Appendix E — Geotechnical Report Preparation

Formerly Geo Rail Chapter 15 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel

Geotechnical Services Manual for Railroad Clients

A Consultant's Reference for Delivering Geotechnical Engineering Services Across North American Railroad Capital Programs

Apps for this Chapter4
E.0 Executive Summary

The geotechnical report is the primary contract deliverable. It is the document upon which the railroad's project engineers, structural engineers, and construction contractors rely to design foundations, size retaining walls, specify embankment fill, and plan construction sequences. A technically sound investigation that is poorly reported is as damaging to a railroad capital program as a poorly executed one — and far more common.

This chapter defines the structure, format, content, and quality standards for geotechnical reports delivered to all nine client railroads. It distinguishes between a Geotechnical Data Report (GDR) and a Geotechnical Design Report (GDR/FGR), explains the executive summary writing framework, defines the required technical sections, specifies boring log and lab data presentation formats, describes calculation appendix organization, covers Geotechnical Special Provisions (GSP) integration, details PE seal requirements, and documents electronic deliverable formats, version control, and comment resolution protocols. All nine client engineering standards are cross-referenced.

E.1 Background: Two Fundamental Report Types

All nine client railroads recognize — explicitly or implicitly — the distinction between two geotechnical deliverables:

E.1.1 Geotechnical Data Report (GDR)

The GDR presents factual subsurface data without interpretation or design recommendations. It is the appropriate deliverable for competitive bid projects where multiple engineering firms will use the same data to develop their own designs, and for early-phase investigations where design parameters have not yet been finalized.

GDR Contents:

  • Project description and investigation scope
  • Boring location plan
  • Boring logs (factual; no interpretation)
  • Laboratory test data tables
  • Groundwater observations
  • Geophysical data (GPR, MASW) — processed, not interpreted
  • No design recommendations, no geotechnical parameters, no analysis

GDR Users: Contractors preparing bids; design engineers developing conceptual foundations; railroad project development group.

E.1.2 Geotechnical Design Report (GDR/FGR)

The GDR/FGR (sometimes called a Final Geotechnical Report or Foundation/Geotechnical Report) presents factual data, interpreted parameters, analysis, and design recommendations. It is the primary deliverable for sole-source design contracts.

GDR/FGR Contents: Everything in the GDR plus:

  • Geologic interpretation
  • Engineering classification and property tables
  • Foundation bearing capacity analysis
  • Settlement analysis
  • Slope stability analysis
  • Seismic hazard and liquefaction assessment
  • Ground improvement design (if applicable)
  • Retaining wall design parameters
  • Construction recommendations
  • Geotechnical Special Provisions (GSP)
  • Calculation appendix
  • PE-sealed signature block
Supplemental reference · LEVI Library

Preliminary vs. final reports (FHWA)

FHWA adds a timing dimension to the GDR/FGR distinction. Issue a preliminary geotechnical report whenever early data or evaluation can shape the design — typically on large projects or complex sites where alignment or grade might change because of the geotechnical findings. The final report follows once alignment, grade and geometry are fixed and specific recommendations can be made. Whatever the format, FHWA lists five essentials: (1) all exploration data (profile, logs, lab and in-situ results, groundwater); (2) interpretation and analysis; (3) specific design recommendations; (4) discussion of anticipated problems and their solutions; and (5) recommended geotechnical special provisions. FHWA also notes that the report is used during design, during construction and after completion when resolving claims — one reason to write every statement as if it will be read by someone looking for a basis for a claim.

Source: Federal Highway Administration (2017). What is a Geotechnical Report? Geotechnical Engineering fact page

Supplemental reference · LEVI Library

A third type: the emergency site-assessment letter

After a slope failure or washout the railroad needs a decision within a day or two, not a GDR. A 2018 preliminary site assessment for CSXT at MP BNA-56.0 (Shortline Subdivision, WV) illustrates the format. It is a two-page letter plus photographs and a sketch, issued the day after a site visit held two days after the event.

  • Site and problem: 25-mph mainline, 3–5 trains/day, on a side-hill cut about 80 ft above a river. A 70-ft cut slope has a 35-ft rock face at its base. After two weeks of heavy rain and a short intense storm, mud and rock debris slid down a gully from about 80 ft above the track, filled the ditch and covered the track for 50–60 ft. A 10-mph slow order and a night watchman were in place.
  • Observations: a bowl-shaped scarp about 100 ft wide, seeps of about 1–2 gpm, severe tension cracks around the perimeter, and a private driveway above that had cracked and settled about 24 in. (Figures E-S1 and E-S2). Track drainage and a nearby culvert were functioning.
  • Assessment: the remaining material is marginally unstable and will likely come down, with timing driven by rainfall and seepage. It could carry on past the track and take the track structure with it. The right-of-way line was unknown, but most of the source appeared to be off railroad property — a point worth stating explicitly because it affects who can act.
  • Recommendations: keep monitoring, especially during and after rain; keep the ditch and shoulder cleared to maximize catchment; consider removing unstable material mid-slope (access is difficult); remove at-risk trees but leave root systems in place.

The structure — who/when/why, site and problem, observations, assessment, prioritized interim actions, and photos keyed to a sketch — is a useful template for GDR/FGR programs that begin with an emergency.

Source: Amec Foster Wheeler (2018). Preliminary Site Assessment of Slope Instability at CSXT MP BNA-56.0, Shortline Subdivision, near Clarksburg, WV (draft letter report, April 6, 2018)

Supplemental figures · LEVI Library
Mudslide debris at the toe of the cut, looking east (CSXT MP BNA-56.0, April 2018).
Supplemental Figure E-S1. Mudslide debris at the toe of the cut, looking east (CSXT MP BNA-56.0, April 2018). Source: Amec Foster Wheeler (2018). Preliminary Site Assessment of Slope Instability at CSXT MP BNA-56.0, Shortline Subdivision, near Clarksburg, WV (draft letter report, April 6, 2018).
Tension cracks at the head of the slide above the track.
Supplemental Figure E-S2. Tension cracks at the head of the slide above the track. Source: Amec Foster Wheeler (2018). Preliminary Site Assessment of Slope Instability at CSXT MP BNA-56.0, Shortline Subdivision, near Clarksburg, WV (draft letter report, April 6, 2018).
E.2 Report Format by Client
Table E-1. Geotechnical Report Format Requirements by Railroad Client
RailroadReport Title ConventionRequired FormatPE Seal RequiredElectronic FormatSubmittal PlatformReview Turnaround
CSXT"Geotechnical Report — [Project Name]"CSXT standard templateYes (project state)PDF + ProjectWise uploadProjectWise20 business days
NSR"Geotechnical Investigation Report — [Project ID]"NSR standard outlineYes (project state)PDF email to PE of RecordEmail + SharePoint15 business days
G&W"Geotechnical Report — [Line Name, MP]"Consultant formatYes (project state)PDF emailEmail15 business days
UPRR"Geotechnical Report — [Project Title, PSA No.]"UPRR template preferredYes (project state)PDF + UPRR portal uploadProcore/UPRR portal20 business days
BNSF"Geotechnical Report — [Project Name, CWS No.]"BNSF standard formatYes (project state)PDF + BIM 360BIM 360 (Autodesk)20 business days
CPKC"Geotechnical Engineering Report — [Project No.]"CPKC format (bilingual for Canadian projects)Yes (project state/province)PDF + CPKC SharePointSharePoint20 business days
Amtrak"Geotechnical Report — [Contract No., Corridor]"Amtrak PEIS formatYes (project state)PDF + Amtrak CMSCMS portal30 business days (NEC)
CN"Geotechnical Investigation Report — [CN Project No.]"CN standard outlineYes (project state/province)PDF + CN SharePointSharePoint20 business days
AREMANo specific formatPer AREMA MRE Ch. 1 AppendixPer state boardPDFClient-directedPer contract
E.3 Report Structure — Required Sections

The following section structure satisfies the requirements of all nine client railroads when tailored to the specific client format. Sections in bold are mandatory for GDR/FGR; unmarked sections are GDR-only.

E.3.1 Cover Page and Title Block

Required elements:

  • Report title (per client naming convention)
  • Railroad client name and project number
  • Project location (county, state, milepost or station)
  • Consultant firm name, address, and project number
  • Report date and revision number
  • Client project engineer name (if known)
  • PE seal block: "Prepared by: [Name, PE, License No., State, Expiration Date]"
E.3.2 Executive Summary

The executive summary is the most-read section of any geotechnical report. Railroad project engineers often read only the executive summary before forwarding to procurement or construction. It must be self-contained and decision-ready.

Executive Summary Framework (PREP Method):

  1. P — Purpose and Scope (2–3 sentences): What was investigated, where, and for what project?
  2. R — Results (3–5 sentences): What conditions were found? What are the key parameters?
  3. E — Engineering Conclusions (3–5 sentences): What do the conditions mean for design? What are the critical findings?
  4. P — Practical Recommendations (numbered list): What should the design and construction teams do?

Length: 1–2 pages maximum. Never include equations, boring log references, or ASTM test numbers in the executive summary.

Example Executive Summary Opening (NSR format):

"This report presents the results of a geotechnical investigation performed at the NSR Shenandoah Valley Division bridge replacement at MP 128.4 near Waynesboro, Virginia. The investigation included four borings (B-1 through B-4) advanced to depths of 40–55 ft, Standard Penetration Tests at 2.5-ft intervals, and laboratory testing on selected samples. Subsurface conditions consist of 8–12 ft of mixed fill and residual silty clay overlying weathered greenstone bedrock, with competent rock encountered at 14–22 ft depth below existing ground surface..."

