NANCY
Railway Ground Hazard Risk Management · Part I · Railway Ground Hazard Risk Management
Sections · click a car to open it

Part I — Manual Overview

About this manual and how it is organized.
Authors: Daniel P. Colwell and Mario Ruel
I.1 Purpose of This Manual

Railway Ground Hazard Risk Management is a geotechnical reference for railroad work. It is organized around the way ground hazards affect track. It starts with the risk framework, then the track substructure that has to be protected, then the ways that substructure fails, and then how to explore, analyze and stabilize it. The manual was reorganized in September 2026 into nine parts.

It is written for geotechnical engineers, geologists and field staff delivering investigation, design, construction-phase and ground hazard risk management services to Class I, regional and short line railroads, and to passenger and commuter operators.

I.2 How the Manual Is Organized
PartTitleScopeContents
IRailway Ground Hazard Risk ManagementAbout this manual and how it is organizedPart I — Manual Overview
IIIntroduction to Railway Ground Hazard Risk ManagementThe risk framework that governs the rest of the manualChapter 1 — Introduction to Railway Ground Hazard Risk Management
IIITrack SubstructureBallast and subballast, subgrade, and the foundation elements beneath the trackChapter 2 — Track Substructure: Ballast, Subballast and Subgrade
Chapter 3 — Track Foundation Elements
IVFailure Mechanisms (Triggers)How track-support and ground-hazard failures develop and what sets them offChapter 4 — Failure Mechanisms and Triggers
VSubsurface ExplorationPlanning, borings, in situ testing, classification, groundwater and laboratory testingChapter 5 — Geotechnical Investigation Planning and Scope
Chapter 6 — Borings and Sampling
Chapter 7 — In Situ Testing
Chapter 8 — Soil and Rock Classification
Chapter 9 — Groundwater Characterization and Seepage
Chapter 10 — Laboratory Testing Program
VIGeotechnical AnalysisBearing capacity, settlement, slope stability and seismic hazardChapter 11 — Foundation Engineering: Bearing Capacity
Chapter 12 — Settlement Analysis
Chapter 13 — Slope Stability Analysis
Chapter 14 — Seismic Hazard and Liquefaction
VIIStabilization MethodsConstruction monitoring, retaining structures and ground improvementChapter 15 — Construction Monitoring and Field Testing
Chapter 16 — Retaining Structures
Chapter 17 — Ground Improvement Methods
VIIIPavementsPavement subgrade evaluation for yards, intermodal facilities and access roadsChapter 18 — Pavement Subgrade Evaluation
IXAppendixReport preparation, templates, special provisionsAppendix E — Geotechnical Report Preparation
Appendices A–C — Templates and Special Provisions
Ground Improvement Technology Library — Chapter 17, Section 17.16

Where the Geotechnology for Railroaders course modules are used in this manual

Benesch’s two-day Geotechnology for Railroaders course (Modules 1–8) is the field-training companion to this manual. Its concepts, case histories, field photographs and job-aid figures are cited in the chapters below. Use the course for crews and inspectors, and this manual for the engineering basis behind it.

Table I-2. Course module to manual chapter crosswalk
Course moduleWhere it appears in this manual
1 — Risk Management of Geo-HazardsChapter 1 (risk equation, classification, case histories, stabilization program)
2 — Geology and Soil EngineeringChapters 5, 6, 8, 10 and 18 (landforms, sampling, field identification, subgrade strength by feel)
3 — Track Substructure: Ballast and Sub BallastChapters 2 and 3 (ballast functions, fouling, undercutting, sub ballast, bridge approaches)
4 — Track DrainageChapters 2, 3 and 9 (cardinal rules, ditches, subdrains, culvert inspection)
5 — Slides and InstabilitiesChapters 4 and 13 (downhill and uphill slide categories, the four don’ts, signs of instability)
6.1 — Slope StabilizationChapters 13 and 16 (berms, realignment, driven and gravity walls, soil nailing)
6.2 — Subgrade StabilizationChapters 11, 15 and 17 (geosynthetics, HMA underlayment, grouting, EPS, screw piles)
6.3 — Scour and ErosionChapter 4 (scour mechanisms, countermeasures)
6.4 — Rock FallsChapters 4 and 13 (rockfall strategies, incident reporting)
6.5 — Beaver DamsChapter 4 (BAHA program, uphill dams, rapid drawdown)
6.6 / 7.1 — Winter Problems, Spring ThawChapters 2, 4 and 13 (frost heave, spring silt liquefaction, rapid drawdown)
7.2 / 7.3 — Extreme Weather, EarthquakesChapters 4 and 14 (event declaration, precipitation indices, seismic response criteria)

