-23. Track buckled into an S-curve by a 2010 earthquake.
Figure 4-23. Track buckled into an S-curve by a 2010 earthquake.
Figure 4-24. A kink in the rail at a culvert crossing.
Figure 4-24. A kink in the rail at a culvert crossing.
Figure 4-25. A slope failure in a muskeg zone, of the type triggered at Saguenay in 1988.
Figure 4-25. A slope failure in a muskeg zone, of the type triggered at Saguenay in 1988.

After Geotechnology for Railroaders Program, Module 7.3; §02, §05–06. Full reference under Supplemental Sources.

4.7 Trigger Inventory

Most failures are set off by water. Load and human activity come next.

TriggerHow It ActsMechanisms Most Affected
Intense short-duration rainfallSurface runoff, erosion, rapid rise of perched waterDebris flow, shallow slides, washout, scour
Prolonged rainfall and antecedent moistureRaises groundwater and pore pressure over days to weeksDeep-seated slides, subgrade softening, pumping
Snowmelt and rain-on-snowLarge water input on saturated or frozen groundSlides, washouts, thaw weakening
Freeze-thaw cyclesIce wedging in rock; ice lens growth and melt in soilRockfall, frost heave, spring pumping
Flood and high waterScour, overtopping, saturation of embankmentsScour, washout, piping
Rapid drawdownLoss of external water support on a saturated slopeSlides of river-bank embankments
Blocked drainagePonding against embankments; water forced through fillPiping, slides, subgrade softening
Increased loadHeavier axle loads, higher tonnage or speed, new track, stockpiles near crestProgressive shear, cumulative deformation, slides
Construction and maintenanceToe excavation, ditch cleaning that undercuts slopes, undercutting, vegetation removal, grade raisesSlides, erosion, settlement
EarthquakeCyclic loading and inertial forcesLiquefaction, lateral spread, slides, rockfall
WildfireLoss of vegetation and water-repellent soils increase runoff for several seasonsDebris flow, erosion
Beaver activityImpounds water against fills; dams fail in stormsWashout, piping
Utility leaks and miningLocalized water or loss of supportSinkholes, collapse, settlement

Climate trends matter for risk evaluation. Where records show more frequent intense rainfall, return-period assumptions behind existing drainage and past stability evaluations may no longer hold. Note this in the risk evaluation (Chapter 1, Section 1.7) rather than assuming past performance will continue.

Triggers and the four don’ts

A trigger is an external stimulus that causes a near-immediate landslide or washout by raising stress, reducing strength or removing soil: intense or persistent rain, floods, high stream flow, rapid snowmelt, earthquakes, elevated seepage, water-level change, freeze–thaw and rapid drawdown. Weather is the most common trigger, and antecedent wetness matters as much as the storm. Underlying causes are geological (weak, sensitive, weathered or jointed materials, adverse bedding, permeability contrasts), morphological (toe erosion, piping, crest loading, vegetation loss, thaw) and human (toe excavation, crest loading, reservoir drawdown, deforestation, irrigation, vibration, leaking utilities).

Water weakens slopes in five ways: it adds weight in the voids, is absorbed by clay minerals with loss of strength, dissolves cement between grains, erodes loose material, and becomes trapped under pressure. A failure surface balances driving and resisting mass, and four actions tip it the wrong way: steepening the slope, removing support at the toe, adding mass high on the slope, and allowing bad drainage to continue.

Figures · click to zoom

Figure 4-26. Removal of the toe: an access-road cut undercutting the fill.
Figure 4-26. Removal of the toe: an access-road cut undercutting the fill.
Figure 4-27. Oversteepening and overloading with fill placed on the shoulder.
Figure 4-27. Oversteepening and overloading with fill placed on the shoulder.
Figure 4-28. Improved slope geometry correcting the same problem.
Figure 4-28. Improved slope geometry correcting the same problem.
Figure 4-29. North Vancouver public-education diagram showing nearly every warning sign and cause.
Figure 4-29. North Vancouver public-education diagram showing nearly every warning sign and cause.

After Geotechnology for Railroaders Program, Module 5, Module 6.4; Module 5 §10, §14; Module 6.4 §07. Full reference under Supplemental Sources.