E.3.3 Introduction
  • Project description and railroad context
  • Scope of geotechnical services
  • Referenced standards (AREMA MRE Chapters, client engineering standards, ASTM methods, USACE EM 1110-1-1804)
  • Report organization
E.3.4 Site Conditions
  • Site location and access (RWP zone, dispatch block)
  • Surface topography and drainage
  • Existing track structure and milepost references
  • Adjacent structures
  • Published geologic mapping reference
  • USGS quadrangle reference
  • FEMA flood zone designation

Reference graphics

Engineering Geology
Engineering Geology
E.3.5 Field Investigation Program
  • Boring layout rationale (referenced to investigation plan from Chapter 5)
  • Drilling method (HSA, mud rotary, etc. — per Chapter 6)
  • SPT procedure and correction chain (N₆₀, (N₁)₆₀ per Chapter 6)
  • Sampling: Shelby tube locations, core intervals
  • In situ tests performed (CPT, VST, MASW — per Chapter 7)
  • Groundwater observations (date, depth, stabilized level)
  • Boring location plan (plan view drawing — Figure 1)

Reference graphics

Geotechnical Investigation
Geotechnical Investigation
E.3.6 Laboratory Testing Program
  • Summary of tests performed (indexed to boring and sample number)
  • Reference to laboratory test data tables (Appendix B)
  • QC/QA notes (accreditation, split-sample check results)
E.3.7 Subsurface Conditions
  • Geologic setting and stratigraphy narrative
  • Soil and rock description by unit (USCS, AASHTO, RQD if applicable)
  • Engineering property summary table (key design parameters by stratum)
  • Groundwater conditions (FEWL, SWL, seasonal assessment)
  • Cross-section profiles (Figure 2 — geologic profiles along track alignment)
E.3.8 Engineering Analyses

For GDR/FGR only. One subsection per analysis type performed:

E.3.8.1 Foundation Bearing Capacity (cross-reference Chapter 11)

  • Vesić equation results for each structure; recommended allowable bearing capacity table; pile capacity results

E.3.8.2 Settlement Analysis (cross-reference Chapter 12)

  • Sublayer model description; computed S_total per structure; comparison to FRA tolerance; serviceability conclusions

E.3.8.3 Slope Stability (cross-reference Chapter 13)

  • Critical cross-sections analyzed; FS results table by condition; minimum FS vs. AREMA requirements

E.3.8.4 Seismic Hazard and Liquefaction (cross-reference Chapter 14)

  • USGS NSHM site class; screening result; FS_L table if triggered

E.3.8.5 Pavement Subgrade / Track Subgrade (cross-reference Chapters 18, 2)

  • CBR/M_r results; design section recommendation; FI data if ballast was sampled

E.3.8.6 Ground Improvement (cross-reference Chapter 17)

  • Method justification; design parameters; expected performance

Reference graphics

Comparison of Geotechnical Models
Comparison of Geotechnical Models

Trackbed findings the design report should carry

For track rehabilitation and substructure projects, the analyses section should present the following, so that the maintenance recommendation can be traced to evidence:

  • A layer profile for each pit or trench: thickness, ASTM D2488 description, color, and the fouling index of each ballast zone.
  • The identified source of fouling or mud (ballast breakdown, subgrade pumping, spillage), with the test that supports it.
  • The drainage condition: outlets, ditch flow lines, and the critical rainfall rate implied by the measured fouling (Chapter 2, Table 2-SW5).
  • Reclaimable stone against undercut depth, where cleaning is an option.
  • The remedy matched to the cause, with short-term and long-term options separated (Section IV, Table 4-SW1).
  • For any geosynthetic recommendation, the basis for the AOS, a field-trial or monitoring plan, and the alternative granular design.

After Selig & Waters (1994), chs. 12, 14 and 16. Full reference under Supplemental Sources.

E.3.9 Conclusions and Recommendations

Numbered list of actionable engineering recommendations. Each recommendation must:

  1. State what to do
  2. Give the governing parameter (e.g., "allowable bearing pressure = 3,500 psf")
  3. Reference the supporting section or calculation
  4. Note any special condition or caveat

Reference graphics

Top 5 Geo Site Red Flags
Top 5 Geo Site Red Flags
Example format:

"3. Design spread footings on the dense sand stratum (Stratum B) at a minimum depth of 4.5 ft below existing grade with an allowable bearing pressure of 3,500 psf (gross). Settlement under design load is estimated at 0.5–0.8 in. (see Section 8.2). Confirm footing bearing elevation in the field during excavation. Notify the geotechnical engineer if the sand stratum is not encountered within 1.0 ft of predicted depth."

E.3.10 Limitations and Conditions of Use

Standard risk-allocation language required by all nine client railroads:

  • Scope limitation: investigation was performed for stated project only; not valid for other locations
  • Temporal limitation: conditions valid at time of investigation; seasonal groundwater variability may affect design
  • Data density: borings are point data; conditions may vary between borings
  • Changed conditions: if excavation reveals conditions differing from report, notify geotechnical engineer before proceeding
  • Report ownership: report prepared for named client; reliance by third parties without written consent is not permitted

UPRR, BNSF, and CSXT require the limitations clause to include a specific sentence regarding the proprietary nature of client engineering standards referenced in the report.

Supplemental reference · LEVI Library

Owner requirements that shape the field program and the report (CSX Public Projects Manual)

  • Access: borings and other investigative work on CSX property need a Temporary Right-of-Entry agreement. That agreement expressly excludes environmental investigation: no soil, sediment, groundwater or surface water sampling for chemical analysis without a separate Environmental Right-of-Entry. Keep geotechnical sampling clearly geotechnical and say so in the report.
  • Overhead bridges: at least one boring for each substructure unit adjacent to the track must accompany the design submittal, with enough information to design shoring and foundations.
  • Shoring next to track: not required only if the excavation stays outside a 1H:1V line from the bottom corner of the tie and the track is on level ground or in a cut on stable soil. Excavating the toe of an embankment without shoring is not permitted. Design shoring for active pressure plus a 1,882-psf live-load surcharge on an 8.5-ft-wide strip, distributed by the AREMA Ch. 8 strip-load formula — much higher than a uniform equivalent surcharge (compare Section 16.3).
  • Soil and water: soil generated on CSX property must be reused on CSX property (with Environmental Department approval) or disposed of at a CSX-approved facility; contractors may not take it off-property. Dewatering discharges need prior approval. The report’s earthwork and dewatering recommendations should assume these constraints.

Source: CSX Transportation (2020). Public Projects Manual, December 2020, incl. Soil and Water Management Policy

Report content and the geotechnical longitudinal section

Profillidis summarizes investigation results in two deliverables: the geotechnical report and the geotechnical longitudinal section along the alignment. His example is the Channel Tunnel profile, routed within a blue chalk layer that proved resistant to water inflow (Figure E-11). The report should give clear recommendations on:

  • geotechnical description of each layer;
  • hydrogeological data: maximum and minimum piezometric levels and drainage requirements;
  • construction methods, earthwork heights and suitability of excavated soils for reuse;
  • recommended slopes, embankment design and any special techniques such as reinforced soil;
  • mechanical properties of the soils and bearing capacity of the subgrade.

For linear railway projects, a longitudinal section that carries strata, groundwater, the track profile and the location of structures is often the most-used figure in the report. It belongs in the figures package with the boring location plan.

Figures · click to zoom

Figure E-11. Geotechnical longitudinal section along the Channel Tunnel, United Kingdom to France. Profillidis Fig. 9.1.
Figure E-11. Geotechnical longitudinal section along the Channel Tunnel, United Kingdom to France. Profillidis Fig. 9.1.

After Profillidis (2014), §9.2.5, Fig. 9.1. Full reference under Supplemental Sources.

E.4 Boring Log Presentation
E.4.1 Required Boring Log Fields

Each boring log must contain (minimum fields per AREMA and client standards):

Header Block:

  • Project name, project number, client railroad
  • Boring ID, location (station + offset, latitude/longitude), ground surface elevation
  • Drilling contractor, drilling method, bit size
  • Date started, date completed
  • Logged by (name, title, certification), approved by (PE name, license)
  • Page number and total pages

Column Layout (left to right):

ColumnContent
Depth (ft)Depth scale, major depth marks every 5 ft
Graphic LogUSCS symbol pattern for each stratum
RecoveryCore recovery or SPT recovery (%)
SPT N-valueRaw N, N₆₀, (N₁)₆₀ (three columns)
Sample IDSample type (SS, ST, RC) and ID
Water Content (%)Field moisture at sample depth
DescriptionUSCS classification, color, consistency, structure
RemarksLab tests assigned, anomalies, notes

Footer Block:

  • Water level readings: date, depth to water during drilling, depth at boring completion, stabilized level
  • PE seal and signature

Reference graphics

Pile Boring Log
Pile Boring Log
Borehole Correlation Soil Layer Interpretation
Borehole Correlation Soil Layer Interpretation
E.4.2 Graphic Log Symbols

Use ASTM D2488 standard symbols for graphic log patterns. All nine client railroads accept ASTM D2488 symbols. Client-specific symbol modifications (e.g., CSXT uses a unique "ballast" symbol for borrow verification borings) must be noted in the legend.

