↑ Parent Menu⌂ Main Menu
← Railway Ground Hazard Risk Management
NANCY
Railway Ground Hazard Risk Management · Part VI · Geotechnical Analysis
Sections · click a car to open it

Chapter 12 — Settlement Analysis

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 11.
Authors: Daniel P. Colwell and Mario Ruel

Railroad Geotechnical Services Manual | Primary Source: USACE EM 1110-1-1804 All equations and parameters expressed in English (Imperial) units throughout.

Apps for this Chapter2

Apps on dirtbert.com that support this chapter. Each one runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (I.3).

NANCY pages ask you to accept the Use and Disclaimers once in each browser.

Executive Summary

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 11. For railroad infrastructure, settlement governs more designs than bearing capacity failure — particularly embankment fills over soft alluvial soils, approach fills behind bridge abutments, and intermodal yard slabs on compressible clay. Total settlement S_total consists of three components: immediate (elastic) settlement S_i, primary consolidation settlement S_c, and secondary compression S_s. Time-rate analysis using Terzaghi's consolidation theory predicts when settlement will occur, enabling the consultant to recommend preloading, staged construction, or ground improvement to achieve acceptable geometry before track placement. This chapter develops all three settlement components in English units, cross-references FRA track geometry tolerances by track class as the acceptance criteria, and presents worked examples for a CSXT embankment over soft clay, a CN bridge approach fill with time-rate prediction, and a BNSF intermodal yard slab on overconsolidated clay. All nine railroad client standards are integrated throughout.

12.1 Background and Railroad Context

FRA track geometry tolerances (49 CFR Part 213) establish the operational framework within which all settlement predictions must be evaluated. Unlike building foundations, where total settlement of 1–2 in. is routinely acceptable, railroad track geometry tolerances are measured in fractions of an inch — the structural consequence of derailment, speed restriction, or emergency slow order is immediate and measurable.

Table 12-1 — FRA Track Geometry Tolerances vs. Settlement Acceptance Criteria
Track ClassMax Speed (Freight)Cross-Level ToleranceSurface (Runoff) ToleranceTotal Settlement Limit (our recommendation)Angular Distortion Limit
Class 110 mph3.0 in.3.0 in. per 62 ft≤ 3.0 in.≤ 1/200
Class 225 mph2.0 in.2.0 in. per 62 ft≤ 2.0 in.≤ 1/300
Class 340 mph1.75 in.1.75 in. per 62 ft≤ 1.5 in.≤ 1/400
Class 460 mph1.5 in.1.5 in. per 62 ft≤ 1.0 in.≤ 1/500
Class 580 mph0.75 in.0.75 in. per 62 ft≤ 0.75 in.≤ 1/700
Class 6110 mph0.5 in.0.5 in. per 62 ft≤ 0.5 in.≤ 1/1,000
Class 7 (Amtrak NEC)125 mph0.5 in.0.5 in. per 62 ft≤ 0.375 in.≤ 1/1,500

Angular distortion δ/L (where δ = differential settlement between two points, L = distance between them) is the critical parameter for bridge approach transitions and structure-embankment interfaces. Amtrak ES and NSR ESM independently impose tighter limits than FRA at structure transitions.

Railroad client settlement requirements beyond FRA minima:

  • CSXT ES: Total settlement ≤ 1.0 in. for Class 4–6 mainline track; differential ≤ 0.5 in. per 62 ft over any embankment section.
  • NSR ESM: Bridge approach fill settlement must be completed to < 0.5 in. residual before track surfacing; construction surcharge required where S_c > 2 in. predicted.
  • G&W EB: Settlement limits for low-speed sidings (Class 1–2) are relaxed to 3.0 in. total with monthly surfacing cycle; G&W accepts higher settlement if tamping frequency increases accordingly.
  • UPRR EIM: Intermodal yard pavement differential settlement ≤ 0.25 in. per 10 ft; crane rail differential ≤ 0.125 in. per 20 ft.
  • BNSF EI: Transcon mainline (Class 5) settlement limit 0.75 in. total; approach embankment instrumentation (settlement plates + piezometers) required when H_fill > 15 ft over soft clay.
  • CPKC TS: Frost heave and thaw consolidation cycles must be accounted for in northern tier projects; post-thaw settlements of 1–3 in. are common in silty subgrades. CN ES has equivalent requirements.
  • Amtrak ES: NEC settlement is measured by automated geometry car every 30 days; any location exceeding 0.5 in. change since last pass triggers a slow order. Settlement predictions must explicitly address post-construction residual.
  • CN ES: Requires bilingual settlement analysis report for any fill exceeding 10 ft over soft ground on CN right-of-way.

Settlement at subgrade, tie and rail level by subgrade class

Elastoplastic finite-element results reproduced by Profillidis show the settlement under a passing axle at the top of subgrade, at the tie and at the rail for subgrade classes S1, S2, S3 and rock, for track-bed thicknesses of 12–39 in.. Subgrade class dominates: moving from S1 to S3 cuts the settlement several-fold, while extra track-bed thickness gives a smaller, steady reduction. Tie type matters less than subgrade class.

For new fills, the book reminds designers to overbuild embankment width and height to allow for the fill’s own compaction after construction (Chapter 3, §3.2).

Figures · click to zoom

Figure 12-11. Vertical settlement at subgrade and tie level vs. track-bed thickness e, for subgrade classes S1–S3 and rock. Profillidis Fig. 8.8.
Figure 12-11. Vertical settlement at subgrade and tie level vs. track-bed thickness e, for subgrade classes S1–S3 and rock. Profillidis Fig. 8.8.
Figure 12-12. Vertical settlement at tie and rail level vs. track-bed thickness e, by tie type and subgrade class. Profillidis Fig. 8.9.
Figure 12-12. Vertical settlement at tie and rail level vs. track-bed thickness e, by tie type and subgrade class. Profillidis Fig. 8.9.

After Profillidis (2014), §8.4.7, Figs. 8.8–8.9. Full reference under Supplemental Sources.

12.2 Stress Increase in Soil — Boussinesq Distribution

Before computing settlement, the change in vertical stress Δσ_v at depth z due to the applied load must be determined. For a uniformly loaded rectangular area of width B and length L at the surface:

Equation 12-1 — Boussinesq Stress Increase Under Corner of Rectangle:

Δσ_v = q · I_σ

Where I_σ is the Boussinesq influence factor (Newmark, 1935), a function of m = B/z and n = L/z:

I_σ = (1/4π)[2mn√(m²+n²+1)/(m²+n²+1+m²n²) × (m²+n²+2)/(m²+n²+1)

+ arcsin(2mn√(m²+n²+1)/(m²+n²+1+m²n²))]

For practical use, Boussinesq influence charts (or tables) are used; I_σ ranges from 0.25 (square footing, z = 0) to near zero at large depth. For a 2:1 stress distribution approximation (AREMA MRE Chapter 8 simplification), commonly used for preliminary analysis:

Equation 12-2 — 2:1 Stress Distribution:

Δσ_v = Q / [(B + z)(L + z)] (psf)

Where Q = total load (lb), B and L = footing dimensions (ft), z = depth below footing base (ft). For strip loads (railroad embankments):

Equation 12-3 — Strip Load Stress Increase:

Δσ_v = (q/π)[β + sin β · cos(β + 2δ)] (psf)

Where β = the angle subtended by the load width at depth z (radians), δ = angle from load centerline, q = applied surface pressure (psf). For the centerline of a strip load:

Δσ_v,center = (q/π)[β + sin β]

12.3 Immediate (Elastic) Settlement

Immediate settlement occurs under undrained loading conditions in saturated cohesive soils, or drained loading in granular soils. It develops essentially instantaneously upon load application.