4.8 Rainfall Thresholds and Weather-Based Operating Protocols

Because rainfall is the dominant trigger, many railroads tie patrols, speed restrictions and special inspections to precipitation. FRA 49 CFR 213.239 requires special inspections of track after events such as floods and severe storms that may have damaged track structure. A threshold-based protocol makes that requirement predictable.

4.8.1 Intensity–Duration Thresholds

Empirical rainfall thresholds relate the average intensity I needed to trigger shallow landslides and debris flows to the storm duration D. The widely cited global lower-bound threshold of Caine (1980) is:

Equation 4-1: I = 14.82 × D−0.39

where I = rainfall intensity (mm/hr) and D = duration (hr), valid for roughly 10 minutes to 10 days.

A global threshold is only a starting point. Thresholds should be calibrated for each territory from the railroad's own incident history and rain-gauge records. They should also account for antecedent moisture, since the same storm is far more damaging on saturated ground.

4.8.2 Building a Protocol
  • Identify sites in the ground hazard inventory whose mechanism is rainfall-sensitive (Section 4.7).
  • Assign each a rain gauge or gridded precipitation source and a threshold (intensity, 24-hour and multi-day totals).
  • Define the response for each threshold level: heightened patrol, speed restriction, or hold trains until inspected.
  • Review each season's triggered responses and incidents, and adjust thresholds and site lists.

Declaring an extreme weather event and scaling the response

In the course’s Class I practice, the Regional Chief Engineer declares an extreme weather event for a defined subdivision and mile range. The declaration draws on weather-service forecasts and warnings and on reports from train crews and engineering forces, and is passed to Rail Traffic Control, the General Manager and the Regional Senior VP. Restrictions are decided jointly. They weigh the nature of the event, pre-existing ground conditions, topography and incident history, the quality of the weather information, the recency of patrols (a daylight inspection within four hours counts for more than a night inspection twelve hours old), train frequency, and wayside protection such as slide fences and high-water detectors.

  • Increased patrol frequency.
  • Patrols immediately ahead of each train.
  • Trains on lookout, prepared to stop within one-half the range of vision.
  • Daylight operations only.
  • No new trains into the territory; clear trains to safety.
  • Cessation of operations; move crews to safety.

The flash-flood trigger used across the Prairies and East is more than 1 in./h totaling over 3 in.; elsewhere, 2 in. in 1 h, 3 in. in 2 h, 4 in. in 4 h or 6 in. in 12 h. A double precipitation index plots short-term intensity against cumulative rainfall to define low-risk, speed-restriction and suspension zones. An antecedent rainfall index plots 2-day against 28-day totals over the history of past landslides at a station. In spring, bearing capacity can drop 30–50%.

Figures · click to zoom

Figure 4-30. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.
Figure 4-30. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.
Figure 4-31. Slopes remain stable until rainfall intensity and duration pass a threshold.
Figure 4-31. Slopes remain stable until rainfall intensity and duration pass a threshold.
Figure 4-32. Dry conditions vs. storm conditions with ponding at a blocked culvert.
Figure 4-32. Dry conditions vs. storm conditions with ponding at a blocked culvert.

After Geotechnology for Railroaders Program, Module 7.2, Module 7.1, Module 4; Module 7.2 §03–06; Module 7.1 §07. Full reference under Supplemental Sources.

4.9 Diagnosing the Mechanism from the Symptom

Use this table to move from what the field inspector sees to the most likely mechanisms, and to the investigation that will confirm which one applies.

Observed SymptomLikely MechanismsConfirming Investigation
Recurring surface or cross-level defect at one locationBallast pocket, progressive shear, soft foundation, culvert backfill lossTrench across track, borings, GPR, geometry-car history
Mud at tie ends, fouled shouldersMud pumping, ballast foulingBallast sampling and fouling index, subgrade plasticity, drainage check
Heaved ballast shoulder or ditch sideProgressive shear failure (subgrade squeeze)Trench, field vane or CPT, moisture content
Longitudinal cracks in crest, parallel to trackRotational or translational slide; embankment spreadingInclinometers, piezometers, stability analysis
Bulging toe, seepage or boils at toeSlide in progress; internal erosionPiezometers, seepage mapping, borings at toe
Circular depression or hole near trackSinkhole, pipe or culvert failure, buried timber decayProbing, geophysics, camera inspection of nearby culverts and utilities
Seasonal heave and spring soft spotsFrost heave and thaw weakeningFrost susceptibility testing, groundwater levels
Fresh rock in ditch or on trackRockfall and toppleRock slope mapping, rockfall hazard rating (Chapter 1)
Scour hole or exposed footing at bridgeLocal or contraction scourUnderwater inspection, scour evaluation per HEC-18