E.4.3 SPT N-Value Presentation

Plot N₆₀ as a bar chart on the boring log (bar length proportional to N₆₀; 50-blow refusal plotted as solid bar to the column edge with "50/X" notation). Tabulate raw N, E_m (%), C_B, C_R, C_S, N₆₀, C_N, and (N₁)₆₀ in the calculation appendix; show only N and N₆₀ on the boring log face for clarity.

Reference graphics

SPT N Values and Trends
SPT N Values and Trends
Project management · Levy (2007)

Differing Site Conditions, Report Disclaimers and the Boring Location Plan

Levy (2007) notes that a large share of construction disputes arise during sitework, when excavation exposes ground that does not match what the geotechnical report led bidders to expect. A boring describes the strata only at its own location, and a hole drilled a few yards away can show something quite different. Standard report disclaimers say so, and often add that the owner should carry an allowance for foundation costs that cannot be known until construction. Levy points out that this cuts both ways: the disclaimer concedes that actual conditions will only be revealed by excavation, and the recommended allowance is really a contingency for the owner’s benefit, since the owner commissioned and paid for the report.

To support a differing-conditions claim the contractor must show that (1) the contract documents indicated certain conditions that formed the basis of the bid, (2) its reading of those documents was reasonable, (3) the conditions encountered differed materially, (4) they could not reasonably have been anticipated, and (5) the costs claimed arise solely from the difference. Recoverable delay costs can include direct labor and equipment, weather-shifted work, acceleration, idle rented equipment, extended field office and home-office overhead, and lost productivity. On unit-price public work Levy cites a common yardstick that quantities varying by 20% or more from bid quantities may justify repricing.

Source example. On a two-building campus project with an “unclassified” site, rock was found at about El. 162.8 where boring B-23 showed rock at El. 152, and other areas did not match the logs either. The owner rejected a $288,000 rock claim. By sliding a transparent overlay of the boring location plan over the building footprint, the contractor showed that the geotechnical engineer had plotted every boring about 50 ft west of its true position; shifted 50 ft east, all logs matched the field conditions, and the owner paid. On a second project, unsuitable soil below the footing “payline” was settled by agreeing on a reasonable limit to the depth the contractor “owned” on an unclassified site.

For railroad work: Boring location plans for embankment, culvert and bridge work should be tied to railroad stationing (milepost and track centerline offset) and surveyed coordinates, and checked against the plan sheets before issue; a plotting error is indefensible once a contractor finds it. Log presentation should state the date of water readings and note where conditions between borings are inferred. Keep disclaimer language factual and pair it with clear baseline statements (for example, expected top of rock or depth of soft fouled subgrade) so that the railroad and contractor share one reference for judging whether a condition is truly different.

Test boring location plan from the case in which every boring had been plotted about 50 ft from its true position relative to the building footprint.
Figure E-PM1. Test boring location plan from the case in which every boring had been plotted about 50 ft from its true position relative to the building footprint. Source: Levy (2007), Figure 12.1.

Source: Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill, pp. 271–281. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

E.5 Laboratory Data Tables
E.5.1 Required Table Format

Present lab results in a single master table (Appendix B) with:

ColumnDescription
Boring IDBoring identifier
Sample IDSample number and type
Depth (ft)Top and bottom of sample interval
USCSUnified classification symbol
LL / PL / PIAtterberg limits
% FinesPercent passing No. 200 sieve
γ_d (pcf)Dry unit weight from Proctor or shelby tube
w (%)Natural water content
s_u (tsf)Undrained shear strength (UU triaxial or vane)
c' (psf), φ' (°)Effective strength parameters (CU/CD triaxial)
C_c / C_rCompression indices (consolidation test)
c_v (ft²/day)Coefficient of consolidation
σ'_p (tsf)Preconsolidation pressure
k (ft/day)Hydraulic conductivity
CBR (%)California Bearing Ratio
NotesTest method, remarks

Completeness: Every sample assigned a lab test on the investigation plan (Chapter 5, Section 5.7) must appear in the table, even if the result is "not tested" due to sample disturbance, with a note explaining why.

Reference graphics

Tests for Soil
Tests for Soil
E.6 GDR vs. FGR: Client Distinctions
Table E-2. GDR vs. FGR Requirements by Railroad Client
RailroadGDR Allowed?FGR Always Required?GSP Required in Report?Calc Appendix Required?Notes
CSXTYes (competitive bid)Yes (sole source)YesYesCSXT prohibits design recoms in GDR
NSRYes (competitive bid)Yes (sole source)YesYesNSR requires split submittal: data then design
G&WUsually FGR onlyYesNo (separate GSP)YesG&W accepts combined memo format for small projects
UPRRYes (competitive bid)Yes (PSA)YesYesUPRR requires all calc appx in MathCAD or Excel
BNSFYes (competitive bid)Yes (PSA)YesYesBNSF requires BIM 360 upload of all appx files
CPKCYesYesYesYesBilingual req't for Canadian territory reports
AmtrakYes (pre-PE)Yes (PE phase)YesYesNEC reports require independent peer review
CNYesYesYesYesCN requires metric conversion table in appendix
AREMAPer projectPer projectRecommendedRecommendedAREMA has no mandatory format
Project management · Twort and Rees (2004)

Unforeseen Ground Conditions Claims and What the Report Must Support

Twort and Rees treat claims for unforeseen ground conditions as among the hardest a resident engineer handles. Their discussion is based on Clause 12 of the UK ICE conditions, which is broadly comparable to the differing-site-conditions clauses in North American contracts. The contractor may claim for physical conditions, other than weather, that could not reasonably have been foreseen by an experienced contractor. Their main points:

  • Deleting the clause does not remove the risk. Bidders simply add a premium, and the owner pays it whether or not bad ground is found. Bidders usually cannot drill their own borings, so price is their only defense.
  • “Everything” descriptions do not work. Describing the excavation as “all materials including boulders, rock and running sand” does not override the clause, because the extent of each material is still undefined.
  • Magnitude is the usual issue. Often the event itself was foreseeable and what was unforeseen was its scale. Their example is a hard siltstone band that was logged in the borings but then stayed in the tunnel crown for a long distance. If borings show variable ground, a contractor cannot be expected to have foreseen uniformly bad ground.
  • Payment. The contractor recovers costs reasonably incurred plus a reasonable profit: labor (including standing time and uneconomic working), materials (including abandoned temporary measures), plant working and standing, site overheads and justified head-office costs. The resident engineer’s own daily records are the check.
  • Prevention. Their first precaution for minimizing claims is an adequate site investigation, followed by complete design and documents before bidding.

The authors note that a fair clause often means the owner pays no more than if the condition had been known and written into the contract.

For railroad work: The decision to issue a factual report only, or a factual report with a design report, determines what an “experienced contractor” can reasonably be expected to have foreseen. To make a later claim decidable:

  • Describe the variability, not just the average. Show the range of depth to firm subgrade along the track and the stations where borings are widely spaced.
  • State plainly where conditions between borings are interpreted rather than observed.
  • Put quantities that depend on ground conditions (undercut depth, rock excavation, obstructions under embankments) into unit-price or provisional items in the GSPs rather than lump sums.

When a claim arises, the boring logs, the report’s stated variability and the inspector’s daily records are the evidence the railroad will rely on.

Source: Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann, pp. 212–219, 223–224. Summarized and paraphrased. Full reference under Supplemental Sources.

Project management · Goldbloom (1989)

Differing Subsurface Conditions Clauses and the Factual/Interpretive Split

Goldbloom argues that subsurface risk belongs mostly with the owner, because only the owner has the time and budget to explore the site. Bidders get a few weeks to price the work and cannot drill their own borings. If each of several bidders had to do that, the owner would pay for the same exploration several times over. Borings and test pits show conditions only at the points sampled, so some differences during construction should be expected. A Differing Subsurface Conditions (changed conditions) article covers this. Its trigger is a condition that (1) differs materially from what the contract documents indicate, or (2) could not reasonably have been anticipated, and that (3) materially affects the cost of the work. The contractor must give notice before the condition is disturbed. The engineer then investigates, and if the claim is justified, an equitable adjustment is made in writing.

The book’s case history comes from a reservoir project that included a railroad relocation. Excavation for the dam was paid under two items, Earth Excavation and Rock Excavation. Rock was defined as ledge that needed drilling and blasting. At one abutment the contractor hit cemented glacial till that a 2½-CY shovel could not dig, and the borings had not shown it. The contract had neither a disclaimer nor a changed-conditions clause. The engineer still recommended paying for the extra drilling and blasting on force account, and the dispute was settled without litigation.

Goldbloom’s disclosure rules:

  • Disclose everything the designer knew, or should have known from records available to it. Withholding information invites misrepresentation claims.
  • State who drilled the borings and when, and where bidders can inspect the samples and cores. Note that samples dry out in storage, and that groundwater readings reflect conditions at the time they were taken.
  • Keep factual data separate from interpretation. In general, do not disclaim the factual data. Recommend that bidders have the interpretations reviewed by their own qualified specialist.
  • Reference reports by others can be furnished “for information only”, clearly marked as not part of the contract documents.