Equation 12-4 — Immediate Settlement (Flexible Rectangular Footing):

Si = q · B · (1 − μ²) / Es · Iw

Where:

  • q = net contact pressure (psf)
  • B = footing width (ft)
  • μ = Poisson's ratio (0.5 for undrained clay; 0.3–0.35 for sand)
  • E_s = elastic modulus of soil (psf)
  • I_w = influence factor for shape and embedment (Bowles, 1996; I_w ≈ 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5)
Table 12-2 — Typical Elastic Modulus Values for Settlement Analysis (English Units)
Soil Type (USCS)E_s (psf)Typical Source
Very soft clay (CH)10,000–25,000Unconfined compression
Soft clay (CL)25,000–75,000Unconfined compression
Medium stiff clay75,000–150,000CPTu, PMT
Stiff clay150,000–300,000CPTu, PMT
Very stiff clay300,000–500,000PMT, pressuremeter
Loose sand (SP/SM)100,000–250,000SPT correlation
Medium-dense sand250,000–500,000SPT correlation
Dense sand/gravel500,000–1,500,000SPT correlation

Immediate settlement is critical for UPRR intermodal yard slab design and for any structure where the total settlement is dominated by granular or stiff-clay subgrades. For most railroad embankment designs over soft cohesive soils, primary consolidation governs and S_i is secondary.

Supplemental reference · LEVI Library

Granular soils: Schmertmann strain-influence method

Eq. 12-4 assumes a single modulus for the whole stressed zone. For footings, signal foundations and yard slabs on sand, USACE EM 1110-1-1904 recommends Schmertmann’s approximation, which sums strain over sublayers of thickness Δz = 0.2B using a triangular strain-influence diagram (Figure 12-S1):

ρi = C1 · Ct · Δp · Σ (Izi / Esi) Δzi

  • C1 = 1 − 0.5 σ′od/Δp ≥ 0.5 (embedment correction); Δp = q − σ′od (net pressure).
  • Ct = 1 + 0.2 log10(t/0.1), t in years — creep of the sand; after 50 years Ct ≈ 1.54, which matters for long-life railroad structures.
  • Peak factor Izp = 0.5 + 0.1(Δp/σ′Izp)1/2, located at B/2 below the base for square/circular footings (Iz reaching zero at 2B) and at B for strip footings (zero at 4B); interpolate for 1 < L/B < 10.
  • Modulus from the cone: Es = 2.5 qc (axisymmetric) and 3.5 qc (plane strain). Where only SPT data exist, USACE converts N to qc (tsf) with qc/N = 2 (silts, sandy silts), 3.5 (clean fine–medium sand), 5 (coarse sand) and 6 (sandy gravel).

Because the method weights the stiffness of each sublayer, it captures a loose sand seam at depth B/2 that a single-modulus calculation averages away.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

Supplemental figures · LEVI Library
Recommended strain influence factors for Schmertmann&rsquo;s approximation (Schmertmann, Hartman &amp; Brown, 1978, reproduced in EM 1110-1-1904).
Supplemental Figure 12-S1. Recommended strain influence factors for Schmertmann’s approximation (Schmertmann, Hartman & Brown, 1978, reproduced in EM 1110-1-1904). Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904, p. 3-8.

Case study: 12.16.1 Unit weight of fill: design assumes 127 pcf, the job measures more (Look 2023), in §12.16 Case Studies.

12.4 Primary Consolidation Settlement
12.4.1 Settlement Equations

Primary consolidation settlement S_c is governed by the compressibility of the clay skeleton as excess pore pressures dissipate. Three cases apply depending on the preconsolidation stress σ'_p:

Reference graphics · click to zoom

Settlement Calculation
Settlement Calculation
Equation 12-5 — Normally Consolidated Clay (σ'_v0 = σ'_p):

Sc = [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]

Equation 12-6 — Overconsolidated Clay, Stress Remains Below σ'_p:

Sc = [Cs / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]

Equation 12-7 — Overconsolidated Clay, Stress Exceeds σ'_p:

Sc = [Cs / (1 + e₀)] · H · log[σ'_p / σ'_v0]

+ [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_p]

Where:

  • C_c = compression index (dimensionless)
  • C_s = swell/recompression index ≈ C_c/5 to C_c/10 (dimensionless)
  • e₀ = initial void ratio (dimensionless)
  • H = layer thickness (ft)
  • σ'_v0 = initial effective vertical stress at midpoint of layer (psf)
  • σ'_p = preconsolidation stress (psf); OCR = σ'_p / σ'_v0
  • Δσ = stress increase at midpoint of layer from applied load (psf)
Equation 12-8 — Empirical C_c Estimate (Skempton, 1944):

Cc = 0.009 · (LL − 10)

Where LL = liquid limit (%). Valid for normally consolidated clays; use with caution for organic soils. For railroad projects, laboratory consolidation tests (ASTM D 2435) are required by CSXT ES, NSR ESM, BNSF EI, and Amtrak ES for all embankments exceeding 6 ft over soft clay.

Equation 12-9 — Void Ratio from Unit Weight:

e₀ = (Gs · γ_w / γ_d) − 1

Where G_s = specific gravity (≈ 2.70 for most clays), γ_d = dry unit weight (pcf), γ_w = 62.4 pcf.

12.4.2 Sublayer Method

When a compressible layer is thick (> 5 ft) or when the stress increase varies significantly with depth, the layer should be divided into sublayers of 2–4 ft thickness. Settlement is computed for each sublayer at its midpoint stress state, then summed:

Equation 12-10 — Sublayer Summation:

Sc,total = Σ [Cc,i / (1 + e₀,i)] · Hi · log[(σ'_v0,i + Δσ_i) / σ'_v0,i]

This sublayer approach is mandatory for BNSF and Amtrak projects with clay layers > 10 ft thick, where ignoring stress variation underestimates settlement at the top of the layer and overestimates at depth.

Settlement on organic ground: field cases

Organic soils can compress by up to about 40% (12 ft of peat can mean 5 ft of settlement). Muskeg also punches under load, and buried corduroy decays. At Bedford Mile 29.8, years of swamp ties never stopped the settlement; only a proper berm, together with draining the water driving the movement, solved it. At Lac la Biche Sub Mile 173.48, 400 ft of differential settlement into deep peat needed piles. In 2016 dollars, swamp ties cost about $670,000 per mile, against about $280,000 per mile for undercutting and about $6.7 million per mile for new track (course figures of $600,000, $250,000 and $6,000,000 in 2012 dollars, escalated by the ENR Construction Cost Index; see Chapter 17, Table 17-6), so diagnosing the mechanism early is the cheapest option.

Figures · click to zoom

Figure 12-14. The Lac la Biche corridor through low-lying burned forest.
Figure 12-14. The Lac la Biche corridor through low-lying burned forest.
Figure 12-15. Bedford Mile 29.8 embankment instability.
Figure 12-15. Bedford Mile 29.8 embankment instability.

After Geotechnology for Railroaders Program, Module 2, Module 6.1, Module 6.2; Module 2 §08; Module 6.1 §03; Module 6.2 §01, §05. Full reference under Supplemental Sources.