Geometry defect types and what drives them

The book defines geometry defects against a theoretical track position averaged over a chord: longitudinal defect (surface or profile), transverse defect (cross-level relative to design cant), horizontal defect (alignment), gauge, and twist (deviation of one of four points on two ties from the plane of the other three, i.e. the change in cross-level per unit length).

  • Longitudinal defect is the most reliable indicator of vertical loading on the track and, with transverse defect, the main driver of maintenance cost. This is where subgrade settlement and pumping appear first.
  • Horizontal defect depends mostly on lateral track effects and rolling-stock behavior, which points toward ballast-section and lateral-resistance issues (Chapter 2, §2.3).
  • Gauge deviations depend mainly on the subgrade and the type of rolling stock.
  • Twist is one of the most frequent causes of derailment, and at speeds below 87 mph it is the main critical safety parameter. Localized differential settlement under one rail, for example at a culvert, a soft spot or a shoulder failure, shows up as twist.

Geometric parameters degrade about 5–15 times faster than mechanical ones (rail, ties, fastenings). On a typical UIC group 4 line, geometry is restored after about 40–50 million tons, while rail lasts 500–600 million tons.

Figures · click to zoom

Figure 4-2. Longitudinal (a), transverse (b) and horizontal (c) track defects. Profillidis Fig. 16.3.
Figure 4-2. Longitudinal (a), transverse (b) and horizontal (c) track defects. Profillidis Fig. 16.3.
Figure 4-3. Track twist: deviation of one point from the plane defined by the other three on successive ties i and i+1. Profillidis Fig. 16.4.
Figure 4-3. Track twist: deviation of one point from the plane defined by the other three on successive ties i and i+1. Profillidis Fig. 16.4.

After Profillidis (2014), §16.2–16.4, Figs. 16.3–16.4. Full reference under Supplemental Sources.

Match the remedy to the cause

Mud on the ballast surface can come from three sources, and each needs a different fix:

  • Subgrade pumping: renew the ballast and add a blanket.
  • Worn ballast: renew the ballast.
  • Spillage from cars: clean the ballast.

Before committing to cleaning or renewal, examine the layers down into the subgrade with trenches, pits or trackbed borings (Chapter 5).

Table 4-SW1. Short-term and long-term remedies by cause (condensed)
CauseShort-term responseLong-term remedy
Ballast and tie wear or attritionAdd ballast depth; tampRenew with more durable ballast
Fouled ballast (breakdown or spillage)Tamp; this delays cleaning only brieflyClean by undercutting or shoulder cleaning
Subgrade attrition and pumping, no subballastClean ballast (temporary)Clean and place a blanket
Subgrade attrition, ballast also worn out—Renew the ballast and place a blanket
Progressive shear failureNo effective short-term fixExcavate and rebuild to the required granular depth, and restore drainage
Ballast pocket holding waterDrain the pocket where possibleReshape the subgrade or reconstruct; provide an outlet

Condensed from the book’s failure-condition and remedy table, which is partly illegible in the source scan. Authors’ wording.

Clues in the geometry record.

  • A sharp rise in the deterioration rate from one cycle to the next flags fouling.
  • Track that settles back to the same profile after each tamp is showing its inherent shape (Chapter 15). Low-lift tamping will not change that shape.

After Selig & Waters (1994), chs. 14 and 15. Full reference under Supplemental Sources.

4.10 Monitoring and Early-Warning Indicators

Monitoring converts an unknown mechanism into a measured one. It also provides warning where mitigation cannot be built right away. Instrument selection, installation and reading frequency are covered in Chapter 15.