For railroad work: The GDR/FGR split described in this chapter maps onto Goldbloom’s factual/interpretive distinction. Bid packages for undercutting, cut-slope or culvert jobs should include the factual report: logs, lab data, groundwater observations with their dates, and GPR or ballast-fouling records. Interpretive design documents should be labeled as such. The pay-item definitions for excavation classes (common, rock, boulders, unsuitable subgrade) need to match how the logs describe materials, because the cemented-till case turned on that definition. Confirm with the railroad’s contracting group whether its standard agreement includes a changed-conditions article. If it does not, put the gap on the project risk register.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 37–39, 182–186, 298–300. Summarized and paraphrased. Full reference under Supplemental Sources.

E.7 Geotechnical Special Provisions (GSP) Integration

GSP are the contract-ready construction specification sections derived from the geotechnical design. They are included as an appendix to the GDR/FGR and are incorporated by reference into the project's construction contract. All nine client railroads require GSP for sole-source projects.

E.7.1 GSP Structure (per AREMA format)

Each GSP section follows:

  1. Scope — what work is covered
  2. Materials — specification by ASTM, AASHTO, or AREMA standard; approval process
  3. Equipment — type, minimum weight/energy, restrictions
  4. Construction Methods — sequence, lift thickness, moisture conditioning
  5. Testing and Acceptance — frequency, method, pass/fail criteria
  6. Measurement and Payment — unit, pay item description

See Appendix C of this manual for complete GSP template language for: earthwork, fill compaction, ballast/subballast, ground improvement, deep foundations, dewatering, and instrumentation.

E.7.2 GSP Coordination with Structural Engineer

The geotechnical consultant produces GSP for geotechnical work only. Structural concrete, steel, and track work GSPs are the responsibility of the structural and track engineers. At the pre-design meeting, confirm the division of GSP responsibility in writing to avoid gaps or duplications.

Supplemental reference · LEVI Library

What a Class I earthwork specification actually says: CSX private sidetracks (2016)

GSPs should not contradict the owner’s own standard specification. The CSX Standard Specifications for Private Sidetracks contains these geotechnical requirements:

ItemRequirement
Unsuitable material in cutsRemove AASHTO A-2-6, A-2-7, A-4, A-5, A-6, A-7 to at least 2 ft below subgrade, ditch line to ditch line (more if local conditions require)
Muck in fill sectionsRemove A-8 within the toes of slope; where fill exceeds 10 ft, excavate a width of 3× the fill height
Embankment lifts≤ 6 in. loose; no frozen or organic material; not on frozen ground; bench into existing slopes; no stones > 6 in. within 2 ft of subgrade
Embankment density95% of modified Proctor (ASTM D1557), with moisture adjusted
Finished subgrade± 0.10 ft of design; no depressions that hold water
Subballast95% modified Proctor; ± 0.10 ft; not placed on wet or rutted roadbed; AREMA Ch. 1 §2.11 materials; gradation (graded aggregate / crusher run) 1½ in. 100/100, No. 10 30–55 / 15–45, No. 200 5–12 / 5–12
Geotextile (when specified)On finished subgrade, no equipment on bare fabric, 2-ft end overlaps, 18-in. side overlaps, no longitudinal overlaps between ballast toes, turned down 2 ft at abutments
Around structuresNo wet or impervious fill; 6-in. layers placed evenly on both sides; no large stones within 2 ft of arches, boxes or large pipes
Riprap¼ to 16 ft3 angular stone, minimum 3 ft thick on slopes in contact with streams

Check against Section 15.2.1: the client compaction table there lists 90% relative compaction for CSXT embankments. The CSX sidetrack specification requires 95% of modified Proctor for embankments as well as subballast. Confirm the governing CSXT document for each project and cite it in the GSP.

Source: CSX Transportation (2016). Standard Specifications for Private Sidetracks (Industrial Sidetrack Manual), September 15, 2016

Project management · Haidar (2016)

Float, Float Ownership and Geotechnical Hold Points in Special Provisions

Haidar defines four kinds of float in arrow notation, where activity ij has duration dij and T(E) and T(L) are the earliest and latest event times:

Table E-PM1. Float definitions (after Haidar 2016, Eqs. 3.6–3.8)

FloatDefinitionMeaning
Total (TF)T(L,j) − [T(E,i) + dij]Delay that will not move completion; belongs to the path and is shared by every activity on it
Free (FF)T(E,j) − [T(E,i) + dij]Delay that will not move the early start of any successor; belongs to the activity
InterferingTF − FFPortion that, if used, takes float from successors
IndependentSuccessor early start − predecessor late finish − durationFloat available even in the worst case for both neighbors

Because total float is shared, using it on one activity reduces it for all later activities on the path. Haidar stresses that the contract should say who owns float. The common default is that the project owns it and whoever uses it first gets it. An extension of time is then due only when an owner-caused event is predicted to push total float below zero on a path that is critical to completion. A contractor who wants a private buffer should show it as a time contingency in the baseline. NEC3 Clause 63.3 preserves terminal float when planned completion is earlier than the contract date. He also notes that in resource-constrained schedules the float concept, and sometimes the critical path itself, breaks down.

For railroad work: GSPs often create geotechnical hold points that act as schedule constraints. Examples include a settlement or piezometer monitoring period before the next fill lift or before final track surfacing, a load test before production piles, and a curing and verification period for treated ground. Write each hold point into the GSP with a stated minimum duration and the measurable criterion that ends it, so that bidders put it in the baseline schedule rather than treating it as float. Say whether an extension caused by monitoring results is an excusable delay, and coordinate that wording with the railroad’s contract staff. Treat track windows and outages as fixed constraints in the same way. A hold point that is clearly specified seldom produces a dispute; an unstated one usually does.

Float shown as the time between the early and late completion of the last project in a program.
Figure E-PM2. Float shown as the time between the early and late completion of the last project in a program. Source: Haidar (2016), Fig. 3.9.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 71–75, 78. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Project management · ASCE (2013)

Planning GSP Production: Scope-of-Work Memorandum and Review Flow

The ASCE guide recommends a planned specification production process instead of copying the last similar job. Copied specifications carry irrelevant requirements and repeat past omissions. Small projects are not exempt: the guide notes that small jobs often produce large claims because of careless or incomplete documents.

Its flow chart has thirteen steps:

  1. Agree the scope and specification philosophy with the owner.
  2. Obtain the owner’s contract terms and standard specifications.
  3. Review them for applicability to the project.
  4. Outline the required sections and set a production schedule.
  5. Draft outline specifications. Decide early on special clauses such as differing site conditions, price escalation, schedule incentives and dispute review boards.
  6. Hold technical reviews.
  7. Owner review.
  8. Expand the drafts.
  9. Constructability and engineering review.
  10. Owner review.
  11. Resolve comments in meetings.
  12. Prepare and submit the final draft.
  13. Owner issues the documents for bid.

Steps 10 to 12 often repeat. Reviews should include field staff who will inspect the work and experienced construction people who can spot constructability problems.

The first document produced should be a scope-of-work memorandum. It lists the areas and types of work, the items furnished by the owner or others, and the specification sections and drawings required. The memorandum is a management tool and not a contract document. Its content later goes into the Summary of Work and the agreement, which lets technical sections stay generic.

Other points from the guide:

  • Drawings carry quantities, dimensions and geometry. Specifications carry quality. Duplicating information between them almost always produces conflicts.
  • Assign testing responsibility explicitly, and state which results mean acceptance or rejection.
  • Research field conditions during design. A clause that makes the contractor verify existing conditions does not replace that research. Resolve known unknowns with the owner as contract requirements.

For railroad work: Treat GSP integration as a scheduled, budgeted deliverable, not a task for the end of the report. A geotechnical scope memo for a culvert replacement or slide repair would record:

  • which GSPs are needed (earthwork, shoring, dewatering, ground improvement, instrumentation);
  • which items the railroad supplies, such as ballast, flaggers, track work by railroad forces and disposal sites;
  • how each GSP ties to the factual and interpretive reports.

Get the railroad’s standard specifications and agreement forms at Step 2, since many Class I railroads have their own. Include the resident engineer or construction manager in the constructability review.

Specification production in three stages (conceptual, preliminary review, intermediate/final), showing where owner reviews, technical reviews and constructability reviews fall before documents are issued for bid.
Figure E-PM3. Specification production in three stages (conceptual, preliminary review, intermediate/final), showing where owner reviews, technical reviews and constructability reviews fall before documents are issued for bid. Source: ASCE (2013), Specification Processing Flow Chart.

Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 6–12, 16–17, 22–23, 29–30. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental Sources.

Project management · Spain (1995)

Defining Rock, Uncertain Work and Bulking When Linking the Report to the Bid Documents

Spain’s commentary on how the CESMM3 measurement rules work gives several points that apply directly when a geotechnical report feeds a bid package.

  • Define rock in geological terms, tied to the borehole logs. The definition of rock decides how much rock excavation is paid, so it belongs in the preamble to the bid schedule. Spain advises against the familiar wording “material which in the opinion of the Engineer can only be removed by blasting, pneumatic tools or wedges,” because it leaves the taker-off, the estimator and the site staff uncertain. He recommends using the same terms as the boring logs.
  • Measure the full excavation depth across layers. The commencing surface is the top of the whole excavation and the excavated surface is its bottom, however many layers lie between them. Stripping over a cut-and-fill site can produce two items for the same work. A note in the preamble, or a wider item description, avoids that.
  • Measure net, from the drawings. Round sensibly, considering the effect on the total.
  • Use a provisional sum, not provisional quantities. Where the design is not developed enough for real quantities, carry the work as a provisional sum in the general items. Do not use provisional quantities, which invite high rates on small items that pay off when the quantities grow. Carry a separate general contingency.