12.5 Time Rate of Consolidation
12.5.1 Terzaghi One-Dimensional Theory

The degree of consolidation U (fraction of ultimate settlement completed at time t) is governed by the dimensionless time factor T_v:

Reference graphics

Karl Von Terzaghi
Karl Von Terzaghi
Drained vs Undrained Analysis
Drained vs Undrained Analysis

Reference graphics · click to zoom

Soil Consolidation Testing
Soil Consolidation Testing
Equation 12-11 — Time Factor:

Tv = cv · t / H_dr²

Where:

  • c_v = coefficient of vertical consolidation (ft²/day; from ASTM D 2435 consolidation test)
  • t = elapsed time (days)
  • H_dr = length of drainage path (ft): H_dr = H/2 for two-way drainage (sand above and below clay); H_dr = H for one-way drainage (clay bounded by impermeable rock)
Table 12-3 — Time Factor T_v vs. Average Degree of Consolidation U
U (%)T_v (simplified)T_v (exact)
100.0080.008
200.0310.031
300.0710.071
400.1260.126
500.1970.197
600.2870.287
700.4030.403
800.5670.567
900.8480.848
951.1631.129
99—1.781

For U ≤ 60%:

Tv = π/4 · (U/100)² (simplified parabolic approximation)

For U > 60%:

Tv = −0.933 · log(1 − U/100) − 0.085

Equation 12-12 — Settlement at Time t:

S(t) = U · Sc,total

Equation 12-13 — Time to Achieve Target Degree of Consolidation:

t = Tv · H_dr² / cv

12.5.2 Typical c_v Values
Table 12-4 — Typical Coefficient of Consolidation c_v (English Units)
Soil Typec_v (ft²/day)c_v (ft²/year)Notes
Soft organic clay0.0005–0.0050.2–2CSXT coastal Georgia, CN Manitoba
Soft marine clay0.005–0.052–18NSR tidewater VA, Amtrak NEC
Medium clay0.05–0.218–73BNSF Kansas, UPRR Nebraska
Stiff clay0.2–1.073–365NSR Appalachian residual
Very stiff clay1.0–10365–3,650Quick-draining; settle rapidly
Silty clay (CL-ML)0.1–0.537–183CPKC Prairie provinces

Multiplying path length squared by unit conversion: if c_v in ft²/day and H_dr in ft, time t is in days.

12.6 Secondary Compression (Creep) Settlement

Secondary compression occurs after primary consolidation is essentially complete (U ≈ 95–100%) as the clay skeleton continues to creep under sustained load. It is particularly significant for organic soils (Pt) and highly plastic clays (CH) — common in CSXT Georgia coastal swamps, CN Manitoba peatlands, and BNSF Louisiana territory.

Equation 12-14 — Secondary Compression Settlement:

Ss = Cα / (1 + ep) · H · log(t₂ / t₁)

Where:

  • C_α = secondary compression index (dimensionless); ≈ 0.04 × C_c for most clays; 0.05–0.10 for organic soils
  • e_p = void ratio at end of primary consolidation (≈ e₀ − ΔeP for primary compression)
  • H = layer thickness (ft)
  • t₁ = time at end of primary consolidation (days)
  • t₂ = design service life or evaluation time (days)
Equation 12-15 — Empirical C_α (Mesri and Godlewski, 1977):

Cα/Cc ≈ 0.04 ± 0.01 (for inorganic clays)

Cα/Cc ≈ 0.05 to 0.07 (for organic clays and peats)

For a 50-year railroad service life (t₂ = 18,250 days) with primary consolidation completing at t₁ = 500 days, log(18,250/500) = log(36.5) = 1.562. Even a modest C_α = 0.010 over a 10 ft clay layer produces S_s = 0.010/(1 + 1.8) × 10 × 1.562 = 0.056 ft = 0.67 in — significant on a Class 5 mainline with a 0.75 in. tolerance.

Supplemental reference · LEVI Library

Cα/Cc by soil type

USACE EM 1110-1-1904 (Table 3-14, after Mesri) extends the ratios in Eq. 12-15 to other materials encountered on railroad alignments:

Table 12-S1. Ratio of secondary compression index to compression index

SoilCα/Cc
Inorganic soils0.025–0.060
Clay0.025–0.085
Silt0.030–0.075
Peat0.030–0.085
Muskeg0.090–0.100

For a first approximation before tests are available, USACE (after NAVFAC DM-7.1) gives Cα ≈ 0.0001 wn for natural water contents 10–3,000%. The manual cautions that sample disturbance lowers the measured Cα in the virgin range and that secondary-compression predictions “have often not been reliable” — one more reason to confirm long-term behavior with settlement plates rather than rely on the calculation alone.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

Supplemental reference · LEVI Library

Testing peat: what changes from inorganic soil

Lea and Brawner’s British Columbia highway experience gives practical guidance for the peat and muskeg crossings noted above:

  • Water content of pure peat is typically 500–1,500% (occasionally > 2,000%); values below 500% usually indicate mineral content. It can vary several-fold within 1 ft, so moisture samples should be at least 10 in.3 Research cited in the paper found the standard 220–230°F oven chars peat; about 185°F was indicated as more appropriate.
  • Specific gravity of pure peat is about 1.5–1.6, so void ratios are very high (about 18 at w = 1,000%). Gas contents of 7–10% were estimated; assuming full saturation can put e off by about 10%.
  • Unit weight of pure peat was generally 55–75 pcf (wet); dry unit weight can be as low as 4 pcf.
  • Permeability of virgin peat was about 30 to 0.3 ft/day but fell to about 0.03 ft/day under a few feet of fill — so cv measured at low stress overstates the rate under the final embankment.
  • The clay under the peat is often the real problem. Because peat is light and recently deposited, underlying clay — even 30–40 ft down — is likely to be very weak. On the Trans-Canada Highway, 6 ft of granular fill was calculated to produce about 11 ft of settlement (8 ft in peat, 3 ft in clay) and enough load to cause a base failure in the clay.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board

12.7 Total Settlement and Angular Distortion
Equation 12-16 — Total Settlement:

S_total = Si + Sc + Ss

Equation 12-17 — Angular Distortion:

α = (S_A − S_B) / L_AB

Where S_A and S_B are predicted settlements at two adjacent structures or reference points, and L_AB is the distance between them (ft). AREMA MRE Chapter 8 limits angular distortion at bridge approach transitions to 1/500 for Class 4 track.

Bridge Approach Transition: The most critical angular distortion check in railroad geotechnical practice is at the abutment–embankment interface. A rigid pile-supported abutment settling < 0.1 in. adjacent to an approach fill settling 3.0 in. over 30 ft produces α = 2.9/30 = 0.097 — far exceeding any FRA class limit. AREMA Chapter 8, CSXT ES, and NSR ESM all require approach slab design or engineered approach fill to limit this transition zone differential.

Supplemental reference · LEVI Library

Settlement that consolidation theory does not predict

Repeated and dynamic loads. USACE EM 1110-1-1904 notes that loose sands compact under vibration and that this is a major cause of differential settlement. Cohesionless soils with Dr above about 75% should not settle significantly, although intense dynamic loading can still compact dense sand by 1–2% of the stratum thickness. Dynamic settlement may be insignificant if the combined static and dynamic bearing stress stays below one-half of the allowable bearing capacity. Errors in dynamic-settlement predictions can be 50% or more. For clays under repeated deviator stress (0.1–10 Hz, a typical range for traffic), the manual gives a creep-strain-rate formulation from cyclic triaxial tests but warns it may underestimate settlement because traffic loading is more complex than repeated vertical load.

Collapsible soils. Loess, some alluvial fans and cemented silts lose their bonded structure on wetting. Typical collapsible soils are light-colored, LL < 45, PI < 25, with dry unit weight 65–105 pcf; collapse rarely occurs below 40% porosity. USACE notes that dynamic loading can also break the bonds, “particularly important for roads, airfields, railways.”