IndicatorInstrument or Data SourceMechanism Monitored
Subsurface displacementInclinometers (ASTM D6230), shape arrays, TDR cableSlides, creep, spreading
Pore pressureVibrating-wire piezometers, observation wellsSlides, consolidation, rapid drawdown
SettlementSettlement plates, survey monuments, track geometry-car trendsConsolidation, cumulative deformation, sinkholes
Ground surface changeLiDAR change detection, InSAR, UAV photogrammetrySlides, subsidence, erosion
Track bed conditionGPR surveys (Chapter 2, Section 2.9)Fouling, ballast pockets, wet subgrade
Rockfall and slide detectionSlide fences and detector wires tied to signalsRockfall, debris flow
Rainfall and stream stageRain gauges, stream gauges, weather servicesAll water-triggered mechanisms (Section 4.8)

Track-recording data as an early-warning stream

Recording cars run at fixed intervals: about 3 times a year on main routes, twice a year on intermediate routes and once a year on branch lines. They measure longitudinal, transverse and horizontal defects on a base of about 33 ft and twist on 8–10 ft. At low and medium speeds the absolute (peak and mean) values govern. At higher speeds the standard deviation over 660–980 ft is used as the quality index. Results are ranked by severity and compared with earlier runs and with the limits.

Defects grow quickly until about 2 million tons after maintenance, then slowly and roughly with log T:

me(T) = a1 + a0 · log(T / Tr),    Tr = 2.2×106 tons

Here a1 is the mean settlement at Tr and a0 is the settlement rate per log cycle, 0.079–0.24 in. per decade, depending mainly on subgrade quality (a0/a1 = 0.25–0.70). The standard deviation of longitudinal defects follows the same form with c0 ≈ 0.0039–0.0079 in. per decade. A segment whose fitted a0 or c0 drifts above its neighbors is a candidate for substructure investigation. The sensitive period (about 1–4 months on a UIC group 4 line, 15–40 days on groups 1–3) is when monitoring after a repair matters most.

Figures · click to zoom

Figure 4-4. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.
Figure 4-4. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.
Figure 4-5. Longitudinal defects as recorded. Profillidis Fig. 16.6.
Figure 4-5. Longitudinal defects as recorded. Profillidis Fig. 16.6.
Figure 4-6. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.
Figure 4-6. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.

After Profillidis (2014), §16.5, §16.7, §16.10, Eqs. 16.3–16.5, Figs. 16.5, 16.6, 16.8. Full reference under Supplemental Sources.

Signs of instability job aid and field reporting

Warning signs appear in a predictable order: unusual high water on one side, seepage at the downhill toe, tension cracks along the shoulder (often hidden in ballast), a bulging toe and a small sand fan, increasingly dirty or milky seepage, trees leaning in different directions, and finally settlement or cross-level change in the track. Test hidden cracks with a lining bar; it meets little resistance over a fissure. Paint reference marks to see whether cracks widen. Walk down to the base of the fill when checking culverts, because much of this cannot be seen from the track. If movement is large and accelerating, take the track out of service and restore drainage urgently.

Moisture clues: groundwater discharge in depressions, wet zones or salt stains in cut ditches, frost boils, ice at culvert sides, moisture-loving plants (cattails, willows), and sudden lush vegetation on a slope. Report every natural-hazard incident, including rock found in a ditch, on the Natural Hazard Incident Report. It records site and weather (at the time and over the prior 24 h), a rockfall section, a mass-movement and washout section, and consequences (damage, delays, slow orders). The data is used to deploy rock gangs and maintenance crews.

Figures · click to zoom

Figure 4-33. Signs-of-instability job aid.
Figure 4-33. Signs-of-instability job aid.
Figure 4-34. Testing a suspected tension crack in the field.
Figure 4-34. Testing a suspected tension crack in the field.
Figure 4-35. Paint marks used to monitor crack widening.
Figure 4-35. Paint marks used to monitor crack widening.
Figure 4-36. Leaning trees: a subtle sign of slope movement.
Figure 4-36. Leaning trees: a subtle sign of slope movement.
Figure 4-37. Natural Hazard Incident Report, rockfall section.
Figure 4-37. Natural Hazard Incident Report, rockfall section.
Figure 4-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.
Figure 4-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.

After Geotechnology for Railroaders Program, Module 5, Module 7.1, Module 4, Module 6.4; Module 5 §11; Module 7.1 §05; Module 4 §10; Module 6.4 §05. Full reference under Supplemental Sources.