After Geotechnology for Railroaders Program, Module 1; course menu. Full reference under Supplemental Sources.

I.3 Using the Apps on a Desktop and a Phone

The manual is supported by a small set of apps on dirtbert.com. They run in any current web browser (Chrome, Edge, Safari or Firefox) on a desktop, laptop, tablet or phone. There is nothing to install and no account to create, except where a sign-in is noted below.

Table I-3. The apps, and how each one works on a desktop and on a phone
AppWhat it doesOn a desktopOn a phoneWhere your work is kept
GHRMThis manual: nine parts, 18 chapters and the appendices.Each chapter opens with an On this page list at the left and the section train across the top. Select a section heading to open it; Expand all opens every section.The page narrows to one column and On this page folds into a button at the top: tap it, then tap a section. Turn the phone sideways for wide tables.Checklist ticks are saved in this browser on this device.
MINA Hazard MonitoringLive river stage, flood, weather and tornado hazards along a railroad, with mileposts, bridges, crossings, rivers, soils and geology on one map.Desktop layout: the map setup panel, watchlist and hazard feed sit beside the map. Open full screen fills the monitor.Phone layout: the map fills the screen, with Map Setup, Gauges, Alerts and Status tabs along the bottom.Nothing is stored. The layout you pick is remembered in the browser. Data loads live from public sources, so a connection is needed.
NANCY Project WorkflowOne project carried through seven phases, from project set-up to the geotechnical report, with the Project Data pages: field log, boring log, laboratory results, design parameters and the two reports.Best for entering borings, samples and test results with a keyboard. Work the phases in order; you can go back to any earlier phase.Works for reviewing a project and for quick entries in the field. Wide tables scroll sideways.Only in this browser on this device. Use Save file to keep a copy or move the project to another computer or phone, and Open file to load it there. Clearing browser data deletes the stored project.

Monitoring a railroad with MINA

Opening MINA picks the layout for the device: phones get the phone layout and everything else gets the full-screen desktop layout. To switch, use Phone view on the desktop layout or Desktop on the phone layout; the choice is remembered in that browser. Then set up the map in four steps:

  1. Select a railroad. Its centerlines load first, and every other layer is filtered to it.
  2. Choose a base map: dark gray, satellite imagery or USGS topographic.
  3. Add sections: mileposts, bridges, crossings, rivers and gauges, weather hazards, flood zones, soils and geology. Layers follow the notebook numbering (01.01, 04.05 and so on); some only draw once you zoom in closer.
  4. Launch the map. Use Find on the line to jump to a subdivision and milepost, a bridge or a crossing.

The river stage watchlist lists gauges near the line against their flood stages, and the hazard feed lists warnings on the selected network. MINA is a monitoring aid; it is not for operational dispatch decisions.

Running a project in NANCY

NANCY asks every user to read and accept the Use and Disclaimers once in each browser before its pages open; the acceptance is remembered after that. Start at NANCY and work the phases in order. Each phase page explains what is done and why, and links to the Project Data pages and the chapters of this manual that support it. Borings and samples entered on the field log appear on the boring log, laboratory results attach to their samples, and each stratum’s tested values become its design parameters. Where a property has no test, NANCY uses a conservative published correlation and marks the value as assumed.

Because the project is kept only in the browser, save a file at the end of each session. To move between a desktop and a phone, use Save file on one device and Open file on the other. Every value NANCY produces must be checked by a qualified, licensed engineer.

Keeping the apps on a phone

Open the app in the phone’s browser and add it to the home screen so it opens like an app:

  • iPhone or iPad (Safari): tap Share, then Add to Home Screen.
  • Android (Chrome): tap the ⋮ menu, then Add to Home screen.