Table 12-S2. Wetting that can trigger collapse (EM 1110-1-1904, Table 5-4, condensed)

Type of wettingRailroad exampleResult
Local, shallowBlocked ditch, leaking pipeline crossingSettlement in the upper layer within the wetted area
Intense localIndustry effluent, broken water main, irrigationCan saturate the whole collapsible zone in < 1 year; uneven, damaging settlement
Slow, uniform groundwater riseReservoir or regional water table riseUniform, gradual settlement
Slow increase in water contentReduced evaporation under a paved yard or slabIncomplete, progressive settlement

Collapse potential CP (Jennings and Knight, 1975) is the strain on flooding a consolidometer specimen at 2 tsf: 0–1% negligible, 1–5% moderate trouble, 5–10% trouble, 10–20% severe trouble, > 20% very severe trouble. For design, load the specimen to the anticipated field stress and then inundate it (ASTM D4546, Method B); settlement = [(eo − ec)/(1 + eo)]H. USACE cautions that lab tests can miss soil that later collapses in the field, and the amount depends on how far the wetting front travels — so drainage control is part of the design.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

How much differential settlement the track itself tolerates

Geometry limits put a practical ceiling on differential settlement under track. European intervention limits for the longitudinal (surface) defect on a 33-ft chord range from about 0.35–0.47 in. at 87–99 mph to 0.55–0.83 in. below 37 mph (Chapter 3, §3.11). Emergency speed restrictions begin at 0.71 in.. Because the chord is short, these are effectively limits on settlement differences over about 33 ft. Embankment, culvert and transition settlement predictions should be checked against that scale, not only against total settlement.

After any surfacing, defects grow quickly up to about 2 million tons of traffic and then slowly, roughly with log T, at a rate (0.079–0.24 in. per decade of traffic) that depends mainly on subgrade quality (Chapter 4, §4.10).

Figures · click to zoom

Figure 12-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.
Figure 12-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.

After Profillidis (2014), §16.3, §16.6–16.7, Fig. 16.2. Full reference under Supplemental Sources.

Settlement of the track section under traffic

Components. Total settlement is the sum of three parts:

  • Ballast strain × ballast thickness.
  • Subballast strain × subballast thickness.
  • Subgrade settlement.

On new track, more than half comes from the ballast. After each tamping the ballast share grows again, because the loosened top ballast starts over.

Use a power law, not a semilog fit. Settlement after N load cycles fits SN = S1 Nb, with b typically 0.10–0.18. A semilog fit increasingly underpredicts at large N, and so overestimates the time to the next surfacing.

Load cycles per MGT. Cm = 106 ÷ (Aa × Na), where Aa is axle load in tons and Na is axles per load cycle. Use Na = 2 per car for ballast. For example, a 39-ton axle gives about 12,800 cycles per MGT.

Table 12-SW1. Settlement relations measured at FAST (T in MGT; site-specific)
LayerRelationAt 100 MGT
Top 12 in. of ballast (strain)ε = 0.026 T0.21ε ≈ 0.068 → 0.8 in.
Subballast (strain)ε = 0.017 T0.16; about 2.6 × 10−5 per MGT beyond ~150 MGTε ≈ 0.036
Subgrade, top 10 ft of moist fine silty sandS (in.) = 0.039 T0.37 (typical); 0.054 T0.52 (worst section)≈ 0.2 in. (typical)
Subgrade, long term0.001–0.0026 in. per MGT, linear beyond ~50 MGT—

the authors evaluated the 100 MGT column from the relations. Rapid compression occurred through the first ~3 MGT, then continued at a slower rate.

Lift and settlement. After a low lift, the track settles back by about the amount it was lifted within roughly a year, so the change does not last. Lifts above about 1 in., which exceed the ballast D50, leave a residual lift. Allow about 0.16 in. of settlement even at zero lift, from wear and compaction.

After Selig & Waters (1994), chs. 8 and 15. Full reference under Supplemental Sources.

12.8 Preloading and Surcharge Design

When predicted settlement S_c exceeds the client's allowable limit, preloading with temporary surcharge fill is the most cost-effective mitigation. The concept: apply a surcharge load greater than the permanent design load, allow consolidation to occur before track placement, then remove the surcharge and install track on a pre-compressed subgrade.

Reference graphics

Settlement Plate Installation
Settlement Plate Installation
Equation 12-18 — Required Surcharge Pressure:

Δσ_surcharge = Δσ_permanent × [Sc,required / Sc,total]^(1/(Cc/Cs))

A simplified approach: select q_surcharge such that primary consolidation under q_surcharge equals the sum of primary consolidation + secondary compression expected under q_permanent over the service life. NSR ESM requires this calculation for all bridge approach fills where predicted settlement exceeds 2 in.

Equation 12-19 — Time for Surcharge to Achieve U = 90%:

t_surcharge = 0.848 · H_dr² / cv

If t_surcharge is prohibitively long (> 6–12 months on a construction schedule), prefabricated vertical drains (PVDs) are combined with the surcharge to accelerate drainage — addressed in Chapter 17 (Ground Improvement).

Supplemental reference · LEVI Library

Field record: preloading, drains and excavation over peat

Lea and Brawner’s case histories from the Vancouver area test the assumptions behind Eq. 12-18 and 12-19:

  • Surcharge works. At Lougheed Highway and Boundary Road (1958), about 1,200 ft of road over up to 14 ft of peat was brought to grade plus a 5-ft surcharge, carried traffic on a temporary surface for three months, then was paved. Settlement plates and piezometers controlled the rate of construction. No differential settlement or pavement failure appeared in the first four years.
  • Vertical drains in peat may not perform as calculated. At Maillardville (1954), 18-in. sand drains at 15-ft triangular spacing were calculated to raise the settlement rate at least eightfold; measured primary settlement was only about 15% faster. Check drain performance in peat with a test section before relying on it in the schedule.
  • Rigid structures in a settling fill create bumps. On the same project, culverts on piles did not settle with the grade, and severe bumps formed at every culvert within a few months. The same applies to pile-supported culverts and pipe crossings under a new railroad embankment on soft ground.
  • Excavate-and-replace is only as good as the cleanup. On the Deas Tunnel Throughway, peat 6–11 ft deep was excavated and replaced with dredged sand. Within a year pockets of peat and organic silt left in place caused up to 3 in. of differential settlement over 50 ft.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board

Supplemental reference · LEVI Library

Lightweight fill: reducing the load instead of waiting for it

When surcharge time is not available, or added fill would cause a stability failure, the alternative is to reduce Δσ itself. Three generations of lightweight fill appear in the library:

Table 12-S3. Lightweight fill options

MaterialKey propertiesDesign notes
Sawdust (historic; Trans-Canada Highway, Burnaby)3–12 ft thick; compressed to 80–90% of placed thickness under about ½ tsf preload; lab φ = 50°Rots and can spontaneously combust above the water table, so the top must end up below groundwater after settlement. Settlement had to be predicted accurately to place it at the right grade.
Expanded shale, clay or slate (ESCS) lightweight aggregateKiln-expanded at 1,900–2,200°F; relative density 1.3–1.6 vs. 2.6–3.0 for normal aggregate (about half the mass per volume); AASHTO M 195 gradationsOpen-graded; still needs compaction (lifts ≤ 12 in. loose with vibratory roller). Density control by a one-point Proctor (modified ASTM D698) plus a method spec.
EPS geofoam (ASTM D6817)EPS 15 / 19 / 22 / 29: minimum density 0.90 / 1.15 / 1.35 / 1.80 pcf; compressive resistance at 10% strain 10.2 / 16.0 / 19.6 / 29.0 psi“Zero net load”: excavate native soil equal in weight to the geofoam plus everything placed on it. It can also replace the active wedge behind an abutment.

Case: US 17 / SC 707, Myrtle Beach, SC. At the nearby Fantasy Harbour project, embankments 10–42 ft high had settled 9 to 67 in. For the US 17 / SC 707 interchange, bridge approach fills over 30–60 ft of soft to firm clay and loose, liquefiable sands were estimated to settle 78 in. at the abutment if built with normal-weight fill (120 pcf). The design combined LWA borrow to cut the magnitude, PVDs with granular surcharge to speed it, and deep soil mixing for seismic slope stability and abutment performance.