Project management · Skill Right (2013)

RASIC Responsibility Matrix for Monitoring and Alarm Response

A responsibility assignment matrix (RAM) makes sure every task has an owner and shows how deeply each person is involved. Tasks are listed as rows and roles as columns. The course uses the RASIC code:

  • R – Responsible: makes sure the work is completed and delivered.
  • A – Approve: confirms the work meets the requirements.
  • S – Support: does the work and is committed to completing it.
  • I – Inform: kept up to date on status; makes no decisions.
  • C – Consult: gives input before the work is done.

The course example assigns codes for a marketing study (identify market, develop and test the survey, collect and analyze the data, report) across project manager, customer, team members, senior management and support staff.

For railroad work: an early-warning system is only as good as the chain from instrument reading to train movement decision, and that chain crosses organizations. A RASIC matrix agreed before the instruments are installed removes ambiguity at 2 a.m. The illustrative example below must be adapted to each railroad’s own operating rules and authority for slow orders and track removal from service.

Table 4-PM1. Illustrative RASIC matrix for an instrumented slide (adapted from the course method)

TaskGeotech consultantRailroad engineeringTrack supervisorOperations / dispatch
Set alert and action thresholdsR/SACI
Read and reduce instrumentsR/SII–
Threshold exceedance noticeR/SIII
Field inspection of track and slopeSAR/SI
Speed restriction or removal from serviceCAR/SS
Return to normal operationCARI

Keep one Approve per row so that the decision has a single owner. Put named people and phone numbers, with alternates, in the monitoring plan, and review the matrix whenever staff or thresholds change.

Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role.
Figure 4-PM1. Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role. Source: Skill Right (2013), Slide: Responsibility Assignment Matrix (RASIC Method).

Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 45–47. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

4.11 Worked Calculation Examples

The two examples below show how a trigger changes the margin of safety at a site.

Example 4-1: Effect of a Rising Water Table on an Embankment Side Slope

Project context: A 2H:1V embankment side slope of silty sand fill carries a main track. Shallow sloughing has been reported after heavy rain. Evaluate the change in factor of safety as seepage develops parallel to the slope, using the infinite-slope model (Chapter 13).

Given:

  • Slope angle β = 26.6° (2H:1V); cos β = 0.894, sin β = 0.447, cos²β = 0.800, sin β·cos β = 0.400
  • Depth to slip surface z = 6 ft; total unit weight γ = 120 pcf; γw = 62.4 pcf
  • c′ = 50 psf; φ′ = 32° (tan φ′ = 0.625)
  • Water table height above slip surface = m·z, with m the saturated fraction

Equation 4-2: FS = [c′ + (γ z cos²β − u) tan φ′] / (γ z sin β cos β), with u = m γw z cos²β

Step 1 — Driving stress: γ z sin β cos β = 120 × 6 × 0.400 = 288 psf

Step 2 — Normal stress: γ z cos²β = 120 × 6 × 0.800 = 576 psf

Step 3 — Factor of safety for three water conditions:

Conditionmu (psf)Resisting stress (psf)FS
Dry (no seepage)0050 + 576 × 0.625 = 4101.42
Half saturated0.515050 + 426 × 0.625 = 3161.10
Fully saturated (water at surface)1.030050 + 276 × 0.625 = 2230.77

Conclusion: The slope is marginal even when dry (FS = 1.42, below the 1.5 target). A storm that saturates half the slipping depth brings it close to failure. Full saturation causes failure. The mechanism is shallow translational sliding. The trigger is rainfall infiltration and seepage. Controls that address the mechanism include flattening the slope, adding a drained rock buttress or surface drainage and vegetation. A rainfall-based patrol (Section 4.8) manages exposure until those are built.

Example 4-2: Checking a Storm Against the Caine Threshold

Project context: A rain gauge near a debris-flow channel above the track records 2.0 in. of rain in 6 hours. Does the storm exceed the Caine (1980) global threshold?

Step 1 — Average intensity: 2.0 in. / 6 hr = 0.333 in./hr × 25.4 = 8.5 mm/hr

Step 2 — Threshold intensity at D = 6 hr (Equation 4-1): I = 14.82 × 6−0.39 = 14.82 / 2.01 = 7.4 mm/hr

Step 3 — Compare: 8.5 mm/hr > 7.4 mm/hr, so the storm exceeds the global threshold.