Spain’s data chapter gives bulking factors for converting excavated volume to loose volume:

Table E-PM2. Table: Bulkage of excavation, percent increase over in-place volume (after Spain 1995, Chapter 9)

MaterialBulkage (%)
Soil (general)25
Gravel15
Sand12.5
Heavy clay30
Rock30
Chalk50

For railroad work: when the report’s recommendations become special provisions:

  • Write the rock-excavation definition from the logged descriptions, such as weathering grade, RQD and refusal criteria, so that the pay line matches the subsurface profile in the report.
  • Carry the uncertain parts as a provisional sum, with the reason stated in the report. Examples are the depth of soft subgrade below a planned undercut and the extent of a slide that is still moving.
  • State plainly that bid quantities are neat in-place volumes. Haul and disposal volumes are then the contractor’s calculation, using bulking factors like those above or values measured on site.

Source: Spain, B. (1995). Taking Off Quantities: Civil Engineering. London: E & FN Spon, pp. 10–11, 19, 23, 194. Summarized and paraphrased. Full reference under Supplemental Sources.

E.8 Calculation Appendix

The calculation appendix must be organized to allow independent checking by the railroad's PE reviewer. Standard organization:

Reference graphics

Top 10 Geo Formulas
Top 10 Geo Formulas
Appendix C — Calculations (subdivided):
  • C-1: SPT correction chain (N to (N₁)₆₀ for all borings)
  • C-2: Bearing capacity calculations (one subsection per structure)
  • C-3: Settlement calculations (one subsection per structure or segment)
  • C-4: Slope stability analysis output (FOS summary sheet + SLOPE/W or SLIDE input/output)
  • C-5: Seismic / liquefaction calculations (CSR, CRR, FS_L by boring)
  • C-6: Pavement/subgrade design (SN equation, CBR, frost if applicable)
  • C-7: Ground improvement design (if applicable)
  • C-8: Pile capacity calculations (static + WEAP/CAPWAP if applicable)
  • C-9: Earth pressure / retaining wall calculations (if applicable)

Each calculation subsection must show:

  • Design basis (which loads, which parameters, from which section/table)
  • All equations written out (not coded into a black-box spreadsheet)
  • Intermediate results clearly labeled with units
  • Final result clearly highlighted
  • Reference to applicable figure, section, or standard

UPRR and BNSF: Require MathCAD Prime or Microsoft Excel (formula-visible) for all calculations. No PDF-only calculation packages.

Amtrak: Requires a separate independent design check by a second PE for all NEC foundation and retaining wall calculations.

E.9 PE Seal Requirements
Table E-3. Professional Engineer Seal Requirements by Client
RailroadReport SealCalc Appendix SealGSP SealIndependent CheckSeal State
CSXTYesYesYesNo (standard projects)Project state
NSRYesYesYesNoProject state
G&WYesYesNo (for small projects)NoProject state
UPRRYesYesYesNo (< $5M); Yes (≥ $5M)Project state
BNSFYesYesYesNo (< $5M); Yes (≥ $5M)Project state
CPKCYesYesYesNoProject state/province
AmtrakYesYesYesYes (all NEC projects)Project state
CNYesYesYesNoProject state/province

Digital PE Seal: All nine client railroads accept a digitally applied PE seal (per applicable state board rules) on PDF documents provided the seal meets state board digital signature standards. A scanned wet-seal image is not a digital seal — confirm with state board.

Multi-state projects: When a project crosses a state line (CSXT SE Division crossing Georgia/Tennessee, for example), the PE must be licensed in both states, or two PEs must co-seal (one per state). Confirm this with the client project engineer before the report is finalized.

Reference graphics

Engineering Ethics — Integrity, Responsibility, Public Trust
Engineering Ethics — Integrity, Responsibility, Public Trust
E.10 Electronic Deliverables and Version Control
E.10.1 File Format Requirements
Table E-4. Electronic Deliverable Formats by Client
DeliverableCSXTNSRUPRRBNSFCPKCAmtrakCNG&W
Main ReportPDF/APDF/APDF/APDF/APDF/APDF/APDF/APDF
Boring LogsPDFPDFPDFPDFPDFPDFPDFPDF
CAD Drawing (boring plan)DWG 2018DWG 2018DWG 2020DWG 2020DWG 2020DWG 2020DWG 2018DWG/PDF
CalculationsPDF + sourcePDF + ExcelPDF + MathCADPDF + ExcelPDF + sourcePDF + sourcePDF + sourcePDF
GSPDOCX + PDFDOCX + PDFDOCX + PDFDOCX + PDFDOCX + PDFDOCX + PDFDOCX + PDFPDF
Lab DataPDF + CSVPDF + CSVPDF + CSVPDF + CSVPDF + CSVPDF + CSVPDF + CSVPDF
GPR DataInterpreted PDFInterpreted PDFFull dataset + PDFFull dataset + PDFFull dataset + PDFFull dataset + PDFFull dataset + PDFPDF only
E.10.2 Version Control Naming Convention

Recommended file naming convention (compatible with all client document management systems):

[ClientCode]_[ProjectNo]_GeoRpt_[DocumentType]_Rev[##]_[YYYYMMDD].pdf

Example:

NSR_22-4182_GeoRpt_MainReport_Rev01_20260515.pdf

NSR_22-4182_GeoRpt_BoringLogs_Rev01_20260515.pdf

NSR_22-4182_GeoRpt_Calculations_Rev01_20260515.pdf

Revision tracking:

  • Rev00 = Issued for Internal Review (not transmitted to client)
  • Rev01 = Issued for Client Review (first submittal)
  • Rev02 = Issued for Client Review (after comment resolution)
  • Rev03 = Issued for Construction (final, PE-sealed)

Include a revision history table on the cover page showing revision number, date, description of changes, and PE initials for each revision.

E.10.3 Comment Resolution Log

When the client returns review comments:

  1. Compile all comments into a Comment-Response Matrix (Word or Excel)
  2. Each row: Comment No. | Source | Section Ref. | Comment Text | Response | Revised Section Reference
  3. Responses must be one of: "Revised as requested" | "Revised, see [section]" | "Not revised — see explanation"
  4. Disagreements with client comments must be escalated to the client project engineer in writing — never silently not incorporated
  5. Return the Comment-Response Matrix with the next revision submittal

UPRR and BNSF require the Comment-Response Matrix to be submitted in their project management portal (Procore and BIM 360, respectively) with each revision.

E.11 Worked Examples
Example E-1: CSXT Embankment — Executive Summary (PREP Method)

Purpose and Scope: This Geotechnical Design Report presents the results of a subsurface investigation for the proposed CSXT Central Division track extension at MP 221.4 near Macon, Georgia. The investigation, performed in March 2026, included six borings (B-1 through B-6) advanced to depths of 20–40 ft, SPT testing at 2.5-ft intervals, Shelby tube sampling at three locations, and laboratory consolidation, triaxial, and Atterberg limit testing on selected samples.

Results: Subsurface conditions consist of 3–8 ft of loose to medium-dense silty fine sand fill (Stratum A) overlying soft to firm brown kaolin-rich clay (Stratum B, SPT N = 2–6 blows/ft, s_u = 320–480 psf) extending to 18–28 ft depth. Dense residual silty sand (Stratum C, N > 30 blows/ft) was encountered beneath Stratum B at all boring locations. Groundwater was encountered at 4–6 ft depth and stabilized at 3.5 ft below existing grade.

Engineering Conclusions: The soft Stratum B clay presents two critical design challenges: (1) total consolidation settlement of 8.4–11.2 in. under the proposed 12-ft embankment load, and (2) a factor of safety against slope failure of 0.82 under rapid fill placement — well below the CSXT-required minimum of 1.25. The dense Stratum C is adequate for spread footing or driven pile support of bridge structures within this project segment.

Practical Recommendations:

  1. Implement staged embankment construction with PVDs at 6-ft triangular spacing (see Section 7 and Appendix C-6); allow minimum 80% consolidation between stages before advancing fill.
  2. Design spread footings on Stratum C with allowable bearing capacity of 4,000 psf (see Appendix C-2); minimum embedment 3.5 ft into Stratum C.
  3. Do not use end-bearing piles in Stratum A or B; tip elevation must be confirmed in Stratum C.
  4. Install settlement plates and piezometers per instrumentation plan (Figure 5); provide monitoring data to CSXT project engineer within 24 hours of each reading.
Example E-2: UPRR Structure — Calculation Appendix Header Format

Below is the standard header format required by UPRR Engineering Instruction Manual for each calculation subsection:

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

CALCULATION APPENDIX C-2: BEARING CAPACITY — PIER 2 FOOTING

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Project: UPRR Columbia River Bridge Replacement

Project No.: 2026-UPRR-0042

Client: Union Pacific Railroad

Location: Milepost 183.2, Portland Subdivision, OR

Date: June 1, 2026

Prepared by: [Name], PE, Oregon License No. XX-XXXX

Checked by: [Name], PE

DESIGN BASIS

Design load: Dead: 180 kips; Live: 220 kips (Cooper E-80, DLF 1.3)

Footing geometry: B = 8 ft, L = 10 ft, D_f = 4.5 ft (embedment)

Soil parameters: φ' = 34°, c' = 0 psf, γ = 121 pcf (from Table 5-2, Stratum C)

Water table: 7.5 ft below grade (SWL, boring B-3, 03/15/26)

References: Vesić (1975); AREMA MRE Ch. 8; UPRR Eng. Instr. Manual Sec. 4

CALCULATION

[Step-by-step calculation follows using all variables defined above]

RESULT

Allowable bearing capacity: q_allow = 4,200 psf (gross)

Applied pressure: q_applied = (180,000 + 220,000) / (8 × 10) = 5,000 psf — EXCEEDS

Action required: Increase footing to B = 10 ft, L = 12 ft → q_applied = 3,333 psf < 4,200 psf ✓

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Example E-3: Comment Resolution — NSR Review Response

Comment No. 07 (from NSR project engineer review, Report Rev01):

"Section 7.3: The settlement analysis uses C_c = 0.35 for Stratum B, but the lab data table (Appendix B) shows C_c values of 0.28, 0.31, 0.39, and 0.42 for the four consolidation tests. Please justify the value used or revise."