Railroad cautions (engineering judgment, not from the sources): lightweight fills must be covered by enough ballast, subballast and soil to spread axle loads and resist buoyancy at flood stage. Geofoam must be protected from petroleum spills (hydrocarbon-resistant membrane) near fueling or derailment-prone areas. Confirm dynamic stiffness under E-80 loading before using any lightweight fill directly under track.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board · Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co. · Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)

Supplemental figures · LEVI Library
Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby).
Supplemental Figure 12-S2. Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby). Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board.
Project management · Levy (2010)

Schedule Float, Change Orders and Surcharge Hold Times

Levy (2010) explains, from the owner’s side, how changes interact with the contractor’s critical path method (CPM) schedule. The critical path moves as the job proceeds, and a delay to one critical task can cascade into later tasks and push out the completion date. When a change may affect time, owners face the question of whether the delay is real. Levy advises settling time when the change is priced, not later, because once unrelated contractor delays accumulate it becomes hard to separate them from the change. Extended time matters because general conditions costs (supervision, trailers, utilities, rentals) continue, and he cites $20,000 to $40,000 per month as a typical range.

Where time cannot be agreed, he suggests two approaches: issue the change with a statement that the work proceeds while the owner reserves the right to challenge any time extension, or sign the cost proposal provisionally, reserving the right to challenge both cost and time. Change-order forms often require checking whether the change increases, decreases or does not affect the contract end date, and owners should read that box before signing.

On float, Levy notes that schedules carry a cushion of extra days for weather, late equipment or short crews. Unless the contract says otherwise, that float belongs to the contractor. If the owner wants float for its own contingencies, such as late delivery of owner-furnished items, it must reserve it in the contract; otherwise an owner-caused delay that consumes the contractor’s float can become a claim.

For railroad work: Preload and surcharge programs for embankment widening or approach fills put a waiting period directly on the critical path, and its true length depends on measured consolidation rather than on the design estimate. Specify in the contract who owns float in the hold period, how the hold may be extended or shortened on the basis of settlement plate and piezometer data, and how extended time will be paid. Write the decision rule (for example, release when the monitored settlement rate falls below a stated value) into the special provisions so that a longer hold is a defined outcome rather than a dispute.

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 215–216. Summarized and paraphrased. Full reference under Supplemental Sources.

12.9 Representative Data Table
Table 12-5 — Sample Consolidation Test Results — CSXT Coastal Georgia Embankment Project
BoringSampleDepth (ft)USCSLL (%)PIe₀C_cC_sC_αc_v (ft²/day)OCRσ'_p (psf)
B-01S-38–10CH72451.820.560.070.0220.00321.0820
B-01S-514–16CH68411.710.520.0650.0210.00511.11,080
B-02S-38–10OH105632.450.880.110.0620.00181.0750
B-02S-514–16CH74471.880.590.0740.0240.00281.01,040
B-03S-411–13CL48251.350.310.0390.0120.01201.41,750
B-03S-618–20CH69431.770.530.0660.0210.00441.01,500

Design values selected: C_c = 0.56 (average CH); C_s = 0.07; C_α = 0.022; c_v = 0.004 ft²/day; e₀ = 1.82; one-way drainage (rock at 22 ft depth); H_dr = 14 ft (clay layer 0–22 ft; drainage to surface sand only).

12.10 Figure Placeholders
  1. Figure 12-1: Terzaghi primary consolidation model — spring-piston analogy with excess pore pressure isochrones.
  2. Figure 12-2: e–log σ' curve from consolidation test showing C_c, C_s, σ'_p (Casagrande construction).
  3. Figure 12-3: T_v vs. U(%) curve — both parabolic and logarithmic branches.
  4. Figure 12-4: Boussinesq stress distribution beneath embankment — centerline Δσ_v vs. depth.
  5. Figure 12-5: Time-settlement curve with primary and secondary phases labeled.
  6. Figure 12-6: Bridge approach transition — angular distortion diagram with settlement profile.
  7. Figure 12-7: Preloading surcharge concept — stress envelope, primary settlement timeline.
  8. Figure 12-8: Sublayer method diagram — compressible layer subdivided with midpoint stress states.
  9. Figure 12-9: FRA geometry car output — surface profile showing measured vs. allowable.
  10. Figure 12-10: Instrumentation plan for BNSF embankment monitoring — settlement plates and piezometers.

Reference graphics

Consolidation Test
Consolidation Test
Immediate vs. Consolidation Settlement
Immediate vs. Consolidation Settlement
Why Soil Consolidation Happens
Why Soil Consolidation Happens
Settlement Plate Installation
Settlement Plate Installation
12.11 Worked Calculation Examples
Example 12.1 — Embankment Settlement over Soft Clay — CSXT Brunswick, GA

Project context: CSXT new siding construction, Coastal Georgia. Proposed embankment: 10 ft of structural fill (γfill = 120 pcf) over 14 ft of normally consolidated soft CH clay (C_c = 0.56, e₀ = 1.82, c_v = 0.004 ft²/day, Cα = 0.022). Clay is underlain by dense sand (H_dr = 14 ft, one-way drainage to surface). Water table at 2 ft below original ground. CSXT ES requires total settlement ≤ 1.0 in. for Class 4 siding. Compute S_c and S_s; evaluate FRA compliance.

Step 1 — Initial effective stress at clay midpoint (z = 7 ft below original surface)

Surface to WT (2 ft): σ_v = 120_fill? No — original ground. Use γ_native = 110 pcf above WT.

σ_v(0–2 ft) = 2 × 110 = 220 psf

σ_v(2–7 ft) = 5 × (110 − 62.4) = 5 × 47.6 = 238 psf

σ'_v0 = 220 + 238 = 458 psf

Note: The clay top is at z = 0 ft (native ground surface); the midpoint of the 14-ft clay layer is at 7 ft depth below original surface.

At clay midpoint (7 ft into clay, WT at 2 ft):

Overburden above clay top: 220 psf (2 ft native soil above WT)

Weight of 7 ft of saturated clay: 7 × (110 − 62.4) = 7 × 47.6 = 333 psf

σ'_v0 = 220 + 333 = 553 psf

Step 2 — Stress increase from 10 ft embankment (strip load, B = 40 ft at base, for siding)

Using 2:1 distribution to midpoint of clay (z = 7 ft below fill base):

q_fill = γ_fill × H = 120 × 10 = 1,200 psf

Δσ = q_fill × B / (B + z) = 1,200 × 40 / (40 + 7) = 48,000 / 47 = 1,021 psf

(Full 2:1 formula for strip requires length; for continuous embankment L >> B, use Δσ_v,center ≈ q for z << B. Use Δσ = 1,021 psf as conservative estimate at centerline midlayer.)

Step 3 — Primary consolidation settlement (NC clay, Eq. 12-5)

Sc = [Cc / (1 + e₀)] × H × log[(σ'_v0 + Δσ) / σ'_v0]

= [0.56 / (1 + 1.82)] × 14 × log[(553 + 1,021) / 553]

= [0.56 / 2.82] × 14 × log[1,574 / 553]

= 0.1986 × 14 × log(2.846)

= 0.1986 × 14 × 0.4543

= 1.263 ft = 15.2 in.

Step 4 — Time to 90% consolidation (U = 90%, T_v = 0.848)

H_dr = 14 ft (one-way drainage)

t_90 = T_v × H_dr² / cv = 0.848 × (14)² / 0.004

= 0.848 × 196 / 0.004

= 166.2 / 0.004

= 41,544 days = 113.8 years

This is far too long for a construction schedule. PVDs or surcharge preloading must be specified.