Conclusion: Under a protocol calibrated to this threshold, the site would move to its heightened-response level, such as a patrol before the next train or a speed restriction, depending on the site's risk rating. Remember that the global threshold is a lower bound drawn from worldwide data. Calibrate it for the territory before relying on it.

4.12 Practical Recommendations
  • Record the mechanism, not just the symptom, in every inspection and report. "Soft track" is a symptom; "progressive shear failure of wet CL subgrade" is a mechanism.
  • Look for the preparatory factor that is eroding the margin: a blocked outlet, rising tonnage, toe erosion or a corroding culvert. It is usually cheaper to stop than the failure it leads to.
  • Before ditch cleaning or toe excavation at a known slope, have the geotechnical engineer review the work. Maintenance activity is a recurring trigger.
  • Pair every rainfall-sensitive site in the inventory with a rain source and response threshold.
  • After an event, document the trigger magnitude (rain totals, flood stage, earthquake magnitude and distance). This data calibrates future thresholds.
  • Use instrumentation to confirm the mechanism before committing capital to a repair. Inclinometers and piezometers cost little compared with a buttress built for the wrong failure surface.
4.13 Failure Mechanism Assessment Checklist

Checklist · Part IV · Failure Mechanisms (Triggers)

Failure Mechanism Assessment Checklist

Failure Mechanism Assessment Checklist0 of 9
Ticks are saved in this browser.
Plain text version
  • [ ] Hazard category assigned (landslide, hydraulic, subsidence) per Chapter 1
  • [ ] Mechanism identified and supported by field evidence (Section 4.9)
  • [ ] Predisposing conditions documented (soil, geometry, groundwater)
  • [ ] Preparatory factors identified and, where possible, stopped
  • [ ] Relevant triggers listed with site-specific thresholds where applicable
  • [ ] Factor of safety estimated for current and triggered conditions
  • [ ] Monitoring installed where the mechanism is uncertain or mitigation is deferred
  • [ ] Operating protocol (patrol, slow order, warning system) defined for residual risk
  • [ ] Mitigation selected to address the mechanism, not only the trigger (Chapter 1, Section 1.9)
4.14 Cross-Reference Table
TopicSee Also
Hazard classification, risk estimation and control hierarchyChapter 1
Subgrade failure modes, fouling index, GPRChapter 2
Foundation elements, culverts, bridge approachesChapter 3
Groundwater and seepageChapter 9
Settlement analysisChapter 12
Slope stability analysisChapter 13
Seismic hazard and liquefactionChapter 14
Instrumentation and monitoringChapter 15
Stabilization and ground improvementChapters 16, 17; Section 17.16
4.15 Practice Questions

Q1. Classify each as a predisposing condition, preparatory factor or trigger: (a) a sensitive clay deposit; (b) a culvert corroding over 20 years; (c) a 100-year storm; (d) tonnage on the line doubling over a decade.

Answer:

  • (a) Predisposing condition; (b) preparatory factor; (c) trigger; (d) preparatory factor. Increased load can also act as a trigger if a single step change pushes a marginal subgrade past its limit.

Q2. Using Example 4-1, what saturated fraction m brings the slope to FS = 1.0?

Answer:

  • Set 50 + (576 − 299.5m) × 0.625 = 288. Then 410 − 187.2m = 288, so m = 0.65. The slope fails when water rises to about two-thirds of the slip depth.

Q3. A storm delivers 3.0 in. of rain in 24 hours. Does it exceed the Caine threshold?

Answer:

  • I = 3.0 × 25.4 / 24 = 3.2 mm/hr. Threshold at D = 24 hr: 14.82 × 24−0.39 = 14.82 / 3.45 = 4.3 mm/hr. 3.2 < 4.3, so the storm does not exceed the global threshold. Antecedent moisture and a locally calibrated threshold could still warrant a response.

Q4. Why is diagnosing the mechanism, and not just the trigger, essential before selecting a repair?