Response:

"Comment accepted. The design value C_c = 0.35 was selected as the average of the four laboratory consolidation test results (0.28 + 0.31 + 0.39 + 0.42)/4 = 0.35; however, this was not explained in the text. Per NSR Engineering Standards Manual Section 3 recommendation to use a conservative representative value for settlement calculations, we have revised to use C_c = 0.40 (the mean of the two higher values, reflecting the softer material likely to govern total settlement) and have updated Section 7.3 and Appendix C-3 accordingly. Settlement estimate is revised to 10.1–13.4 in. (was 8.4–11.2 in.). Recommendation 1 (staged construction with PVDs) is unchanged. See revised Section 7.3 and Appendix C-3, Rev02."

E.12 Representative Report Outline

The following outline satisfies all nine client railroad requirements for a GDR/FGR:

COVER PAGE

TABLE OF CONTENTS

LIST OF FIGURES

LIST OF TABLES

1.0 EXECUTIVE SUMMARY

2.0 INTRODUCTION

2.1 Project Description

2.2 Scope of Investigation

2.3 Report Organization

3.0 SITE CONDITIONS

3.1 Location and Access

3.2 Topography and Drainage

3.3 Existing Structures and Track

3.4 Published Geologic References

4.0 FIELD INVESTIGATION

4.1 Boring Program

4.2 Drilling Methods

4.3 Sampling and Testing

4.4 Groundwater Observations

5.0 LABORATORY TESTING

5.1 Program Summary

5.2 Results Overview (detail in Appendix B)

6.0 SUBSURFACE CONDITIONS

6.1 Geologic Setting

6.2 Stratigraphy and Soil/Rock Description

6.3 Engineering Properties Summary Table

6.4 Groundwater Conditions

7.0 ENGINEERING ANALYSES

7.1 Foundation Bearing Capacity

7.2 Settlement Analysis

7.3 Slope Stability (if applicable)

7.4 Seismic Hazard and Liquefaction (if applicable)

7.5 Track Subgrade Evaluation (if applicable)

7.6 Ground Improvement (if applicable)

8.0 CONCLUSIONS AND RECOMMENDATIONS

9.0 LIMITATIONS AND CONDITIONS OF USE

FIGURES

Fig. 1 Site Location Map

Fig. 2 Boring Location Plan

Fig. 3 Geologic Profile (along alignment)

Fig. 4 Geologic Profile (cross-section)

Fig. 5 Instrumentation Plan (if applicable)

APPENDIX A BORING LOGS

APPENDIX B LABORATORY TEST DATA

APPENDIX C CALCULATIONS

APPENDIX D GEOTECHNICAL SPECIAL PROVISIONS

APPENDIX E FIELD EXPLORATION PHOTOGRAPHS

Project management · Oberlender (2000)

Design Proposals and “Mini-Drawings” as a Budgeting Tool

Oberlender’s chapter on design proposals is written for the design-side project manager, who must turn a sponsor’s request for proposal into an engineering scope, a work-hour budget and a schedule. The key steps:

  • Lock the assumed scope. Where the RFP is vague and the sponsor cannot clarify it, define the scope as well as you can, budget it, and document the assumptions back to the sponsor. When better information arrives, that portion is re-priced.
  • Discipline detail sheets. Each discipline lead converts the project definition into a discipline scope, a specification list and a preliminary drawing list. With the discipline manager, the lead estimates work-hours by personnel category. The project manager then adds project management, clerical and reproduction hours.
  • Mini-drawings. These are quick hand sketches on letter-size sheets, one for each full-size sheet expected in the final set, in final order, with plans, sections and details blocked out. They give an early sheet count, show the expertise needed, support the work-hour estimate, and later serve as drafting assignments and a progress record.
  • Sanity checks. Compare drawings per facility, hours per drawing, design cost as a percentage of construction cost, and expected duration against past projects. Confirm that the people in the budget will actually be available.
  • Contingency. The most common error in design schedules is leaving no allowance for permit delays, client review time and slow responses to information requests.

He also recommends budgeting design in work-hours rather than dollars, because hours are what drive design.

For railroad work: The “mini-drawing” translates directly into a mini-report, a one-page-per-item dummy of the geotechnical report. List each figure (site location, boring location plan, subsurface profile along the track centerline, cross-sections at each repair station, stability output sheets), each appendix (boring logs, lab summary, calculations, GSPs) and each table, and assign estimated hours to every item. Building this dummy from the report outline in this appendix during the proposal makes the sheet and figure count visible. It also exposes scope the client may not have priced, such as a second cross-section for a slide that extends past the original limits, and gives a ready basis for the client-review allowance and the peer-review hours required under I.11.

Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 118–134. Summarized and paraphrased. Full reference under Supplemental Sources.

E.13 Figure Placeholders
  • Figure E-1. PREP method executive summary framework: annotated example showing Purpose, Results, Engineering Conclusions, and Practical Recommendations in a two-page format.
  • Figure E-2. Required boring log header format (annotated): all mandatory fields per AREMA and client standards.
  • Figure E-3. Laboratory data master table format (annotated sample showing 10 borings, 25 samples).
  • Figure E-4. Report file naming convention decision tree: client code, project number, document type, revision, and date fields.
  • Figure E-5. Comment-Response Matrix format (spreadsheet extract): columns for comment number, source, section, comment text, response, revised section, and reviewer initials.
  • Figure E-6. Calculation appendix cover sheet format: header block, design basis, result summary, and PE signature block.
  • Figure E-7. PE seal placement: page-level seal location on cover page; digital seal application workflow for PDF/A format.
  • Figure E-8. ProjectWise upload workflow: folder structure, file naming, metadata tags, and transmittal generation (CSXT-specific).
  • Figure E-9. GDR vs. FGR decision flowchart: contract type × project phase × client → report type.
  • Figure E-10. Report revision history table format: columns for revision number, date, description, changed sections, and PE initials.

Reference graphics

Pile Boring Log
Pile Boring Log
Engineering Reports Explained
Engineering Reports Explained
E.14 Practical Recommendations
  1. Write the executive summary last. It must accurately reflect the analysis, not the assumptions made at the start of the project. Draft it after all calculations are reviewed and conclusions are firm.
  2. Use client-specific terminology throughout. NSR calls track extensions "capacity projects"; UPRR refers to PSA task orders by CWS number; BNSF uses "CWS project number" in all document headers. Using client-standard terminology signals familiarity with the client's program and avoids the perception of a generic deliverable.
  3. Never embed critical parameters only in calculation appendices. If a load-bearing recommendation depends on a specific value of φ' or c', that value must appear in the body of Section 6 (engineering properties table) AND in Section 8 (recommendations). Structural engineers who receive the report may not open the calculation appendix.
  4. Submit a draft boring log to the client before the report. For projects with any geologic uncertainty, submit draft boring logs within 5 business days of completion of field work. This allows the client's PE to flag concerns — soft zones, unexpected rock, groundwater anomalies — before the report analysis is finalized. All Class I clients welcome early data sharing.
  5. Track all report versions in a single master file list. Use the naming convention in Section E.10.2 consistently. Project records are subject to litigation discovery for 7–10 years after construction. A clear version history prevents confusion about which calculations governed final design.
  6. Document field changes to boring scope in writing. When a boring is terminated early, relocated, or added to address unexpected conditions, document it in a brief field memorandum to the client project engineer on the same day. Do not simply adjust the boring logs after the fact.
  7. Verify PE license currency before sealing. Every sealing PE should confirm their license is active and in good standing in the specific project state before sealing documents. Multi-state projects with tight delivery schedules have failed due to a PE's license lapsing in a required state. Add license verification to the project initiation checklist.
Supplemental reference · LEVI Library

When the report is about a failure

Forensic reports are read by lawyers as well as engineers. Rao (2016) recommends a fixed scope. Compulsory: survey and document the distress; review all design documents, the original investigation and the construction records; interview those involved. Optional: additional investigation, special tests and NDT of structural elements. The report should cover authority and scope, history, summary of original documents, data collected, interviews, meteorological and earthquake information, investigations and results, analysis and conclusions. Parameters must represent the actual site condition (avoid unvalidated empirical correlations), because the engineer must be able to justify them in court.

ISSMGE TC302 Task Force 10 reviewed about 100 failures from Asia, South America and Europe. Roughly half were caused by design shortcomings (including the ground model and parameters), about a fifth each by inadequate site investigation and unforeseen phenomena, and about a seventh by construction. In the Asian cases, inadequate investigation caused about half the failures, and in 60% of those no investigation had been done at all. Recommendations that belong in every railroad report’s QA process: a desk study with a geological framework on every project, adequate investigation funding, design by engineers who know their limits, independent checking or peer review of designs and construction methods, qualified oversight during construction, and publishing lessons from failures.