Step 5 — Secondary compression (t₁ = end of primary; t₂ = 50 yr service life)

Assuming PVDs accelerate primary consolidation to t₁ = 180 days; service life t₂ = 50 yr = 18,250 days:

Ss = [Cα / (1 + ep)] × H × log(t₂/t₁)

ep ≈ e₀ − ΔeP = 1.82 − Cc × log(Δσ/σ'_v0 + 1) = 1.82 − 0.56 × log(2.846) = 1.82 − 0.254 = 1.566

Ss = [0.022 / (1 + 1.566)] × 14 × log(18,250/180)

= [0.022 / 2.566] × 14 × log(101.4)

= 0.00857 × 14 × 2.006

= 0.241 ft = 2.9 in.

Step 6 — FRA compliance check

Total post-construction settlement (after 90% primary complete with PVDs + 50 years secondary):

S_total = 0.10 × 15.2 + 2.9 = 1.52 + 2.9 = 4.4 in. >> CSXT limit of 1.0 in. for Class 4

Conclusion: Primary consolidation of 15.2 in. is unacceptably large; PVDs alone will not reduce the magnitude, only the time rate. Ground improvement is required — either (a) preloading with surcharge to achieve > 90% primary consolidation before track, combined with secondary compression acceptance, or (b) deep soil mixing or rigid inclusion columns to reduce compressible layer contribution. See Chapter 17. CSXT ES requires BNSF-equivalent settlement plate monitoring during surcharge loading.

Example 12.2 — Bridge Approach Fill Time-Rate — CN Manitoba

Project context: CN Prairie Subdivision, southern Manitoba. Bridge approach fill: 18 ft over 20 ft of soft silty clay (CL-ML: C_c = 0.35, C_s = 0.04, e₀ = 1.25, c_v = 0.08 ft²/day, OCR = 1.0). Two-way drainage (sand above and below clay). Design fill stress increase at midpoint: Δσ = 1,440 psf. CN ES requires settlement report in English and French; allowable post-construction settlement for CN Class 3 main line = 1.5 in. How long must preloading run to achieve ≤ 1.5 in. residual settlement?

Step 1 — Initial effective stress at clay midpoint (z = 10 ft into clay)

Water table at original ground surface (Manitoba prairie); γ_sat = 115 pcf:

σ'_v0 = 10 × (115 − 62.4) = 10 × 52.6 = 526 psf

Step 2 — Primary consolidation settlement

NC clay (OCR = 1.0); Eq. 12-5:

Sc = [0.35 / (1 + 1.25)] × 20 × log[(526 + 1,440) / 526]

= [0.35 / 2.25] × 20 × log[1,966 / 526]

= 0.1556 × 20 × log(3.738)

= 0.1556 × 20 × 0.5727

= 1.782 ft = 21.4 in.

Step 3 — Time to various degrees of consolidation (H_dr = 10 ft, two-way)

t = Tv × H_dr² / cv = Tv × 100 / 0.08 = Tv × 1,250 days

U = 50%: Tv = 0.197 → t = 246 days

U = 70%: Tv = 0.403 → t = 504 days

U = 80%: Tv = 0.567 → t = 709 days

U = 90%: Tv = 0.848 → t = 1,060 days (2.9 years)

Step 4 — Residual settlement at U = 90%

S_completed = 0.90 × 21.4 = 19.3 in.

S_residual (primary) = 0.10 × 21.4 = 2.1 in. > CN limit of 1.5 in.

Must achieve U ≥ 93% before track placement:

S_residual = (1 − U) × 21.4 ≤ 1.5 in.

1 − U ≤ 1.5/21.4 = 0.0701

U ≥ 93.0%

From the T_v formula for U > 60%:

Tv = −0.933 × log(1 − 0.930) − 0.085

= −0.933 × log(0.070) − 0.085

= −0.933 × (−1.155) − 0.085

= 1.078 − 0.085 = 0.993

t = 0.993 × 1,250 = 1,241 days = 3.4 years

Step 5 — CN ES requirement

CN ES Chapter 6 requires settlement plate monitoring at 500-ft intervals and monthly readings. This timeline (3.4 years) must be communicated to CN's Project Engineer. If the construction schedule cannot accommodate 3.4 years, PVDs at 5-ft triangular grid reduce H_dr from 10 ft to approximately 1.5 ft (effective radial drainage distance), cutting t_required to approximately:

t_PVD ≈ 1,241 × (1.5/10)² = 1,241 × 0.0225 = 27.9 days ≈ 4 weeks

This PVD option must be evaluated and costed in the design phase per Chapter 17.

Example 12.3 — Overconsolidated Clay Settlement — BNSF Intermodal Yard, Kansas City

Project context: BNSF intermodal expansion, Kansas City KS. New crane rail pavement slab: net load Δσ = 800 psf from slab and crane. Subgrade: 12 ft of stiff CH (C_c = 0.42, C_s = 0.05, e₀ = 0.88, σ'_v0 = 1,850 psf at midpoint, σ'_p = 4,200 psf, OCR = 2.27). UPRR EIM crane rail differential limit: 0.125 in. per 20 ft. Compute S_c.

Step 1 — Check whether Δσ exceeds σ'_p

σ'_v0 + Δσ = 1,850 + 800 = 2,650 psf

σ'_p = 4,200 psf

2,650 < 4,200 → Overconsolidated case; stress remains below σ'_p (Eq. 12-6)

Step 2 — Consolidation settlement using C_s only

Sc = [Cs / (1 + e₀)] × H × log[(σ'_v0 + Δσ) / σ'_v0]

= [0.05 / (1 + 0.88)] × 12 × log[2,650 / 1,850]

= [0.05 / 1.88] × 12 × log(1.432)

= 0.02660 × 12 × 0.1561

= 0.0498 ft = 0.598 in.

Step 3 — Secondary compression (50 yr service life)

Ss = [Cα / (1 + ep)] × H × log(t₂/t₁)

Cα = 0.04 × 0.42 = 0.017 (Mesri correlation)

ep ≈ 0.88 − 0.05 × log(1.432) = 0.88 − 0.0078 = 0.872

Ss = [0.017 / 1.872] × 12 × log(18,250/60)

= 0.00908 × 12 × log(304)

= 0.1090 × 2.483

= 0.271 ft → No, recalculate:

= 0.00908 × 12 × 2.483

= 0.2705 ft? Check: 0.00908 × 12 = 0.1090; × 2.483 = 0.2706 ft = 3.25 in.

Correction check — this seems high. Let me verify the time ratio: t₁ = 60 days (primary consolidation rapid in stiff OC clay with c_v ≈ 1.0 ft²/day; T_v,90 = 0.848, H_dr = 6 ft → t = 0.848 × 36 / 1.0 = 30.5 days; use t₁ = 31 days).

Revised: log(18,250/31) = log(588.7) = 2.770

Ss = 0.00908 × 12 × 2.770 = 0.302 ft = 3.62 in.

Wait — this is very large for secondary in stiff OC clay. Recheck C_α:

C_α = 0.04 × C_c = 0.04 × 0.42 = 0.0168

With H = 12 ft and 50-yr log ratio = 2.770:

Ss = [0.0168/1.872] × 12 × 2.770

= 0.00898 × 12 × 2.770 = 0.2983 ft = 3.58 in.

This result indicates secondary compression dominates for a 50-year service life even in OC clay. For the UPRR crane rail tolerance of 0.125 in. per 20 ft, differential secondary compression between two points 20 ft apart requires a spatial variation analysis. If secondary is spatially uniform (uniform layer), differential ≈ 0. If C_α varies laterally between borings, differential can be significant.