Answer:

  • The same symptom can come from different mechanisms. A repair aimed at the wrong mechanism (for example, undercutting ballast when the cause is a deep-seated slide) spends money without reducing the hazard. Managing only the trigger leaves the hazard in place and relies on operating restrictions indefinitely.
References
  • Caine, N. (1980). The rainfall intensity–duration control of shallow landslides and debris flows. Geografiska Annaler, Series A, 62(1–2), 23–27.
  • Cruden, D.M. and Varnes, D.J. (1996). Landslide types and processes. In Landslides: Investigation and Mitigation, TRB Special Report 247.
  • Hungr, O., Leroueil, S. and Picarelli, L. (2014). The Varnes classification of landslide types, an update. Landslides, 11, 167–194.
  • Selig, E.T. and Waters, J.M. (1994). Track Geotechnology and Substructure Management. Thomas Telford.
  • Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016). Railway Geotechnics. CRC Press.
  • Federal Railroad Administration, Track Safety Standards, 49 CFR Part 213 (incl. §213.239 Special inspections).
  • FHWA, HEC-18, Evaluating Scour at Bridges, current edition.
  • ASTM D6230, Standard Test Method for Monitoring Ground Movement Using Probe-Type Inclinometers.
4.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S4 under Supplemental Sources.

Case Study 4.16.1 — Slope failures whose consequences left the site
Case study · Look (2023) §3.8

Related section: 4.3 Embankment and Slope Failure Mechanisms

Look uses three historical failures to show that a slope’s safety obligations extend beyond the construction boundary:

  • Aberfan, South Wales (1966). Colliery spoil tips had been built over highly porous sandstone containing numerous springs. After heavy rain, water built up in the tip and it failed as a slurry flow that travelled about 1,430 ft downhill, killing 144 people, 116 of them schoolchildren.
  • Samarco tailings dam, Brazil (2015). The collapse flooded downstream villages, killed 19 people and carried pollutants hundreds of kilometers down watercourses. Look notes an upward trend in deaths from tailings-dam failures.
  • Po Shan Road, Hong Kong (1972). After about 27.6 in of rain in three days, a landslip on a developed hillside with cuttings killed 67 people. It led to the formation of the Geotechnical Engineering Office.

Most slope instability is smaller and stays on site, costing time and money; but a single 12 in boulder from a cutting can reach a traffic lane or a house 164 ft away.

For railroad work: a track at the toe of mine spoil, a tailings embankment or a steep developed hillside is exposed to a failure that starts on someone else’s property. Section 4.3’s flow-slide mechanisms apply, and these sources belong on the hazard inventory even when they are outside the right-of-way.

Aberfan, 1966: flow of uncontrolled colliery spoil over porous sandstone with springs (after Bromhead 1992).
Figure 4-LK1. Aberfan, 1966: flow of uncontrolled colliery spoil over porous sandstone with springs (after Bromhead 1992). Source: Look (2023), Figure 3.9-1, p. 91.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §3.8, pp. 92. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Supplemental Sources

Sections on this page marked “After Profillidis (2014)” draw on the document below. Text is summarized or paraphrased; tables are transcribed or reproduced with their original source noted; figures and photos are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S3 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S4 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)
  2. Benesch. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. Colwell
  3. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 3, 4, 8, 14 and 15
  4. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §3.8
  5. Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute. Used on this page for project-management material
  6. Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]. Used on this page for project-management material
Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This part was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

References

  • Caine, N. (1980). The rainfall intensity–duration control of shallow landslides and debris flows. Geografiska Annaler, Series A, 62(1–2), 23–27.
  • Cruden, D.M. and Varnes, D.J. (1996). Landslide types and processes. In Landslides: Investigation and Mitigation, TRB Special Report 247.
  • Hungr, O., Leroueil, S. and Picarelli, L. (2014). The Varnes classification of landslide types, an update. Landslides, 11, 167–194.
  • Selig, E.T. and Waters, J.M. (1994). Track Geotechnology and Substructure Management. Thomas Telford.
  • Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016). Railway Geotechnics. CRC Press.
  • Federal Railroad Administration, Track Safety Standards, 49 CFR Part 213 (incl. §213.239 Special inspections).
  • FHWA, HEC-18, Evaluating Scour at Bridges, current edition.
  • ASTM D6230, Standard Test Method for Monitoring Ground Movement Using Probe-Type Inclinometers.

Case studies

  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §3.8

Project management sources

  • Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute
  • Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]