Source: Rao, V. V. S. (2016). “Guidelines for Forensic Investigation of Geotechnical Failures,” and Jessep, R. A., de Mello, L. G. and Rao, V. V. S. (2016). “Technical Shortcomings Causing Geotechnical Failures: Report of Task Force 10, TC 302.” In Rao and Sivakumar Babu (eds.), Forensic Geotechnical Engineering. Springer India

Project management · Hutchings (2004)

Differing Site Conditions and the As-Planned / As-Built / Adjusted Schedule Method

Hutchings describes changed conditions, also called unforeseen or differing site conditions, as a standard clause in federal contracts that is increasingly used by other public owners. The policy behind it is that the owner accepts certain subsurface and latent-condition risks so that bidders do not have to carry large contingencies for them. His examples of qualifying conditions include a buried pipeline that is missing from the drawings or shown in the wrong place, unusually severe weather for the season and location, and expansive clay in the excavation that was not identified in the geologic survey or the prior soil investigations. He notes that severe weather may be ruled excusable (time only) but not compensable.

He also lists constructive changes, informal owner acts or omissions that increase cost or time. These include defective plans and specifications, the engineer’s interpretation of documents, demanding a higher standard than specified, improper rejection of work, changes in method or sequence, and owner nondisclosure of pertinent facts. The contractor must give written notice within the contract period or may waive the claim.

To measure the time effect of a change after the fact, Hutchings uses three schedules:

  1. As-planned – the accepted baseline.
  2. As-built – the historical schedule built from the periodic updates, which contains every effect that actually occurred.
  3. Adjusted – the as-built with the effect of the one change removed from each update.

The difference between the as-built and adjusted completion dates is the time attributable to that change. Before a change is made, a single revised as-planned schedule that includes the change shows its predicted effect on the end date.

For railroad work: the geotechnical report is the baseline against which a differing-condition claim is judged, so write it with that use in mind. Present factual data (logs, groundwater readings, lab results) separately from interpretation. State the limits of the data between borings. Include or reference all relevant information the railroad holds, such as historical borings, earlier slide reports and drainage records, because withholding pertinent facts can itself become a constructive change. During construction, document any suspected differing condition immediately: milepost, station and offset, depth, photographs, samples, and the work affected. Report it to the railroad’s project manager in writing the same day.

Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 209–212. Summarized and paraphrased. Full reference under Supplemental Sources.

Project management · Bissonette (2016)

Assumptions Versus Risks: The Acid Test and the Assumption Register

Bissonette treats the line between a valid assumption and an unrecognized risk as central to planning. An assumption bounds the work to known constraints, or records a condition outside the team’s control that the stakeholders have agreed to. He applies a two-question “acid test” taken from the PMBOK® Guide:

  1. Could the assumption or constraint prove false?
  2. If it were false, would one or more project objectives be harmed?

If both answers are yes, the statement is a risk and must be moved to the risk register or reworded until it passes. A companion sentence form, “<assumption> may prove false, leading to <effect on objectives>,” makes the consequence explicit. His examples show the range of outcomes. One assumption is valid because a contract clause already provides an equitable adjustment if customer-furnished equipment arrives late. Another, “the team assumes no liability for scope omissions,” fails the test and should prompt more planning. He recommends an assumption register on every project, whatever its size. Its columns are number, description, “could it prove false?”, “if false, would it affect the project?” and “convert to a risk?”.

For railroad work: Geotechnical reports are full of assumptions: groundwater at the level measured during drilling, subsurface conditions between borings similar to those at the borings, no undocumented fill or buried timber trestle, drainage outfalls that remain functional, and tie and ballast renewal staying on the maintenance cycle. Run each one through the acid test before the report is sealed. Assumptions that pass belong in the limitations or design-basis section. Those that fail, such as a water level measured in a dry month at a site that seeps in spring, should be stated as a risk with a recommended response, for example a piezometer, a contingency quantity or a construction-phase observation. Including a short assumption register in the report appendix helps the railroad’s reviewers and the contractor see what the recommendations depend on. It also gives a clear basis for comparison if conditions found during construction differ.

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 5, “Assumptions Versus Risks” (unpaginated e-book; PDF pp. 62–65). Summarized and paraphrased. Full reference under Supplemental Sources.

E.15 Report Preparation Checklist

Checklist · Part IX · Appendix

Report Preparation Checklist

Pre-Drafting0 of 6
Report Drafting0 of 8
Pre-Submittal0 of 7
Post-Submittal0 of 6

ASCE (2012) describes the design professional’s quality control as a plan that evolves with the project rather than a single check at the end. A typical project-specific design QC plan provides enough experienced staff; communication with the owner on priorities and within the design team; confirmation of field conditions, codes, standards and safety conditions that affect the design; preparation, review and coordination of drawings, estimates and specifications; scheduled reviews, audits and progress reporting; and specialty advisers on construction and maintenance who are not on the day-to-day team.

The QC focus changes by phase. In pre-design the parties agree on the QC plan. In schematic design the designer studies alternatives and the owner accepts a schematic design report. In design development alternatives and costs are refined, stakeholders such as regulators comment, and once the design development report is approved the design is “frozen.” In the contract documents phase QC includes detailed checking of computations, drawings and quantity take-offs, review of pay items and specifications, and constructability review. During bidding, the designer must correct ambiguities and errors that bidders identify before bids are due.

The Manual distinguishes the routine checking every design team does (dimensions, notes, cross-references, drawing–specification conflicts) from design reviews and audits. A design review is internal QC by team members and an experienced review board. A design audit is done by people outside the design team: an independent technical review if by others in the same firm, or an external peer review if by an unaffiliated organization. External peer review is recommended for complex, controversial, or high-risk projects. The Manual notes that owners and designers usually hold at least a final review at about 90% design completion.

For railroad work: Build the report checklist around these milestones: confirm the investigation scope against the project phase, check calculations independently (boring-depth, bearing, settlement, slope stability) before recommendations are written, reconcile the report’s quantities and pay items with the GSP and plan sheets, and hold a 90% review with the railroad’s engineering staff before sealing. Record who checked what and when, so the QC trail is part of the project file.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 193–196. Summarized and paraphrased. Full reference under Supplemental Sources.

Ticks are saved in this browser.
Plain text version

Pre-Drafting

  • [ ] All boring logs reviewed and approved by responsible PE
  • [ ] All laboratory test data quality-checked (chains of custody verified, QC split results acceptable)
  • [ ] All calculations reviewed internally; no unresolved discrepancies between data and analysis
  • [ ] Client naming convention and file format confirmed
  • [ ] PE sealed by appropriate state-licensed Professional Engineer
  • [ ] Peer review performed (Amtrak NEC: independent PE; other clients: internal senior review)

Report Drafting

  • [ ] Executive summary written using PREP method (after all analysis complete)
  • [ ] All referenced figures generated (location map, boring plan, geologic profiles)
  • [ ] Boring log header fields complete (all 9 required items)
  • [ ] Laboratory data master table complete (all samples; no blank cells without explanation)
  • [ ] All recommendations in Section 8 include governing parameter, source section, and caveat
  • [ ] Limitations clause included verbatim (or per client template)
  • [ ] GSP draft attached as Appendix D
  • [ ] Calculation appendix organized per Section E.8; each subsection has header block

Pre-Submittal

  • [ ] All figures numbered and titled; all tables numbered and titled
  • [ ] Table of contents accurate and paginated
  • [ ] All cross-references verified (e.g., "see Figure 3" exists and is correct)
  • [ ] File naming per Section E.10.2 convention; revision number and date correct
  • [ ] PDF/A format verified (not PDF 1.7 or earlier for CSXT, NSR, UPRR, BNSF)
  • [ ] PE seal applied to all required pages (cover page, boring logs, calculations)
  • [ ] Transmittal form prepared per client protocol (ProjectWise, BIM 360, or email)

Post-Submittal

  • [ ] Transmittal receipt confirmed from client
  • [ ] Review period calendared (see Table E-1 for turnaround times by client)
  • [ ] Comment-Response Matrix template prepared; ready to receive comments
  • [ ] All comments addressed in writing; no comments silently ignored
  • [ ] Final revision re-submitted with Comment-Response Matrix attached
  • [ ] "Issued for Construction" (Rev03 or final) confirmed with client PE before construction
Project management · ASCE (2012)

Design-Phase QC: Reviews, Audits and Phase Milestones

ASCE (2012) describes the design professional’s quality control as a plan that evolves with the project rather than a single check at the end. A typical project-specific design QC plan provides enough experienced staff; communication with the owner on priorities and within the design team; confirmation of field conditions, codes, standards and safety conditions that affect the design; preparation, review and coordination of drawings, estimates and specifications; scheduled reviews, audits and progress reporting; and specialty advisers on construction and maintenance who are not on the day-to-day team.

The QC focus changes by phase. In pre-design the parties agree on the QC plan. In schematic design the designer studies alternatives and the owner accepts a schematic design report. In design development alternatives and costs are refined, stakeholders such as regulators comment, and once the design development report is approved the design is “frozen.” In the contract documents phase QC includes detailed checking of computations, drawings and quantity take-offs, review of pay items and specifications, and constructability review. During bidding, the designer must correct ambiguities and errors that bidders identify before bids are due.