Step 4 — Total settlement and compliance

S_total = 0.598 + 3.58 = 4.18 in. over 50 years

S_primary only (construction phase) = 0.598 in. ← within UPRR crane rail limit

S_post-construction (secondary over 50 yr) = 3.58 in. — requires detailed differential analysis

Conclusion: Primary consolidation of 0.60 in. is acceptable for crane rail geometry at construction. However, 50-year secondary compression of 3.58 in. is a significant long-term concern; BNSF/UPRR intermodal yards require re-leveling of crane rails on a periodic cycle (typically every 10–15 years). This result should be communicated explicitly to the client in the geotechnical report's executive summary with a recommended crane rail re-leveling schedule. Ground improvement (deep soil mixing or stone columns per Chapter 17) can reduce C_α by replacing compressible material and is worth evaluating for the economic trade-off against long-term maintenance.

12.12 Practical Recommendations
  1. Always compute settlement before bearing capacity governs your design advice: For wide embankments over soft clay, settlement is virtually always the controlling limit state. A footing may pass bearing capacity (FS = 3.0) while the predicted settlement is 12 in. — a number that instantly triggers ground improvement requirements regardless of the bearing capacity outcome.
  2. Use the sublayer method for any clay layer > 5 ft: Treating a 20-ft clay layer as a single layer with midpoint stress overpredicts settlement for lightly loaded footings and underpredicts for heavily loaded ones. CSXT ES and Amtrak ES require sublayer analysis for clay layers > 10 ft.
  3. Distinguish OCR carefully — it changes the settlement by a factor of C_c/C_s (5–10×): A misidentified OCR (treating lightly overconsolidated clay as NC) can produce a tenfold overestimate of settlement. Casagrande construction on every consolidation test, confirmed by the stress history from geologic context, is mandatory. BNSF EI requires OCR determination from both consolidation test and CPTu K_D (Chapter 7) for cross-validation.
  4. Time-rate analysis must accompany every settlement estimate: The magnitude of settlement is useless to a railroad scheduler without knowing when it will occur. A 3-in. settlement in 2 weeks (from granular fill self-weight) is handled differently from 3 in. over 20 years (secondary creep). NSR ESM requires time-settlement curves to be submitted with every geotechnical report for bridge approach fills.
  5. Report residual settlement explicitly: The railroad owner needs to know what settlement will remain after construction and how much will develop over the first 5–10 years of service. CSXT ES and BNSF EI both require residual settlement predictions at years 1, 5, 10, and 25 as part of the geotechnical deliverable.
  6. Address approach-slab transition on every bridge project: The abutment-embankment angular distortion is the single most common cause of geometry exceptions on Class 4–5 mainlines. AREMA Chapter 8 approach slab design must be cross-referenced in the geotechnical report whenever the predicted embankment settlement exceeds 0.5 in. at the abutment interface.
  7. Flag secondary compression early for organic soils: For G&W Gulf Coast territory (Pt soils common) and CN Manitoba peatlands, secondary compression often exceeds primary consolidation. C_α/C_c ratios of 0.05–0.08 for organic soils require explicit long-term maintenance planning; recommend periodic light tamping cycles and document the expected frequency in the geotechnical report.
12.13 Settlement Analysis Checklist

Checklist · Part VI · Geotechnical Analysis

Settlement Analysis Checklist

Pre-Analysis0 of 6
Settlement Computation0 of 7
Time-Rate Analysis0 of 4
Deliverables0 of 6
Ticks are saved in this browser.
Plain text version

Pre-Analysis

  • [ ] Collect consolidation test results: C_c, C_s, e₀, c_v, C_α, σ'_p for all clay layers (Chapter 10)
  • [ ] Determine OCR from Casagrande construction; cross-check with CPTu K_D if available
  • [ ] Identify drainage boundaries (sand/gravel layers above/below clay; bedrock)
  • [ ] Confirm groundwater table: FEWL and SWL from Chapter 9
  • [ ] Compute effective stress profile with correct γ' = γ_sat − γ_w = 62.4 pcf
  • [ ] Confirm design load: DL, LL×DLF per client standard (Chapter 11)

Settlement Computation

  • [ ] Compute Δσ at midpoint of each sublayer (Boussinesq or 2:1)
  • [ ] Classify each layer as NC, OC with σ'_v0+Δσ < σ'_p, or OC crossing σ'_p
  • [ ] Apply correct equation (7-5, 7-6, or 7-7) for each sublayer
  • [ ] Sum sublayer settlements for S_c,total
  • [ ] Compute S_i (immediate) for granular soils or highly loaded stiff clays
  • [ ] Compute S_s (secondary) for OCR < 2 clays and all organic soils
  • [ ] Sum S_total; compare to FRA tolerance by track class (Table 12-1)

Time-Rate Analysis

  • [ ] Confirm H_dr (one-way or two-way); document drainage layer identification
  • [ ] Compute t_90 and t_95 using Eq. 12-11 and 7-13
  • [ ] If t_90 > project schedule, evaluate PVDs (Chapter 17) or surcharge preloading
  • [ ] Generate time-settlement curve; provide residual at Years 1, 5, 10, 25

Deliverables

  • [ ] Settlement calculation memorandum with all sublayer computations shown
  • [ ] Time-settlement curve (labeled with construction milestones and track placement date)
  • [ ] Residual settlement table (Years 1, 5, 10, 25 post-construction)
  • [ ] Angular distortion check at bridge approach transitions
  • [ ] Instrumentation plan if BNSF EI or NSR ESM monitoring required
  • [ ] Ground improvement recommendation (Chapter 17) if S_total exceeds tolerance
12.14 Practice Questions and Full Answers

Question 7.1 A 5-ft wide spread footing applies a net foundation pressure of 2,000 psf to a 10-ft thick layer of normally consolidated soft clay (C_c = 0.45, e₀ = 1.60, σ'_v0 = 500 psf at clay midpoint). Δσ at midpoint = 1,200 psf. Compute S_c.

Answer:

Sc = [Cc / (1+e₀)] × H × log[(σ'v0 + Δσ) / σ'v0]

= [0.45 / (1+1.60)] × 10 × log[(500+1200)/500]

= [0.45/2.60] × 10 × log[3.40]

= 0.1731 × 10 × 0.5315

= 0.920 ft = 11.0 in.

This large settlement would exceed FRA Class 4 limits (1.0 in. total) by a factor of 11; ground improvement or pile foundations would be required.

Question 7.2 A 15-ft thick normally consolidated silty clay has c_v = 0.10 ft²/day and two-way drainage. A railroad embankment is placed quickly. How long (in days and years) will it take to reach 90% primary consolidation? How much does PVD installation at 4.0-ft triangular spacing (effective diameter d_e = 4.5 ft → equivalent radial drainage = 0.564 × d_e = 2.54 ft) reduce this time?

Answer:

Without PVDs (H_dr = 7.5 ft, two-way):

t_90 = 0.848 × (7.5)² / 0.10 = 0.848 × 56.25 / 0.10 = 477 days = 1.31 years

With PVDs (radial drainage controls; use Barron's theory with H_dr ≈ d_e/2 = 1.27 ft for approximation): Radial c_h ≈ 2 × c_v = 0.20 ft²/day (horizontal > vertical in layered sediments):

t_90,PVD ≈ 0.848 × (1.27)² / 0.20 = 0.848 × 1.613 / 0.20 = 6.84 days

PVDs reduce the time to 90% consolidation from ~477 days to ~7 days — a 68× acceleration. This is why BNSF EI and NSR ESM specify PVDs for embankments over soft clay whenever the schedule requires track placement within 60–90 days of fill completion.

Question 7.3 An overconsolidated clay layer (C_c = 0.38, C_s = 0.048, e₀ = 0.95, σ'_v0 = 1,200 psf, σ'_p = 2,800 psf) has a thickness of 8 ft. An embankment imposes Δσ = 2,000 psf. Compute S_c, identifying which equation applies.