Good candidates are MINA’s phone layout, NANCY, and the chapter you use most in the field.

Where the apps appear in this manual

  • Apps for this Chapter: a green card at the top of every chapter lists the apps that support it, with a line on what each one is for there.
  • Checklists: sections marked with a checklist save your ticks in the browser and can be printed.
I.4 Conventions and Standards Basis
  • Units: English (U.S. customary) units throughout, with SI in parentheses where a source equation is SI-based.
  • Loading: Cooper E-80 and 286,000-lb gross rail load are the default design bases unless the client specifies otherwise.
  • Governing references: AREMA Manual for Railway Engineering; FRA Track Safety Standards (49 CFR Part 213) and Bridge Safety Standards (49 CFR Part 237); ASTM test methods; FHWA and USACE guidance; and each client railroad's engineering standards, which govern where they differ.
  • Client values: Client-specific criteria quoted in this manual are summaries for planning. Always confirm them against the client's current standard before use on a project.

Reading European (UIC / EN) railway sources alongside AREMA

Several sections of this manual draw on Profillidis, Railway Management and Engineering, which is written to UIC and European (EN) practice in metric units. AREMA and FRA remain the governing basis for North American work; the European material is included for the mechanics, the data and the design logic behind it. The terms and units below appear wherever that material is cited.

Table I-1. Terms and units used where this manual cites Profillidis
European / UIC termNorth American equivalent or conversion
SleeperTie (crosstie)
Track bedBallast + subballast together
Formation layerEngineered top-of-subgrade layer; comparable in role to a blanket or prepared subgrade layer
SubsoilNative or embankment fill below the formation layer
Cant / cant deficiencySuperelevation / unbalanced superelevation
Longitudinal, transverse, horizontal defectSurface (profile), cross-level, alignment
t (metric tonne) — axle load1 t = 2,205 lb; a 286,000-lb car on 4 axles ≈ 32.4 t/axle
kp/cm² (kilopond per cm²)1 kp/cm² ≈ 14.2 psi
t/mm (track or layer reaction coefficient)1 t/mm ≈ 56 kip/in.
‰ (per mille) gradient10‰ = 1.0% grade
MGT / million tons of trafficSame concept; UIC counts gross metric tons

UIC axle-load categories for standard gauge: A = 18 tons, B = 20 tons, C = 22 tons, D = 25 tons. Profillidis notes that standard-gauge axle loads in the USA are 28–35 tons, so European design charts calibrated to 22–25 tons sit well below North American heavy-haul loading. Rail stress is reported to grow roughly with Q3 to Q4 (Q = axle load), so a modest axle-load increase produces a much larger increase in fatigue.

UIC line groups (UIC Code 714R) classify lines by a fictitious daily tonnage Tth that weights freight, locomotive and speed effects: group 1 > 130,000 t/day; group 2 = 80,000–130,000; group 3 = 40,000–80,000; group 4 = 20,000–40,000; group 5 = 5,000–20,000; group 6 < 5,000 t/day. Group 4 is described as representative of most lines worldwide. Several UIC thickness and maintenance rules in this manual are keyed to these groups.

Regulation, specification, code, standard and guideline are not interchangeable. In the book’s usage, regulations and specifications are rules issued by governmental or inter-governmental bodies that impose specific instructions or methods; codes are a form of legislation defining a procedure or performance to be followed; standards are uniform criteria developed by a national or international body and are suggested rather than obligatory; guidelines are non-mandatory recommendations.

After Profillidis (2014), §7.5 (axle and traffic load), §12 footnote (definitions). Conversions added by the authors. Full reference under Supplemental Sources.

Supplemental Sources

Sections on this page marked “After Profillidis (2014)” draw on the document below. Text is summarized or paraphrased; tables are transcribed or reproduced with their original source noted; figures and photos are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design.

  1. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)
  2. Benesch. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. Colwell
Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This part was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

This part summarizes and organizes material from the chapters that follow; see the Author and Sources section at the end of each chapter for the works cited.

Next · Part II → Chapter 1 — Introduction to Railway Ground Hazard Risk Management