The Manual distinguishes the routine checking every design team does (dimensions, notes, cross-references, drawing–specification conflicts) from design reviews and audits. A design review is internal QC by team members and an experienced review board. A design audit is done by people outside the design team: an independent technical review if by others in the same firm, or an external peer review if by an unaffiliated organization. External peer review is recommended for complex, controversial, or high-risk projects. The Manual notes that owners and designers usually hold at least a final review at about 90% design completion.

For railroad work: Build the report checklist around these milestones: confirm the investigation scope against the project phase, check calculations independently (boring-depth, bearing, settlement, slope stability) before recommendations are written, reconcile the report’s quantities and pay items with the GSP and plan sheets, and hold a 90% review with the railroad’s engineering staff before sealing. Record who checked what and when, so the QC trail is part of the project file.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 193–196. Summarized and paraphrased. Full reference under Supplemental Sources.

E.16 Cross-Reference Table
TopicSee Also
Investigation planning (boring scope)Chapter 5
Boring and sampling (log details)Chapter 6
In situ test results presentationChapter 7
Soil and rock classification (USCS, RMR)Chapter 8
Groundwater data reportingChapter 9
Bearing capacity calculationsChapter 11
Settlement calculationsChapter 12
Slope stability outputChapter 13
Seismic/liquefaction calculationsChapter 14
GSP template languageAppendix C
Borehole log template (blank form)Appendix A
Lab test data table templateAppendix B
Final report delivery checklistAppendix E
E.17 Practice Questions

Q1. An NSR project requires a GDR/FGR for a 60-ft bridge abutment replacement. The PE on the project is licensed in Virginia and North Carolina; the project is located in Tennessee. What action is required before the report can be sealed and submitted to NSR?

Answer: The PE must obtain a Tennessee Professional Engineering license (or Tennessee comity registration) before sealing a geotechnical report for a project located in Tennessee. Alternatively, a co-sealing arrangement with a Tennessee-licensed PE may be used if state board rules permit. NSR Engineering Standards require PE seal in the project state. This must be resolved before the report reaches its final review stage — not during the submittal process.

Q2. A consolidation test dataset from a BNSF project shows C_c values of 0.18, 0.22, 0.31, and 0.28 for four samples from the same stratum. (a) What is the mean C_c? (b) For design, should the mean or the upper-bound value be used? (c) How should the choice be justified in the report?

Answer:

  • (a) Mean C_c = (0.18 + 0.22 + 0.31 + 0.28) / 4 = 0.248
  • (b) For settlement calculations, use a conservatively high (upper-bound) value to avoid underestimating settlement. BNSF Engineering Instructions recommend using the mean of the upper two values = (0.31 + 0.28)/2 = 0.295 as the representative design value.
  • (c) Justify in Section 6 (engineering properties table footnote) and in the calculation header: "C_c = 0.295 selected as mean of upper two consolidation test results, reflecting conservatism appropriate for primary settlement prediction where underestimation of settlement would compromise FRA track geometry tolerances (49 CFR Part 213, Class 4)."

Q3. A UPRR project is submitted as Report Rev01. The UPRR reviewer returns seven comments. Comment No. 3 states: "Increase FS_bearing from 2.5 to 3.0 for all spread footing designs." The consultant's PE believes FS = 2.5 is appropriate per AREMA Chapter 8 and the project-specific soil conditions. What is the correct response?

Answer: Do not silently ignore the comment or automatically comply without documenting the technical basis. The correct response is: (1) Write a Comment-Response Matrix entry for Comment No. 3; (2) Acknowledge UPRR's position; (3) Provide the technical rationale for FS = 2.5 (citing AREMA MRE Ch. 8, specific soil conditions, and available test data); (4) Propose a path to resolution — either the consultant revises to FS = 3.0 per client direction, or escalates to the UPRR chief engineer for a technical determination. The Comment-Response Matrix must record the disagreement, the consultant's justification, and the final resolution direction. "Not revised — see explanation" is a valid response category.

Q4. A CSXT geotechnical report for a bridge approach embankment must include GSP for staged construction. List the six required elements of a GSP section (per Section E.7.1) and give an example content item for each element.

Answer:

  1. Scope: "This section covers the construction of the proposed 15-ft embankment fill at Station 220+00 to 224+50 using staged loading with PVDs."
  2. Materials: "Embankment fill shall be select borrow material meeting ASTM D2487 classification of SM, SC, ML, or CL with LL < 40 and PI < 20; no organic material."
  3. Equipment: "Compaction shall be performed with a 25-ton vibratory smooth-drum roller; no compaction equipment within 5 ft of installed PVD mandrel holes."
  4. Construction Methods: "Fill shall be placed in maximum 18-in. loose lifts. Fill rate shall not exceed 0.5 ft/day until piezometer r_u < 0.40."
  5. Testing and Acceptance: "Compaction: nuclear gauge per ASTM D6938 at 1 test per 500 ft of track per lift; minimum RC 92% Modified Proctor. Piezometers read twice daily during fill placement."
  6. Measurement and Payment: "Embankment fill: measured in cubic yards (cy) of compacted material in place; paid per cubic yard at contract unit price."

Q5. A BNSF geotechnical report is at Rev02 ("Issued for Client Review — 2nd Submittal"). The construction contract is awarded and the contractor begins mobilizing. The geotechnical engineer discovers that the consolidation test data from one boring was erroneously transposed (lab data was entered in the wrong row in the table), which changes the estimated settlement from 3.2 in. to 6.8 in. — above the FRA Class 4 tolerance. What must the consultant do?

Answer: Issue an immediate written notice (email + formal letter) to the BNSF project engineer and the project PE of Record, describing the error, the corrected analysis results, and the changed conclusion. Do not wait for the formal report revision cycle. Issue a Rev03 report correcting the error, with a clear revision history notation explaining the correction. The recommendations section must be updated — staged construction or ground improvement may now be required. Notify the structural engineer of record and the contractor if the change affects foundation design or construction sequence. This situation constitutes a changed condition that triggers the notification obligation in the Limitations clause. BNSF Engineering Instructions require all errata affecting design recommendations to be resubmitted within 5 business days of discovery.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

  • USACE EM 1110-1-1804, Geotechnical Investigations (2001)
  • FHWA (2017). What is a Geotechnical Report?
  • AREMA MRE Chapters 1 and 8
  • ASTM D2487, D2488, D1557, D6938
  • Vesić (1975)
  • Client railroad engineering standards as cited in the text (CSXT, NSR, UPRR, BNSF, CPKC, CN, Amtrak, G&W)

Supplemental sources (LEVI Library)

  • Federal Highway Administration (2017). What is a Geotechnical Report? Geotechnical Engineering fact page
  • Amec Foster Wheeler (2018). Preliminary Site Assessment of Slope Instability at CSXT MP BNA-56.0, Shortline Subdivision, near Clarksburg, WV (draft letter report, April 6, 2018)
  • CSX Transportation (2016). Standard Specifications for Private Sidetracks (Industrial Sidetrack Manual), September 15, 2016
  • CSX Transportation (2020). Public Projects Manual, December 2020, incl. Soil and Water Management Policy
  • Rao, V. V. S. (2016). “Guidelines for Forensic Investigation of Geotechnical Failures,” and Jessep, R. A., de Mello, L. G. and Rao, V. V. S. (2016). “Technical Shortcomings Causing Geotechnical Failures: Report of Task Force 10, TC 302.” In Rao and Sivakumar Babu (eds.), Forensic Geotechnical Engineering. Springer India

File locations for these documents are listed under Supplemental Sources — LEVI Library.

Project management sources

  • Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill
  • Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann
  • Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold
  • Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing
  • ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers
  • Spain, B. (1995). Taking Off Quantities: Civil Engineering. London: E & FN Spon
  • Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill
  • Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc.
  • Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute
  • American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE
Supplemental Sources — LEVI Library

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S7 for railroad clients; tables are condensed from the book and its figures are not reproduced. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Federal Highway Administration (2017). What is a Geotechnical Report? Geotechnical Engineering fact page
  2. Amec Foster Wheeler (2018). Preliminary Site Assessment of Slope Instability at CSXT MP BNA-56.0, Shortline Subdivision, near Clarksburg, WV (draft letter report, April 6, 2018)
  3. CSX Transportation (2016). Standard Specifications for Private Sidetracks (Industrial Sidetrack Manual), September 15, 2016
  4. CSX Transportation (2020). Public Projects Manual, December 2020, incl. Soil and Water Management Policy
  5. Rao, V. V. S. (2016). “Guidelines for Forensic Investigation of Geotechnical Failures,” and Jessep, R. A., de Mello, L. G. and Rao, V. V. S. (2016). “Technical Shortcomings Causing Geotechnical Failures: Report of Task Force 10, TC 302.” In Rao and Sivakumar Babu (eds.), Forensic Geotechnical Engineering. Springer India
  6. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)
  7. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 12, 14 and 16
  8. Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill. Used on this page for project-management material
  9. Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann. Used on this page for project-management material
  10. Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold. Used on this page for project-management material
  11. Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing. Used on this page for project-management material
  12. ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers. Used on this page for project-management material
  13. Spain, B. (1995). Taking Off Quantities: Civil Engineering. London: E & FN Spon. Used on this page for project-management material
  14. Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill. Used on this page for project-management material
  15. Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc.. Used on this page for project-management material
  16. Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute. Used on this page for project-management material
  17. American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE. Used on this page for project-management material