Answer:

Check: σ'_v0 + Δσ = 1,200 + 2,000 = 3,200 psf > σ'_p = 2,800 psf → Overconsolidated case crossing preconsolidation stress: use Eq. 12-7.

Sc = [Cs/(1+e₀)] × H × log(σ'_p/σ'_v0)

+ [Cc/(1+e₀)] × H × log[(σ'_v0+Δσ)/σ'_p]

Part 1 (recompression to σ'_p):

= [0.048/1.95] × 8 × log(2800/1200)

= 0.02462 × 8 × log(2.333)

= 0.02462 × 8 × 0.3680

= 0.0724 ft

Part 2 (virgin compression beyond σ'_p):

= [0.38/1.95] × 8 × log(3200/2800)

= 0.1949 × 8 × log(1.143)

= 0.1949 × 8 × 0.0580

= 0.0904 ft

Sc,total = 0.0724 + 0.0904 = 0.1628 ft = 1.95 in.

Note that treating this as NC (σ'_p = σ'_v0) would give: [0.38/1.95] × 8 × log(3.167) = 0.1949 × 8 × 0.5007 = 0.780 ft = 9.36 in. — a 4.8× overestimate, illustrating the critical importance of correct OCR determination.

Question 7.4 Explain why angular distortion is the critical settlement metric for railroad bridge approaches rather than total settlement, and provide the AREMA Chapter 8 limit for Class 4 track.

Answer: Total settlement at a bridge abutment is largely irrelevant if the abutment is pile-supported (total settlement ≈ 0) because the concern is not the absolute vertical position of the rail but the rate of elevation change along the track. When a rigid, pile-supported abutment (S ≈ 0) is adjacent to a settling approach embankment (S = 1–3 in. within 30 ft), the rail experiences a ramp or "bump" at the transition. If the change in elevation over a 62-ft chord exceeds FRA surface tolerances, the track geometry car flags a slow order and ultimately a stop. Angular distortion α = ΔS/L combines differential settlement with distance, capturing the sharpness of the grade change. AREMA MRE Chapter 8 limits angular distortion at approach transitions to 1/500 (i.e., 0.002 ft/ft) for Class 4 track — equivalent to 0.6 in. differential over 25 ft, or 1.5 in. over 62 ft. Approach slabs, sleepers, or geosynthetic reinforced approach zones are the standard mitigation tools.

Question 7.5 A soft clay embankment site for Amtrak NEC has predicted total primary settlement of 8.0 in. and secondary settlement of 1.5 in. over 50 years. Amtrak ES requires post-construction residual settlement ≤ 0.375 in. What degree of consolidation must be achieved before track placement, and is it feasible without PVDs if c_v = 0.006 ft²/day and H_dr = 12 ft?

Answer:

Required: residual primary settlement ≤ 0.375 − 0 = 0.375 in. (secondary is long-term; assume secondary only starts after track placement and is addressed by periodic track geometry maintenance).

Residual primary = (1 − U) × 8.0 in. ≤ 0.375 in.

1 − U ≤ 0.375 / 8.0 = 0.0469

U ≥ 95.3%

From T_v formula for U > 60%:

Tv = −0.933 × log(1 − 0.953) − 0.085

= −0.933 × log(0.047) − 0.085

= −0.933 × (−1.328) − 0.085

= 1.239 − 0.085 = 1.154

t = 1.154 × (12)² / 0.006

= 1.154 × 144 / 0.006

= 27,696 days = 75.8 years

Without PVDs, achieving U = 95.3% requires 76 years — clearly infeasible. With PVDs reducing H_dr to 1.5 ft (effective radial drainage, c_h ≈ 0.012 ft²/day):

t_PVD = 1.154 × (1.5)² / 0.012 = 1.154 × 2.25 / 0.012 = 216 days ≈ 7 months

PVDs are mandatory for this Amtrak NEC project. Amtrak ES requires instrumented monitoring (settlement plates every 200 ft, VW piezometers) throughout preloading, with readings submitted weekly and reviewed by Amtrak Structures Engineering before track placement authorization.

12.15 Cross-References
TopicChapter
SPT N₆₀ for E_s estimation in granular soilsChapter 6
CPTu and DMT for E_s, M, and OCR estimation in clayChapter 7
Atterberg limits for C_c estimation (Skempton)Chapter 8
Groundwater and effective stress; seasonal WT variationChapter 9
Bearing capacity (companion to settlement)Chapter 11
Slope stability of consolidating embankmentsChapter 13
Seismic-induced settlement in granular soilsChapter 14
PVD and surcharge preloading designChapter 17
Bridge approach settlement mitigationChapter 16
Subgrade deformation under repeated train loadingChapter 2
Settlement plate monitoring and inclinometer readingsChapter 15
Settlement analysis documentation in geotechnical reportsAppendix E
Consolidation test (ASTM D 2435) data and quality checksChapter 10

End of Chapter 12 — Settlement Analysis

Primary source: USACE EM 1110-1-1804, Geotechnical Investigations (January 2001). Settlement equations follow Terzaghi (1943), Skempton (1944), Mesri & Godlewski (1977), and FHWA GEC No. 5. FRA geometry tolerances per 49 CFR Part 213; AREMA MRE Chapter 8.

12.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S8 under Supplemental Sources.

Case Study 12.16.1 — Unit weight of fill: design assumes 127 pcf, the job measures more
Case study · Look (2023) §8.8

Related section: 12.3 Immediate (Elastic) Settlement

Look found that 127 pcf is used in about 70% of reports for fill unit weight. Compaction records give a large, cheap dataset to check it, and they are rarely used for that. On a Southeast Queensland project, 5,644 density tests had a 10% lower bound of 126 pcf, a median of 134 pcf and a 10% upper bound of 140 pcf. On a North Queensland road, imported fill mostly fell between 135 and 148 pcf, median 141.

On that second job the heavier fill caused more elastic settlement of a high embankment on competent ground than the bill of quantities had allowed for, and a contractual claim followed. Using the as-built 146 pcf instead of 20 gives about 15% more fill settlement. Look’s suggested unit weights for well-compacted fill:

  • cut to fill, no weathered rock: 127–134 pcf
  • cut to fill with residual soil and extremely to highly weathered rock: 127–146 pcf
  • imported quarry overburden: 134–153 pcf
  • imported quarry rock fill: 140–159 pcf

For railroad work: rail embankments are often high and wide, so a 15% settlement difference becomes a real quantity of fill to pay for. Feed the density test results back into the settlement and stability checks.

Design assumes a unit weight for settlement and stability; construction measures density only to pass or fail it, and the two are rarely compared.
Figure 12-LK1. Design assumes a unit weight for settlement and stability; construction measures density only to pass or fail it, and the two are rarely compared. Source: Look (2023), Figure 8.8-1, p. 265.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §8.8, pp. 266–268. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

  • USACE EM 1110-1-1804, Geotechnical Investigations (2001)
  • Terzaghi (1943); Skempton (1944); Mesri and Godlewski (1977) — consolidation and secondary compression
  • FHWA GEC No. 5, Evaluation of Soil and Rock Properties
  • FRA Track Safety Standards, 49 CFR Part 213
  • AREMA MRE Chapter 8

Supplemental sources (LEVI Library)

  • U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904
  • Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board
  • Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co.
  • Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §8.8

File locations for these documents are listed under Supplemental Sources — LEVI Library.

Project management sources

  • Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier)
Supplemental Sources — LEVI Library

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S7 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S8 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904
  2. Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board
  3. Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co.
  4. Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)
  5. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)
  6. Benesch. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. Colwell
  7. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 8 and 15
  8. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §8.8
  9. Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier). Used on this page for project-management material
← Previous · Part VI Chapter 11 — Foundation Engineering: Bearing Capacity
Next · Part VI → Chapter 13 — Slope Stability Analysis